Quarterly Schedules | ||
| HRERA Panchkula | ||
| Project Registration Number : HRERA-PKL-KNL-81-2018 | ||
| Project Name : YET TO BE DECIDED | ||
| Project Number : RERA-PKL-360-2018 | ||
| Project Type : NEW | ||
| Report Online Submission Date : 09-Oct-2019 |
| S.No. | Particulars | Amount (In Lakhs) |
| 1 | Cost of the land (if included in the estimated cost) | 2904.34 |
| 2 | Estimated cost of construction of apartments | 0.00 |
| 3 | Estimated cost of infrastructure & other structure | 4339.28 |
| 4 | Other cost including EDC taxes, levies, etc | 215.99 |
| Total | 7459.61 |
| Name of the approval | Status | Date |
| Layout Plan | Obtained Approval on | 25-06-2021 |
| Demarcation Plan | Obtained Approval on | 30-05-2018 |
| Zoning Plan | Obtained Approval on | 07-09-2021 |
| Service Plans | Obtained Approval on | 24-08-2018 |
| Electricity Plans | Obtained Approval on | 15-07-2022 |
| Total Expenditure on the project | 3615.11 |
| Expenditure made upto the date of Registration | 212.56 |
| EDC due as on the date of Registration | 118.06 |
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0.00 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0.00 |
| 3 | Amount availed from the bank/financial institutions | 0.00 |
| 4 | Amount contributed by the promoters/his associates | 425.01 |
| 5 | Any other receipt | 0.00 |
| Total | 425.01 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0.00 |
| 2 | Expenditure on infrastructure & other structure | 306.96 |
| 3 | Other costs including EDC, taxes, etc | 118.06 |
| Total | 425.02 | |
| Balance | 3190.10 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.00 |
| 2 | Amount deposited in Escrow Account | 0.00 |
| 3 | Amount withdrawn during the quarter | 0.00 |
| 4 | Balance at the end of the quarter | 0.00 |
| Total Plots in the colony | 207 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0.00 |
| 2 | Apartments | 0.00 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.5 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 118.06 |
| 2 | EDC due as on date | 0.00 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 425.02 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0.35 |
| 5 | Any other receipt | 0 |
| Total | 425.37 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0.35 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 0.35 | |
| Balance | 3189.74 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.00 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 207 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | NIL | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | NIL | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | NIL | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.5 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 118.06 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 425.37 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0.18 |
| 5 | Any other receipt | 0 |
| Total | 425.55 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0.18 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 0.18 | |
| Balance | 3189.56 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 207 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.5 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 118.06 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 0 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 31.39 |
| 5 | Any other receipt | 0 |
| Total | 31.39 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 31.39 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 31.39 | |
| Balance | 3158.17 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 207 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.5 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 118.06 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3158.17 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 85.69 |
| 5 | Any other receipt | 0 |
| Total | 3243.86 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 85.69 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 85.69 | |
| Balance | 3072.48 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 207 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.5 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 118.06 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3072.48 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 3072.48 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 0 | |
| Balance | 3072.48 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 207 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.5 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 118.06 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3072.48 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 1.84 |
| 5 | Any other receipt | 0 |
| Total | 3074.32 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 1.84 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 1.84 | |
| Balance | 3070.65 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 207 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.5 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 118.06 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3070.65 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 3070.65 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 544.46 | |
| Balance | 3070.65 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 207 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.5 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 118.06 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3070.65 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 5.25 |
| 5 | Any other receipt | 0 |
| Total | 3075.90 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 5.25 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 549.71 | |
| Balance | 3065.4 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 207 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.5 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 118.06 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3075.90 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 18.09 |
| 5 | Any other receipt | 0 |
| Total | 3093.99 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 1.61 |
| 3 | Other costs including EDC, taxes, etc | 16.48 |
| Total | 567.80 | |
| Balance | 3047.31 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 207 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | A | 0 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 134.54 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 134.54 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3047.31 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 1580.99 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 2955.88 |
| 5 | Any other receipt | 0 |
| Total | 7584.18 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 2874.43 |
| 3 | Other costs including EDC, taxes, etc | 81.45 |
| Total | 3523.68 | |
| Balance | 3935.93 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 1580.99 |
| 3 | Amount withdrawn during the quarter | 1564.14 |
| 4 | Balance at the end of the quarter | 16.85 |
| Total Plots in the colony | 248 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | A | 73 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 215.99 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3935.93 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 218.31 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 31.99 |
| 5 | Any other receipt | 0 |
| Total | 4186.23 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 31.99 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 3555.67 | |
| Balance | 3903.94 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 16.85 |
| 2 | Amount deposited in Escrow Account | 218.31 |
| 3 | Amount withdrawn during the quarter | 235.16 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 248 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | A | 34 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.5 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3903.94 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 199.71 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 4103.65 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0.23 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 3555.90 | |
| Balance | 3903.71 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 199.71 |
| 3 | Amount withdrawn during the quarter | 199.71 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 248 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | A | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3903.71 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 480.70 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 4384.41 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 237.57 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 3793.47 | |
| Balance | 3666.14 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 480.70 |
| 3 | Amount withdrawn during the quarter | 480.70 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | DSS | 9 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3666.14 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 372.19 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 4038.34 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 13.13 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 3806.59 | |
| Balance | 3653.02 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 372.19 |
| 3 | Amount withdrawn during the quarter | 367.34 |
| 4 | Balance at the end of the quarter | 4.85 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | PLOT | 24 |
| 2 | DSS | 6 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | - | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | - | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3653.02 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 1147.40 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 4800.42 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 137.57 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 3944.16 | |
| Balance | 3515.45 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 4.85 |
| 2 | Amount deposited in Escrow Account | 1147.40 |
| 3 | Amount withdrawn during the quarter | 1126.25 |
| 4 | Balance at the end of the quarter | 26.01 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | PLOT | 71 |
| 2 | DSS | 2 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | - | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | - | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3515.45 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 1324.70 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 4840.15 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 233.35 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 4177.51 | |
| Balance | 3282.10 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 26.01 |
| 2 | Amount deposited in Escrow Account | 1324.70 |
| 3 | Amount withdrawn during the quarter | 1340.71 |
| 4 | Balance at the end of the quarter | 10.00 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | PLOT | 7 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | - | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | - | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3282.10 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 364.95 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 3647.04 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 153.51 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 4331.02 | |
| Balance | 3128.59 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 10.00 |
| 2 | Amount deposited in Escrow Account | 364.95 |
| 3 | Amount withdrawn during the quarter | 372.43 |
| 4 | Balance at the end of the quarter | 2.52 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | PLOT | 15 |
| 2 | DSS | 1 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3128.59 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 229.37 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 3357.96 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 24.81 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 4355.83 | |
| Balance | 3103.78 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 2.52 |
| 2 | Amount deposited in Escrow Account | 229.37 |
| 3 | Amount withdrawn during the quarter | 231.90 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | PLOT | 5 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3103.78 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 58.26 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 3162.04 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 37.91 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 4393.74 | |
| Balance | 3065.87 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 58.26 |
| 3 | Amount withdrawn during the quarter | 58.26 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | PLOT | 1 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3065.87 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 103.97 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 3169.84 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 4.44 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 4398.18 | |
| Balance | 3061.43 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 103.97 |
| 3 | Amount withdrawn during the quarter | 75.45 |
| 4 | Balance at the end of the quarter | 28.52 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | PLOT | 2 |
| Total Apartments in the colony | 0 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3061.43 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 10.28 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 3071.71 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 1.29 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 4399.47 | |
| Balance | 3060.14 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 28.52 |
| 2 | Amount deposited in Escrow Account | 10.28 |
| 3 | Amount withdrawn during the quarter | 38.80 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | PLOTS | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3060.14 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 50.97 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 3111.11 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0.10 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 4399.57 | |
| Balance | 3060.04 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 50.97 |
| 3 | Amount withdrawn during the quarter | 50.97 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | PLOT | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3060.04 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 66.85 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 3126.90 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 4.64 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 4404.21 | |
| Balance | 3055.40 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 66.85 |
| 3 | Amount withdrawn during the quarter | 66.56 |
| 4 | Balance at the end of the quarter | 0.30 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | PLOT/DSS | 1 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3055.40 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 8.91 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 3064.31 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 2.30 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 4406.50 | |
| Balance | 3053.11 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.30 |
| 2 | Amount deposited in Escrow Account | 8.91 |
| 3 | Amount withdrawn during the quarter | 9.21 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | PLOT/DSS | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3053.11 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 7.31 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 3060.42 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 15.56 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 4422.07 | |
| Balance | 3037.54 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 7.31 |
| 3 | Amount withdrawn during the quarter | 7.31 |
| 4 | Balance at the end of the quarter | 0 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | PLOT/BOOTH | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 3037.54 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 3.55 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 3041.09 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 1.36 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 4423.43 | |
| Balance | 3036.18 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0 |
| 2 | Amount deposited in Escrow Account | 3.55 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 3.55 |
| Total Plots in the colony | 266 |
| Plots sold upto the date of Registration | 0 |
| S.No. | Type/Size | Plots Sold in the Quarter |
| 1 | PLOT/DSS | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 118.06 |
| 4 | Others Expenditure | 94.50 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 215.99 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||