Quarterly Schedules

HRERA Gurugram
Project Registration Number : GGM/342/74/2019/36 DATED 05.07.2019
Project Name : SS HIGH POINT
Project Number : RERA-GRG-255-2019
Project Type : NEW
S.No.ParticularsAmount
(In Lakhs)
1Cost of the land (if included in the estimated cost)2410
2Estimated cost of construction of apartments6873
3Estimated cost of infrastructure & other structure1827
4Other cost including EDC taxes, levies, etc4566
Total18204



Name of the approvalStatusDate
Layout PlanHave not applied till dateN/A
Demarcation PlanHave not applied till dateN/A
Zoning PlanHave not applied till dateN/A
Service PlansHave not applied till dateN/A
Electricity PlansHave not applied till dateN/A



Name of the approvalStatusDate
Demarcation PlanObtained Approval on28-11-2018
Zoning PlanObtained Approval on17-01-2019
Service PlansHave not applied till dateN/A
Electricity PlansHave not applied till dateN/A
Site PlansObtained Approval on17-05-2019
Building PlansObtained Approval on17-05-2019
FIre NOCHave not applied till dateN/A
Total Expenditure on the project18204
Expenditure made upto the date of Registration3444.20



EDC due as on the date of Registration325

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance63
2Amount collected from allottees against booked plots and/or apartments316.07
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total379.07



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments137.35
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc29.71
Total167.06
Balance18.88



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter56.65
2Amount deposited in Escrow Account44.21
3Amount withdrawn during the quarter84.30
4Balance at the end of the quarter16.56
Total Apartments in the colony207
Apartments sold upto the date of Registration19



S.No.Type/SizePlots Sold in the Quarter
1COMMERCIAL1



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments137.35
3EDC, IDC, etc0
4Others Expenditure29.71



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date325
2EDC due as on date162
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 24-07-2020  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 24-07-2020  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 28-07-2020  View 
4 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 28-07-2020  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 24-07-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance18.88
2Amount collected from allottees against booked plots and/or apartments160.31
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total179.19



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments139.67
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc32.44
Total172.01
Balance0.80



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter16.56
2Amount deposited in Escrow Account32.70
3Amount withdrawn during the quarter48.50
4Balance at the end of the quarter0.76
Total Apartments in the colony207
Apartments sold upto the date of Registration19



S.No.Type/SizePlots Sold in the Quarter
1RETAIL SHOPS21



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1UNDERGROUND PARKING0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments139.67
3EDC, IDC, etc0
4Others Expenditure32.44



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date325
2EDC due as on date325
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 26-09-2020  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 26-09-2020  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 26-09-2020  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 26-09-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 26-09-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0.80
2Amount collected from allottees against booked plots and/or apartments37.58
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt5.52
Total43.90



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments27.27
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc11.12
Total38.39
Balance5.51



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.76
2Amount deposited in Escrow Account3.50
3Amount withdrawn during the quarter0.27
4Balance at the end of the quarter3.99
Total Apartments in the colony207
Apartments sold upto the date of Registration19



S.No.Type/SizePlots Sold in the Quarter
1RETAIL SHOPS4



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1UNDERGROUND PARKING0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments27.27
3EDC, IDC, etc11.12
4Others Expenditure38.39



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date325
2EDC due as on date487
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 26-09-2020  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 26-09-2020  View 
3 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 26-09-2020  View 
4 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 26-09-2020  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 26-09-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance5.51
2Amount collected from allottees against booked plots and/or apartments86.33
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates44.28
5Any other receipt0
Total136.12



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments40.17
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc94.06
Total134.23
Balance1.89



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter3.99
2Amount deposited in Escrow Account60.81
3Amount withdrawn during the quarter64.50
4Balance at the end of the quarter0.31
Total Plots in the colony207
Plots sold upto the date of Registration19



S.No.Type/SizePlots Sold in the Quarter
10



Total Apartments in the colony207
Apartments sold upto the date of Registration19



S.No.Type/SizePlots Sold in the Quarter
1RETAILS SHOPS8



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments40.17
3EDC, IDC, etc0
4Others Expenditure94.06



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date325
2EDC due as on date162
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 31-12-2020  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 31-12-2020  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 31-12-2020  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 31-12-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 31-12-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance1.89
2Amount collected from allottees against booked plots and/or apartments336.28
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates-236.21
5Any other receipt0
Total338.17



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments59.52
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc30.93
Total90.85
Balance11.51



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0.31
2Amount deposited in Escrow Account8.09
3Amount withdrawn during the quarter0
4Balance at the end of the quarter8.40
Total Apartments in the colony207
Apartments sold upto the date of Registration19



S.No.Type/SizePlots Sold in the Quarter
1RETAILS SHOPS16



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments95.42
3EDC, IDC, etc0
4Others Expenditure30.93



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date325
2EDC due as on date812.25
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 10-04-2021  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 10-04-2021  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 10-04-2021  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 10-04-2021  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 10-04-2021  View