S.No. | Particulars | Amount (In Lakhs) |
1 | Cost of the land (if included in the estimated cost) | 3113 |
2 | Estimated cost of construction of apartments | 7148 |
3 | Estimated cost of infrastructure & other structure | 0 |
4 | Other cost including EDC taxes, levies, etc | 1539 |
Total | 11800 |
Name of the approval | Status | Date |
Demarcation Plan | Obtained Approval on | 04-10-2019 |
Zoning Plan | Obtained Approval on | 04-10-2019 |
Service Plans | Have not applied till date | N/A |
Electricity Plans | Have not applied till date | N/A |
Site Plans | Have not applied till date | N/A |
Building Plans | Obtained Approval on | 29-01-2020 |
FIre NOC | Have not applied till date | N/A |
Total Expenditure on the project | 0 |
Expenditure made upto the date of Registration | 0 |
EDC due as on the date of Registration | 0 |
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 0 |
2 | Amount collected from allottees against booked plots and/or apartments | 5 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | 2301 |
5 | Any other receipt | 4.5 |
Total | 2310.5 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 55 |
2 | Expenditure on infrastructure & other structure | 0 |
3 | Other costs including EDC, taxes, etc | 275 |
Total | 330 | |
Balance | 8357 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 8 |
3 | Amount withdrawn during the quarter | 0 |
4 | Balance at the end of the quarter | 8 |
Total Plots in the colony | 0 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | NA | 0 |
Total Apartments in the colony | 72 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 3BHK+3T (CORNER) | 1 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | NA | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 0 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 0 |
4 | Others Expenditure | 0 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 0 |
2 | EDC due as on date | 0 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 2310 |
2 | Amount collected from allottees against booked plots and/or apartments | 100 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | -180 |
5 | Any other receipt | 0 |
Total | 2230 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 55 |
2 | Expenditure on infrastructure & other structure | 0 |
3 | Other costs including EDC, taxes, etc | 59 |
Total | 114 | |
Balance | 8243 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 8 |
2 | Amount deposited in Escrow Account | 70 |
3 | Amount withdrawn during the quarter | 78 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 0 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 0 |
Total Apartments in the colony | 72 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 3BHK+3T (CORNER) | 6 |
2 | 3BHK+3T (MIDDLE) | 3 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 0 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 0 |
4 | Others Expenditure | 0 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 0 |
2 | EDC due as on date | 0 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 2230 |
2 | Amount collected from allottees against booked plots and/or apartments | 465 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | 204 |
5 | Any other receipt | 1 |
Total | 2900 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 174 |
2 | Expenditure on infrastructure & other structure | 0 |
3 | Other costs including EDC, taxes, etc | 141 |
Total | 315 | |
Balance | 7928 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 234.78 |
3 | Amount withdrawn during the quarter | 234.78 |
4 | Balance at the end of the quarter | 0 |
Total Plots in the colony | 0 |
Plots sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 0 |
Total Apartments in the colony | 72 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 3BHK+3T (CORNER) | 8 |
2 | 3BHK+3T (MIDDLE) | 13 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 0 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 0 |
4 | Others Expenditure | 0 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 0 |
2 | EDC due as on date | 0 |
|
S.No. | Cash Inflow | Amount (In Lakhs) |
1 | Opening Balance | 2900 |
2 | Amount collected from allottees against booked plots and/or apartments | 979 |
3 | Amount availed from the bank/financial institutions | 0 |
4 | Amount contributed by the promoters/his associates | 8 |
5 | Any other receipt | 12 |
Total | 3898 |
S.No. | Cash Outflow | Amount (In Lakhs) |
1 | Expenditure on construction of apartments | 92 |
2 | Expenditure on infrastructure & other structure | 0 |
3 | Other costs including EDC, taxes, etc | 298 |
Total | 390 | |
Balance | 7538 |
S.No. | Information relating to Escrow Account | Amount (In Lakhs) |
1 | Opening balance at the beginning of the quarter | 0 |
2 | Amount deposited in Escrow Account | 464.77 |
3 | Amount withdrawn during the quarter | 125.97 |
4 | Balance at the end of the quarter | 338.80 |
Total Apartments in the colony | 72 |
Apartments sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 3BHK+3T (CORNER) | 10 |
2 | 3BHK+3T (MIDDLE) | 24 |
Total Garages in the colony | 0 |
Garages sold upto the date of Registration | 0 |
S.No. | Type/Size | Plots Sold in the Quarter |
1 | 0 |
S.No. | Expenditure on Infrastructure made in the Quarter | Amount (In Lakhs) |
1 | Infrastructure | 0 |
2 | Apartments | 0 |
3 | EDC, IDC, etc | 0 |
4 | Others Expenditure | 0 |
S.No. | Expenditure on Taxes,Levies,EDC etc in the Quarter | Amount (In Lakhs) |
1 | Actual paid as on date | 0 |
2 | EDC due as on date | 0 |
|