HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1144-2022
Submission Date : 15-09-2022 06:11:28 PM
Applicant Type : Company
Project Type: NEW




DLF HOME DEVELOPERS LIMITED
1ST FLOOR, GATEWAY TOWER, R BLOCK, DLF CITY PHASE III, GURUGRAM
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
https://www.dlf.in
XXXX037H
U74899HR1995PLC082458
 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 







ALAMEDA CENTRAL
SECTOR 73, GURUGRAM
GURGAON
GURUGRAM
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
SUNIL ARORA
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
152116009-09-2022723883ICICI BANKHRERA Gurugram







2.98125 (Acre)
1.5
1.5
2.98125 (Acre)
139 of 2022
Yes







7125 Lakhs
2702 Lakhs
0 Lakhs
1192 Lakhs
3231 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD1.04
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS1.01
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0.45
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0.04
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.04
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
13OPEN0.40
Total2.98




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDANo
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS179.33AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM62.06AS PER PROJECT REPORT
3STORM WATER DRAINAGE60.31AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM217.85AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL63.08AS PER PROJECT REPORT
6STREET LIGHTING26.06AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS298.88AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT
15EARTH WORKS62.68AS PER PROJECT REPORT
16SEWERAGE SYSTEM119.55AS PER PROJECT REPORT
17UGT56.77AS PER PROJECT REPORT
18RAINWATER HARVESTING45.42AS PER PROJECT REPORT


13-09-2022 (date)
13-09-2022 (date)
01-04-2023
08-09-2027
Plot Area(In Square Meter)Number of plots in the project
136.1515
88.2010
86.4415


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System012.4115.51
Sewerage treatment & garbage disposal023.9129.81
Electricity Supply System000
Storm Water Drainage012.0615.08
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000
Earth works31.3431.34
rain water Harvesting11.35

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System15.5118.6200
Sewerage treatment & garbage disposal29.8935.8715.7715.77
Electricity Supply System054.4654.460
Storm Water Drainage15.0818.0900
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Rainwater Harvesting11.3513.63
Internal roads and Pavements44.83
UGT14.1914.19
Internal road and pavements44.83
Elect Supply System54.46
Street Lighting13.03
Parking and parks149.44

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal31.54000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
UGT28.39
Street Light13.03
Internal road and pavements89.66
Elect supply System54.46
Parking and parks149.44












Yes
No
ICICI BANK LIMITED 9A, CONNAUGHT PLACE NEW DELHI - 110 001
000705053446
ICIC0000007
110229002
0007
1. Mr. Vivek Anand (E1001, Palm Springs, Golf Course Road, opposite IBIS Hotel, Sector 54, Gurgaon, Haryana 122002) 2. Mr. Puneet Rakheja (H.No. 386, Sector 31, Faridabad, Haryana 121003) 3. Mr. Pankaj Kumar Jain (C701, Apex Acacia Valley, Sector 3, Ghaziabad, Uttar Pradesh 201010) 4. Mr. Saurabh Kumar Gupta (1116, Vikas Kunj, Vikaspuri, Delhi 110018) 5. Mr. Gaurav Arora (A-33, Near Mehfil Banquet Hall Mahendru Enclave, GT Karnal Road, Delhi 110009) 6. Ms. Sandhya Singla (Neelanchal Apartments, Plot No. 3, Sector 4, Dwarka, Delhi 110075) 7. Mr. Ashok Nanda (A255, Surya Nagar, Chander Nagar, Ghaziabad. Uttar Pradesh 201011) 8. Mr. Rajeev Singhal (Flat No. 14, Tower No. 4, Raj Nagar Extension, Signature Homes, Ghaziabad, Uttar Pradesh 201001) 9. Mr. Sujeet Kumar Sinha (C-061, DLF New Town Heights, IMT Manesar, Sector 91, Gurgaon, Haryana 122505) 10. Mr. Pankaj Kumar (A3, Rajcottage 1/18, Rajendra Nagar, Ghaziabad, Uttar Pradesh 201005)
No Default Certificate Annexed











Yes
Yes
No
No
Yes
No
No
No
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSEALREADY BEEN OBTAINED09-09-2022
II. LAYOUTALREADY BEEN OBTAINED13-09-2022








Yes


Yes


As Per RERA Act







GARDENCITY CENTRAL
8.0396
0
122
0
89
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
9948114887867
Cost of the apartments000
Cost of the infrastructure16083380486
Others costs72027811438


8077 Lakhs
16069 Lakhs
0 Lakhs
126 Lakhs
No
24-08-2024
24-08-2024




INDEPENDENT FLOORS AT DLF ALAMEDA
2.78
116
0
106
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
17660188336579
Cost of the apartments15506140182512
Cost of the infrastructure000
Others costs539861654586


10223 Lakhs
30971 Lakhs
0 Lakhs
5941 Lakhs
No
24-11-2024
24-11-2024




INDEPENDENT FLOORS AT DLF CITY PHASE I & II
0.9726
52
0
1
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
76477647671
Cost of the apartments61836183318
Cost of the infrastructure000
Others costs20142014480


10 Lakhs
415 Lakhs
0 Lakhs
0 Lakhs
No
15-12-2024
15-12-2024




INDEPENDENT FLOORS AT DLF CITY PHASE IV
0.8314
44
0
33
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
913291321182
Cost of the apartments53195319756
Cost of the infrastructure000
Others costs55965596975


2367 Lakhs
12473 Lakhs
0 Lakhs
1200 Lakhs
No
14-11-2024
14-11-2024




INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92
0.9650
64
0
64
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
735152192645
Cost of the apartments4321453532085
Cost of the infrastructure000
Others costs303033371599


1982 Lakhs
6843 Lakhs
0 Lakhs
1133 Lakhs
No
16-06-2025
16-06-2025




MOULSARI ENCLAVE
1.035
40
0
40
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
577657762684
Cost of the apartments473447341908
Cost of the infrastructure000
Others costs693069303946


3116 Lakhs
11430 Lakhs
0 Lakhs
2258 Lakhs
No
31-10-2024
31-10-2024










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN14-09-2022 View Document
2IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN14-09-2022 View Document
3CASH FLOW STATEMENT OF THE PROPOSED PROJECT14-09-2022 View Document
4CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT14-09-2022 View Document
5NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT14-09-2022 View Document
6DEMARCATION PLAN14-09-2022 View Document
7LC-IV BILATERAL AGREEMENT SECTOR 73 (2.98 ACS)01-10-2022 ------
8COPY OF LICENSE ALONG WITH SCHEDULE OF LAND01-10-2022 View Document
9LOI-COMM-PLOTTED-2.98125 ACS-SECTOR 7301-10-2022 ------
10DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD01-10-2022 View Document
11JAMABANDI01-10-2022 ------
12AKS 01-10-2022 ------
13SEARCH REPORT01-10-2022 ------
14NON ENCUMBRANCE01-10-2022 ------
15SPE SUBMISSION RECEIPT01-10-2022 ------
16SPE PLANS01-10-2022 ------
17MUTATION01-10-2022 ------
18SPE - SERVICE ESTIMATE DOCUMENT-19.9.2203-10-2022 ------
19STORM WATER LAYOUT PLAN22-11-2022 ------
20ASSURANCE OF WATER SUPPLY22-11-2022 ------
21SEWERAGE CONNECTION FOR DISPOSAL22-11-2022 ------
22DOMESTIC FIRE FITTING 22-11-2022 ------
23ELECTRICAL LOAD22-11-2022 ------
24ASSURANCE OF STORM WATER22-11-2022 ------
25SEWAGE LAYOUT PLAN-122-11-2022 ------
26FLUSHY AND IRRIGATIONS SUPPLY22-11-2022 ------
27ROAD LAYOUT22-11-2022 ------
28REP II07-12-2022 ------
29PERT07-12-2022 ------
30PROMOTER AFFIDAVIT07-12-2022 ------
31DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.09-12-2022 View Document