HRERA GurugramTemp Project Id : RERA-GRG-PROJ-2133-2025
Submission Date : 11-12-2025 02:55:34 PM
Applicant Type : Company
Project Type: NEW




TARC LIMITED
2ND FLOOR, C-3, QUTAB INSTITUTIONAL AREA ROAD, BLOCK C, KATWARIA SARAI, NEW DELHI, DELHI 110016
1141244344
9810585435 (Number Shared by Promoter in Public)
ajay.pathania@tarc.in
https://www.tarc.in
XXXX650B
L70100DL2016PLC390526
 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 







TARC ISHVA
SECTOR 63A GURUGRAM
GURGAON
GURUGRAM
1141244344
9810585435 (Number Shared by Promoter in Public)
tarc@tarc.in
RATNADEEP PAUL
1141244344
9958112270 (Number Shared by Promoter in Public)
ratnadeep.paul@tarc.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques/Online Banking:-

Drafts/ Banker’s Cheques

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
158901706-07-20241775000KOTAK MAHINDRA BANKHRERA Gurugram
258901606-07-2024887000KOTAK MAHINDRA BANKHRERA Gurugram
358902719-08-2024886500KOTAK MAHINDRA BANKHRERA Gurugram
458903127-08-202427000KOTAK MAHINDRA BANKHRERA Gurugram
583757310-12-20251000000KOTAK MAHINDRA BANKHRERA Gurugram
683756830-12-20251130740KOTAK MAHINDRA BANKHRERA Gurugram
7176708225130-12-20257953ONLINE PAYMENTHRERA Gurugram

Online Banking








9.1405 (Acre)
3.15
3.1415
9.1405 (Acre)
137 of 2023 Dated 05.07.2023 15 of 2025 Dated 29.01.2025 99 of 2025 Dated 13.06.2025 100 of 2025 Dated 17.06.2025
No
Address     2ND FLOOR, C-3, QUTAB INSTITUTIONAL AREA ROAD, BLOCKC, KATWARIA NEW DELHI-110016 SARAI,
Address     EMERALD HILLS IVORY 132, SEC-65 GURUGRAM- 122001
Annexure-B- ANNEXURE-B
BEFORE
Yes
ATTACHED
No
Yes
Yes







245377.75 Lakhs
75209.00 Lakhs
90919.15 Lakhs
11150.36 Lakhs
68099.24 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 1.0083
3CONSTRUCTION OF ROADS 3.4485
4PAVEMENTS 1.9131
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0.2244
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 2.2552
13SECURITY 0.0084
14PARKING 0.0627
15UNDERGROUND 0.0886
16STP 0.1313
Total9.1405




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSALREADY CONNECTEDYes
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS2696.80AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM932.41AS PER PROJECT REPORT
3STORM WATER DRAINAGE339.49AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM3278.58AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL302.26AS PER PROJECT REPORT
6STREET LIGHTING75.55AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING158.36AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS1221.94AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM79.95AS PER PROJECT REPORT
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15PARKING948.68AS PER PROJECT REPORT
16UNDERGROUND WATER TANK104.98AS PER PROJECT REPORT
17RAIN WATER HARVESTING59.19AS PER PROJECT REPORT
18STP172.20AS PER PROJECT REPORT
19ELECTRICAL SUB STATION779.97AS PER PROJECT REPORT
20SHOPPING AREA243.56AS PER PROJECT REPORT


NA (date)
11-12-2025 (date)
01-09-2024
31-12-2031
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings150.50033
Apartment/Shops/Other Buildings151.52033
Apartment/Shops/Other Buildings153.9801273
Apartment/Shops/Other Buildings155.120673
Apartment/Shops/Other Buildings155.120603
Apartment/Shops/Other Buildings203.10933
Apartment/Shops/Other Buildings204.82033
Apartment/Shops/Other Buildings206.970243
Apartment/Shops/Other Buildings206.9701113
Apartment/Shops/Other Buildings208.5691113
Apartment/Shops/Other Buildings346.50933
Apartment/Shops/Other Buildings348.18933
Apartment/Shops/Other Buildings20.225951
Apartment/Shops/Other Buildings175.5511





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2117.80
Shops4.4145
Plots0
Nursery School4.1805
Community Building39.696

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2117.802117.803231.541440.18
Shops4.41454.41454.41455.886
Plots0000
Nursery School4.18054.18054.18055.574
Community Building39.69639.69639.69652.928

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2761.392434.952642.412642.41
Shops10.1784.2928.5848.584
Plots0000
Nursery School9.3743.87.67.6
Community Building89.014536.086572.17372.173

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2642.412642.416382.836382.83
Shops8.5848.58415.08315.083
Plots0000
Community Building72.17372.173143.1435143.1435
Nursery School7.67.615.07315.073

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments6382.834155.344554.534139.61
Shops15.08315.08321.58212.998
Plots0000
Nursery School15.07315.07322.54614.946
Community Building143.1435143.1435214.114141.941

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments4139.614139.612468.992468.99
Shops12.99812.99812.99812.998
Plots0000
Community Building141.941141.941141.941141.941
Nursery School14.94614.94614.94614.946

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2468.992468.99
Shops12.99812.998
Plots00
Community Building141.941141.941
Nursery School14.94614.946




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements134.84134.84134.84134.84
Water Supply System00046.62
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
STP8.618.618.61
Underground water tank5.255.255.25

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements134.84134.84134.84134.84
Water Supply System46.6246.6246.6293.24
Sewerage treatment & garbage disposal15.1115.1115.1115.11
Electricity Supply System163.93163.93163.93163.93
Storm Water Drainage16.9716.9733.9533.95
Parks and Playgrounds61.1061.1061.1061.10
Clubhouse/community centres0000
Shopping area0000
Other0000
Rain water harvesting2.962.962.962.96
STP8.618.618.618.61
Parking47.4347.4347.4347.43
Underground water tank5.255.255.255.25
Renewable energy system4.004.004.004.00
Security and fire fighting7.927.927.927.92
Street Lighting3.783.783.783.78

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements134.84134.84269.68269.68
Water Supply System93.2493.2493.2493.24
Sewerage treatment & garbage disposal30.2330.2330.2330.23
Electricity Supply System327.86327.86327.86327.86
Storm Water Drainage33.9533.9533.9533.95
Parks and Playgrounds122.19122.19122.19122.19
Clubhouse/community centres0000
Shopping area0000
Other0000
Underground water tank5.255.255.2510.50
Rain water harvesting5.925.925.925.92
Street Lighting7.567.567.567.56
Electrical sub station39.0078.0078.00
STP8.618.618.6117.22
Security and fire fighting15.8415.8415.8415.84
Renewable energy system8.008.008.008.00
Parking94.8794.8794.8794.87

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements269.68269.68269.680
Water Supply System93.2493.2493.240
Sewerage treatment & garbage disposal30.2330.2330.2330.23
Electricity Supply System327.86327.86327.86327.86
Storm Water Drainage33.9533.9533.950
Parks and Playgrounds122.19122.19122.19122.19
Clubhouse/community centres0000
Shopping area0000
Other0000
STP17.2217.2217.2217.22
Street Lighting7.567.567.567.56
Security and fire fighting15.8415.8415.8415.84
Renewable energy system8.008.008.008.00
Parking94.8794.8794.8794.87
Underground water tank10.5010.5010.5010.50
Rain water harvesting5.925.925.925.92
Electrical sub station78.0078.0078.00117.00

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00
Water Supply System00
Sewerage treatment & garbage disposal00
Electricity Supply System00
Storm Water Drainage00
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other00
Electrical sub station117.00117.00








Cash Flow in each quarter (In Lakhs)












Yes
Yes
Account Details
KOTAK MAHINDRA BANK ADDRESS AMBADEEP BUILDING, KG MARG, NEW DELHI
8947709925
KKBK0000172
110485003
000172
RAJEEV TREHAN ADDRESS: C-3, Qutab Institutional Area Road, Block C, Katwaria Sarai, New Delhi
YES











No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. BUILDING PLAN (BR-III)ALREADY BEEN OBTAINED26-12-2025
II. FOREST NOCALREADY BEEN OBTAINED06-06-2025
III. HUDA CONSTRUCTIONALREADY BEEN OBTAINED21-08-2025
IV. ASSURANCE FOR STORM WATER ALREADY BEEN OBTAINED22-08-2025
V. ASSURANCE FOR WATER SUPPLYALREADY BEEN OBTAINED22-08-2025
VI. ASSURANCR OF SEWERAGE CONNECTIONALREADY BEEN OBTAINED21-08-2025
VII. ENVIRONMENT CLEARANCE APPROVALALREADY BEEN OBTAINED26-12-2025
VIII. AAIALREADY BEEN OBTAINED17-02-2025
IX. SERVICE ESTIMATES AND PLAN ALREADY BEEN OBTAINED31-12-2025
X. FIRE SCHEME APPROVALAPPLIED FOR BUT YET TO RECEIVE05-12-2025








Yes


Yes


As per Norms













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSETILE/WOODEN FLOORING/MARBLE
2WALL FINISHING DETAILSACRYLIC EMULSION PAINT
3KITCHEN DETAILSSINGLE LEVER COUNTER TOP
4BATHROOM FITTINGSCHINAWARE , SINGLE LEVER COUNTER TOP
5WOOD WORK ETCNO
6DOORS AND WINDOS FRAMESWINDOWS - ALUMINIUM POWDER-COATED SECTIONS AND FLUSH DOOR
7GLASS WORKWINDOWS- ALUMINIUM POWDER-COATED SECTIONS
8ELECTRIC FITTINGSFAN AND ELECTRIC POINT
9CONDUCTING AND WIRING DETAILSHEAVY DUTY , MODULAR
10CUPBOARD DETAILSNA
11WATER STORAGEYES
12LIFT DETAILS2 PASSENGER LIFTS SERVING EVERY APARTMENT
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSWINDOWS- ALUMINIUM POWDER COATED SECTIONS
14DOORSFLUSH DOOR
14.1MAIN DOORSFLUSH DOOR
14.2INTERNAL DOORSFLUSH DOOR
15AIR CONDITIONINGVARIABLE RATE FLOW SYSTEM
16ELECTRICAL FITTINGSHEAVY DUTY CONDUTING MODULAR SWITCHES, C CURVE MCB
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERNAL GRADE TEXTURE PAINT
20INTERNAL FINISHINGACRYLIC EMULSION PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORMARBLE
1 . 2 WALLSACRYLIC EMULSION PAINT
1 . 3 CEILINGPOP CEILING
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORWOODEN
2 . 2 WALLSACRYLIC EMULSION PAINT
2 . 3 CEILINGPOP CEILING
2 . 4 MODULAR WARDROBESNO
3 . MASTER TOILET
3 . 1 FLOORMARBLE
3 . 2 WALLSMARBLE
3 . 3 CEILINGFALSE CEILING
3 . 4 COUNTERSVANITY COUNTER
3 . 5 SANITARY WARE/CP FITTINGSSINGLE LEVER COUNTER TOP
3 . 6 FITTING/FIXTURESSINGLE LEVER COUNTER TOP
4 . BED ROOMS
4 . 1 FLOORWOODEN FLOORING
4 . 2 WALLSACRYLIC EMULSION PAINT
4 . 3 CEILINGPOP CEILING
4 . 4 WARDROBESNO
5 . TOILET
5 . 1 FLOORTILE
5 . 2 WALLSTILE
5 . 3 CEILINGFALSE CEILING
5 . 4 COUNTERSVANITY COUNTER
5 . 5 SANITARY WARE/CP FITTINGSCP FITTING & CERAMIC FIXTURES
5 . 6 FIXTURESSINGLE LEVER COUNTER TOP
6 . KITCHEN
6 . 1 FLOORMARBLE
6 . 2 WALLSACRYLIC EMULSION PAINT
6 . 3 CEILINGPOP CEILING
6 . 4 COUNTERSMARBLE/KOREAN
6 . 5 FIXTURESCP FITTING & FIXTURES
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORTILE
7 . 2 WALLS & CEILINGOBD PAINT
7 . 3 TOILETTILE
7 . 4 BALCONYTILE
8 . SIT-OUTS
8 . 1 FLOORTILE
8 . 2 WALLS & CEILINGOBD PAINT
8 . 3 RAILINGSMETAL
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 FIRE SCHEME 09-12-2025 View Document
2 LC-IV 09-12-2025 View Document
3 N SCHOOL -1 FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
4 FOREST NOC 09-12-2025 View Document
5 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 09-12-2025 View Document
6 COMMUNITY FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
7 EWS PLANS AND AREA CALCULATION 09-12-2025 View Document
8 PAYMENT PLAN 09-12-2025 View Document
9 ASSURANCE OF SEWERAGE CONNECTION 09-12-2025 View Document
10 DEMARCATION PLAN 09-12-2025 View Document
11 ZONING PLAN 09-12-2025 View Document
12 COMMUNITY FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
13 EWS - ELEVATION AND SECTION 09-12-2025 View Document
14 BASEMENT -02 PLANS AND AREA CALCULATION 09-12-2025 View Document
15 ASSURANCE FOR WATER SUPPLY 09-12-2025 View Document
16 BASEMENT -01 PLANS AND AREA CALCULATIONS 09-12-2025 View Document
17 SALE DEED 09-12-2025 View Document
18 EWS PLANS AND AREA CALCULATION 09-12-2025 View Document
19 ASSURANCE FOR STORM WATER 09-12-2025 View Document
20 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 09-12-2025 View Document
21 BANK UNDERTAKING 09-12-2025 View Document
22 AAI NOC 09-12-2025 View Document
23 ELEVATIONS AND SECTION -AA 09-12-2025 View Document
24 SITE PLAN FOR SERVICES AND GREEN AREA CALCULATION 09-12-2025 View Document
25 TOWER - 2 ELEVATION 1,2,3 09-12-2025 View Document
26 TOWER - 3 & 4 TYPICAL FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
27 TOWER - 1 - ELEVATION 09-12-2025 View Document
28 TOWER - 1- 1ST FLOOR PLAN & AREA CALCULATION 09-12-2025 View Document
29 TOWER - 1 GROUND FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
30 TOWER - 1 REFUGE FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
31 TOWER - 1 SECTION AND ELEVATION 09-12-2025 View Document
32 TOWER - 1 TERRACE AND OTH FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
33 TOWER - 1- TYPICAL -2 FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
34 TOWER - 1 -TYPICAL FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
35 TOWER - 2 REFUGE FLOOR PLAND AND AREA CALCULATION 09-12-2025 View Document
36 TOWER - 2 TERRACE AND OTH PLAN AND AREA CALCULATION 09-12-2025 View Document
37 TOWER - 2 TYPICAL -2 FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
38 TOWER - 3 & 4 FIRST FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
39 TOWER - 3 AND 4 ELEVATION - 1,2,3 09-12-2025 View Document
40 TOWER - 3 AND 4 SECTIONS AND ELEVATION 09-12-2025 View Document
41 TOWER - 5 - ELEVATION - 1,2,3 09-12-2025 View Document
42 TOWER - 5 - SECTIONS AND ELEVATION 09-12-2025 View Document
43 TOWER - 5 FIRST FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
44 TOWER - 5 LOWER PENTHOUSE FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
45 TOWER - 5 REFUGE FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
46 TOWER - 5 SERVICE FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
47 TOWER - 5- TERRACE FLOOR LMR & OHT PLAN AND AREA CALCULATION 09-12-2025 View Document
48 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 10-12-2025 View Document
49 TOWER - 5 TYPICAL FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
50 TOWER - 6 1ST AND REFUGE FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
51 TOWER - 6 ELEVATION - 1,2,3 09-12-2025 View Document
52 TOWER - 6 TYPICAL - 2 FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
53 TOWER-6 SECTIONS AND ELEVATION 09-12-2025 View Document
54 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 10-12-2025 View Document
55 TOWER - 6 GROUND FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
56 TOWER - 6 TERRACE AND OTH FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
57 TOWER - 6 TYPICAL FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
58 TOWER 2 1ST AND REFUGE FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
59 TOWER- 2 GROUND FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
60 TOWER- 2 SECTIONS AND ELEVATION 09-12-2025 View Document
61 TOWER- 2 TYPICAL FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
62 TOWER -3 & 4 LOWER PENTHOUSE FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
63 TOWER -3 & 4 REFUGE FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
64 TOWER -3 & 4 SERVICE FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
65 MUTATION 06-01-2026 View Document
66 TOWER- 3 & 4 TERRACE FLOOR LMR & OTH PLAN AND AREA CALCULATION 09-12-2025 View Document
67 TOWER- 3 & 4 UPPER PENTHOUSE FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
68 TOWER- 3 &4 GROUND FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
69 TOWER -5 GROUND FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
70 TOWER -5 UPPER PENTHOUSE FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
71 TOWER- 6 REFUGE FLOOR PLAN AND AREA CALCULATION 09-12-2025 View Document
72 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 10-12-2025 View Document
73 AFFIDAVIT 4(2)(L)(D) 11-12-2025 View Document
74 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 11-12-2025 View Document
75 NCZ AFFIDAVIT 11-12-2025 View Document
76 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 11-12-2025 View Document
77 SERVICE PLANS AND ESTIMATES 06-01-2026 View Document
78 SIZRA 06-01-2026 View Document
79 ASSURANCE CERTIFICATE OF DHBVN 06-01-2026 View Document
80 NON ENCUMBRANCE 06-01-2026 View Document
81 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 06-01-2026 View Document
82 JAMABANDI 06-01-2026 View Document
83 EC 06-01-2026 View Document
84 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 06-01-2026 View Document
85 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 06-01-2026 View Document
86 INFO TO REVENUE DEPT 06-01-2026 View Document