Quarterly Schedules | ||
| HRERA Gurugram | ||
| Project Registration Number : GGM/340/72/2019/34 DATED 27.05.2019 | ||
| Project Name : SOBHA CITY PHASE IV | ||
| Project Number : RERA-GRG-139-2018 | ||
| Project Type : NEW | ||
| Report Online Submission Date : 22-Oct-2020 |
| S.No. | Particulars | Amount (In Lakhs) |
| 1 | Cost of the land (if included in the estimated cost) | 5730 |
| 2 | Estimated cost of construction of apartments | 14262 |
| 3 | Estimated cost of infrastructure & other structure | 368 |
| 4 | Other cost including EDC taxes, levies, etc | 13935 |
| Total | 34295 |
| Name of the approval | Status | Date |
| Demarcation Plan | Obtained Approval on | 04-08-2010 |
| Zoning Plan | Obtained Approval on | 30-08-2010 |
| Service Plans | Obtained Approval on | 17-01-2023 |
| Electricity Plans | Obtained Approval on | 15-11-2019 |
| Site Plans | Obtained Approval on | 27-09-2022 |
| Building Plans | Obtained Approval on | 27-09-2022 |
| FIre NOC | Obtained Approval on | 01-02-2023 |
| Total Expenditure on the project | 368 |
| Expenditure made upto the date of Registration | 0 |
| EDC due as on the date of Registration | 0 |
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 162.80 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 402 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 564.80 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 114 |
| Total | 114 | |
| Balance | 450.80 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 28.13 |
| 2 | Amount deposited in Escrow Account | 238.72 |
| 3 | Amount withdrawn during the quarter | 266.70 |
| 4 | Balance at the end of the quarter | 0.15 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | B | 5 |
| 2 | C | 9 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 114 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 450.80 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 421 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 871.80 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 137 | |
| Balance | 734.80 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 0.15 |
| 2 | Amount deposited in Escrow Account | 364.22 |
| 3 | Amount withdrawn during the quarter | 341 |
| 4 | Balance at the end of the quarter | 23.37 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | B | 6 |
| 2 | C | 4 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 137 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 734.80 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 317 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 1051.80 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 113 |
| Total | 113 | |
| Balance | 938.80 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 23.37 |
| 2 | Amount deposited in Escrow Account | 165.45 |
| 3 | Amount withdrawn during the quarter | 183.20 |
| 4 | Balance at the end of the quarter | 5.62 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | B | 4 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 113 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 938.80 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 322 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 1260.80 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 115 |
| Total | 115 | |
| Balance | 1145.80 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 5.62 |
| 2 | Amount deposited in Escrow Account | 307.93 |
| 3 | Amount withdrawn during the quarter | 291.80 |
| 4 | Balance at the end of the quarter | 21.75 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | B | 4 |
| 2 | C | 5 |
| 3 | C1 | 1 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 115 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 1145.80 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 506.50 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 1652.30 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 188 |
| Total | 188 | |
| Balance | 1464.30 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 21.75 |
| 2 | Amount deposited in Escrow Account | 338.45 |
| 3 | Amount withdrawn during the quarter | 43.90 |
| 4 | Balance at the end of the quarter | 316.31 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | B | 7 |
| 2 | C | 5 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 188 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 1464.30 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 828.45 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 2292.75 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 304 |
| Total | 304 | |
| Balance | 1988.75 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 316.31 |
| 2 | Amount deposited in Escrow Account | 681.27 |
| 3 | Amount withdrawn during the quarter | 404 |
| 4 | Balance at the end of the quarter | 593.58 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | B | 10 |
| 2 | C | 6 |
| 3 | C1 | 2 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 304 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 1988.75 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 911 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 2899.75 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 754 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 310 |
| Total | 1064 | |
| Balance | 1835.75 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 593.58 |
| 2 | Amount deposited in Escrow Account | 493.41 |
| 3 | Amount withdrawn during the quarter | 303.90 |
| 4 | Balance at the end of the quarter | 783.09 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | A | 3 |
| 2 | B | 15 |
| 3 | C | 2 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 754 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 310 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 1835.75 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 1380 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 3215.75 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 690 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 559 |
| Total | 1249 | |
| Balance | 1966.75 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 783.09 |
| 2 | Amount deposited in Escrow Account | 1013.61 |
| 3 | Amount withdrawn during the quarter | 1697.50 |
| 4 | Balance at the end of the quarter | 99.20 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | A | 1 |
| 2 | B | 22 |
| 3 | B1 | 1 |
| 4 | C | 15 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 690 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 559 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 1966.75 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 2488 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 4454.75 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 846 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 884 |
| Total | 1730 | |
| Balance | 2724.75 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 99.20 |
| 2 | Amount deposited in Escrow Account | 1655.04 |
| 3 | Amount withdrawn during the quarter | 1685.80 |
| 4 | Balance at the end of the quarter | 68.45 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | A | 5 |
| 2 | B | 12 |
| 3 | B1 | 2 |
| 4 | C | 13 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 846 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 884 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 2724.75 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 3429 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 6153.75 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 799 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 1272 |
| Total | 2071 | |
| Balance | 4082 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 68.45 |
| 2 | Amount deposited in Escrow Account | 2260.19 |
| 3 | Amount withdrawn during the quarter | 1865.75 |
| 4 | Balance at the end of the quarter | 462.89 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | A | 10 |
| 2 | A1 | 1 |
| 3 | B | 26 |
| 4 | B1 | 2 |
| 5 | C | 3 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 799 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 1272 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 4082 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 2474 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 6556 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 617 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 947 |
| Total | 1564 | |
| Balance | 4992 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 462.89 |
| 2 | Amount deposited in Escrow Account | 1491.93 |
| 3 | Amount withdrawn during the quarter | 1875.89 |
| 4 | Balance at the end of the quarter | 78.94 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | A | 6 |
| 2 | B | 28 |
| 3 | B1 | 2 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 617 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 947 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 4992 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 6086 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 11078 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 882 |
| 2 | Expenditure on infrastructure & other structure | 94 |
| 3 | Other costs including EDC, taxes, etc | 2350 |
| Total | 3326 | |
| Balance | 7752 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 78.94 |
| 2 | Amount deposited in Escrow Account | 4410.03 |
| 3 | Amount withdrawn during the quarter | 2588.40 |
| 4 | Balance at the end of the quarter | 1900.58 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | A | 26 |
| 2 | A1 | 1 |
| 3 | B | 7 |
| 4 | B1 | 3 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 94 |
| 2 | Apartments | 882 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 1482 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 7752 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 2506 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 10258 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 1162 |
| 2 | Expenditure on infrastructure & other structure | 24 |
| 3 | Other costs including EDC, taxes, etc | 1216 |
| Total | 2402 | |
| Balance | 7856 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 1900.58 |
| 2 | Amount deposited in Escrow Account | 1798.55 |
| 3 | Amount withdrawn during the quarter | 2732.00 |
| 4 | Balance at the end of the quarter | 967.13 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | A | 18 |
| 2 | A1 | 2 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 24 |
| 2 | Apartments | 1162 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 1216 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 7856 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 4773 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 12629 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 816 |
| 2 | Expenditure on infrastructure & other structure | 17 |
| 3 | Other costs including EDC, taxes, etc | 1620 |
| Total | 2453 | |
| Balance | 10176 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 967.13 |
| 2 | Amount deposited in Escrow Account | 3077.15 |
| 3 | Amount withdrawn during the quarter | 2548.98 |
| 4 | Balance at the end of the quarter | 1495.31 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 17 |
| 2 | Apartments | 816 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 1620 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 10176 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 1781 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 11957 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 625 |
| 2 | Expenditure on infrastructure & other structure | 54 |
| 3 | Other costs including EDC, taxes, etc | 695 |
| Total | 1374 | |
| Balance | 10583 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 1495.31 |
| 2 | Amount deposited in Escrow Account | 1756.02 |
| 3 | Amount withdrawn during the quarter | 1853.69 |
| 4 | Balance at the end of the quarter | 1397.64 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 54 |
| 2 | Apartments | 625 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 695 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 10583 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 2467 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 13050 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 901 |
| 2 | Expenditure on infrastructure & other structure | 80 |
| 3 | Other costs including EDC, taxes, etc | 981 |
| Total | 1962 | |
| Balance | 11088 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 1397.64 |
| 2 | Amount deposited in Escrow Account | 2174.28 |
| 3 | Amount withdrawn during the quarter | 1559.09 |
| 4 | Balance at the end of the quarter | 2012.84 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 80 |
| 2 | Apartments | 901 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 981 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 11088 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 3337 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 14425 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 1858 |
| 2 | Expenditure on infrastructure & other structure | 38 |
| 3 | Other costs including EDC, taxes, etc | 1306 |
| Total | 3202 | |
| Balance | 11223 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 2012.84 |
| 2 | Amount deposited in Escrow Account | 2466.47 |
| 3 | Amount withdrawn during the quarter | 3325.56 |
| 4 | Balance at the end of the quarter | 1153.75 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 38 |
| 2 | Apartments | 1858 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 1306 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 11223 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 0 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 11223 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 0 | |
| Balance | 11223 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 1153.75 |
| 2 | Amount deposited in Escrow Account | 0 |
| 3 | Amount withdrawn during the quarter | 0 |
| 4 | Balance at the end of the quarter | 1153.75 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 11223 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 3593 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 14816 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 2200 |
| 2 | Expenditure on infrastructure & other structure | 45 |
| 3 | Other costs including EDC, taxes, etc | 2115 |
| Total | 4360 | |
| Balance | 10456 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 1153.75 |
| 2 | Amount deposited in Escrow Account | 2599.33 |
| 3 | Amount withdrawn during the quarter | 2475.49 |
| 4 | Balance at the end of the quarter | 1277.59 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 45 |
| 2 | Apartments | 2200 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 2115 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 10456 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 3983 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 14439 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 988 |
| 2 | Expenditure on infrastructure & other structure | 18 |
| 3 | Other costs including EDC, taxes, etc | 1337 |
| Total | 2343 | |
| Balance | 12096 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 1277.59 |
| 2 | Amount deposited in Escrow Account | 2716.41 |
| 3 | Amount withdrawn during the quarter | 3936.46 |
| 4 | Balance at the end of the quarter | 57.55 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 18 |
| 2 | Apartments | 988 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 1337 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 12096 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 3105 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 15201 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 462 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 1122 |
| Total | 1584 | |
| Balance | 13617 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 57.55 |
| 2 | Amount deposited in Escrow Account | 2188.04 |
| 3 | Amount withdrawn during the quarter | 1431.30 |
| 4 | Balance at the end of the quarter | 814.30 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 462 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 1122 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 13617 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 2590.11 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 16207.11 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 202 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 1075 |
| Total | 1277 | |
| Balance | 14930.11 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 814.30 |
| 2 | Amount deposited in Escrow Account | 1841.46 |
| 3 | Amount withdrawn during the quarter | 1317.90 |
| 4 | Balance at the end of the quarter | 1337.87 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 202 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 1075 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 14930.11 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 206.29 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 15136.4 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 217 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 85 |
| Total | 302 | |
| Balance | 14834.4 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 1337.87 |
| 2 | Amount deposited in Escrow Account | 174.91 |
| 3 | Amount withdrawn during the quarter | 1075 |
| 4 | Balance at the end of the quarter | 437.78 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 217 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 85 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 14834.4 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 1212.12 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 16046.52 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 236 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 220 |
| Total | 456 | |
| Balance | 15590.52 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 437.78 |
| 2 | Amount deposited in Escrow Account | 849.40 |
| 3 | Amount withdrawn during the quarter | 302.20 |
| 4 | Balance at the end of the quarter | 984.99 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 236 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 220 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||
| S.No. | Cash Inflow | Amount (In Lakhs) |
| 1 | Opening Balance | 15590.52 |
| 2 | Amount collected from allottees against booked plots and/or apartments | 103.91 |
| 3 | Amount availed from the bank/financial institutions | 0 |
| 4 | Amount contributed by the promoters/his associates | 0 |
| 5 | Any other receipt | 0 |
| Total | 15694.43 |
| S.No. | Cash Outflow | Amount (In Lakhs) |
| 1 | Expenditure on construction of apartments | 0 |
| 2 | Expenditure on infrastructure & other structure | 0 |
| 3 | Other costs including EDC, taxes, etc | 0 |
| Total | 0 | |
| Balance | 15694.43 |
| S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
| 1 | Opening balance at the beginning of the quarter | 984.99 |
| 2 | Amount deposited in Escrow Account | 99.85 |
| 3 | Amount withdrawn during the quarter | 341.50 |
| 4 | Balance at the end of the quarter | 743.34 |
| Total Apartments in the colony | 288 |
| Apartments sold upto the date of Registration | 0 |
| S.No. | Type/Size | Apartments Sold in the Quarter |
| 1 | 0 |
| Total Garages in the colony | 0 |
| Garages sold upto the date of Registration | 0 |
| S.No. | Type/Size | Garages Sold in the Quarter |
| 1 | 0 |
| S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
| 1 | Infrastructure | 0 |
| 2 | Apartments | 0 |
| 3 | EDC, IDC, etc | 0 |
| 4 | Others Expenditure | 0 |
| S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
| 1 | Actual paid as on date | 0 |
| 2 | EDC due as on date | 0 |
| ||||||||||||||||||||||||||