HRERA GurugramTemp Project Id : RERA-GRG-PROJ-484-2019
Submission Date : 13-01-2020 11:12:52 AM
Applicant Type : Company
Project Type: ONGOING




VATIKA ONE ON ONE PRIVATE LIMITED (FORMERLY KNOWN AS CALDER DEVELOPERS PVT. LTD.)
FLAT NO. 224A, 2ND FLOOR DEVIKA TOWER, 6, NEHRU PLACE NEW DELHI - 110019.
01244177777
9810566938 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com
http://www.vatikagroup.com
XXXX937P
U70101DL2011PTC213593
 
 


 
 


 
 


 
 


 
 







ONE ON ONE (PHASE-I)
SECTOR-16, VILLAGE SILOKHERA
WAZIRABAD ST
GURUGRAM
0000000000
9810656416 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com
SUBHASH GOEL
0000000000
9810656416 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
15694228-07-2017850000.00HDFC BANK LIMITEDHRERA Gurugram







49093.349 (Sqr/mtrs)
175
86.465
49093.349 (Sqr/mtrs)
License No. 5 of 2015 dated 06.08.2015
No
Address     R/O - 1589, MADARSA ROAD, KASHMERE GATE, DELHI.
Address     R/O - 1589, MADARSA ROAD, KASHMERE GATE, DELHI.
Address     R/O - 1589, MADARSA ROAD, KASHMERE GATE, DELHI.
Address     R/O - 1589, MADARSA ROAD, KASHMERE GATE, DELHI.
Address     R/O - 1589, MADARSA ROAD, KASHMERE GATE, DELHI.
Address     R/O - 1589, MADARSA ROAD, KASHMERE GATE, DELHI.
Address     R/O - 1589, MADARSA ROAD, KASHMERE GATE, DELHI.
Address     R/O - 1589, MADARSA ROAD, KASHMERE GATE, DELHI.
Annexure-B- COLLABORATION AGREEMENTS, GPA REVENUE RECORDS, ETC.
YES
Yes
PROVIDED
No
Yes
Yes







63342.00 Lakhs
15200.00 Lakhs
22500.00 Lakhs
2500.00 Lakhs
23142.00 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS9417.242
3CONSTRUCTION OF ROADS0
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0
7VEHICLE PARKINGS5180.843
8ELECTRICITY SUB-STATION260.458
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER34234.806
Total49093.349




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDA/HSVPNo
WATER SUPPLYHUDA/HSVPNo
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHUDA/HSVPNo
STORM WATER DRAINAGEHUDA/HSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS450.00AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM375.00AS PER PROJECT REPORT
3STORM WATER DRAINAGE200.00AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM100.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL250.00AS PER PROJECT REPORT
6STREET LIGHTING100.00AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING275.00AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS25.00AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM50.00AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT
15STP150.00YET TO BE PREPARED
16UNDERGROUND TANK175.00YET TO BE PREPARED
17RAIN WATER HARVESTING75.00YET TO BE PREPARED
18ELECTRICAL SUB STATION125.00YET TO BE PREPARED
19PARKING150.00YET TO BE PREPARED


18-05-2017 (date)
18-05-2017 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type ANNEX-20 (DETAILS OF UNITS)34285.8210986324664






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
ANNEX-20 (DETAILS OF UNITS)632ANNEXURE 20


20-05-2017
31-07-2020
31-07-2020
20-05-2017
9.12
31-07-2020
PROVIDED
PROVIDED


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
20-05-2017
0
31-07-2020
NOT APPLICABLE
NOT APPLICABLE


0
0
850
30
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops5349.60
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments000
Shops0750900
Plots000
Infrastructure Development Charges0
Other Cost0
External Development Charges0
Cost of Construction0
Internal Development Works0

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops950110012501290
Plots0000

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops1881229710402081
Plots0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops10401356.001215.400
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments00
Shops00
Plots00




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements100.00
Water Supply System100.00
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Electrical Sub station0
Parking28.06
Rain Water Harvesting0
Renewable energy system0
Security and fire fighting0
STP0
Street lighting0
Underground Tank0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements13.5016.20
Water Supply System11.2513.50
Sewerage treatment & garbage disposal7.509.00
Electricity Supply System3.003.60
Storm Water Drainage6.007.20
Parks and Playgrounds0.750.90
Clubhouse/community centres00
Shopping area00
Other00
STP4.505.40
Street lighting3.003.60
Security and fire fighting8.259.90
Renewable energy system1.501.80
Underground Tank5.256.30
Rain Water Harvesting2.252.70
Electrical Sub station3.754.50
Parking4.505.40

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements18.0022.5025.2029.88
Water Supply System15.0018.7521.0024.90
Sewerage treatment & garbage disposal10.0012.5014.0016.60
Electricity Supply System4.005.005.606.64
Storm Water Drainage8.0010.0011.2013.28
Parks and Playgrounds1.001.251.401.66
Clubhouse/community centres0000
Shopping area0000
Other0000
Rain Water Harvesting3.003.754.204.98
STP6.007.508.409.96
Underground Tank7.008.759.8011.62
Electrical Sub station5.006.257.008.30
Parking6.007.508.409.96
Street lighting4.005.005.606.64
Security and fire fighting11.0013.7515.4018.26
Renewable energy system2.002.502.803.32

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements41.5844.8120.8877.58
Water Supply System34.6537.3417.4064.65
Sewerage treatment & garbage disposal23.1024.8911.6043.10
Electricity Supply System9.249.964.6417.24
Storm Water Drainage18.4819.929.2834.48
Parks and Playgrounds2.312.491.164.31
Clubhouse/community centres0000
Shopping area0000
Other0000
Rain Water Harvesting6.937.473.4812.93
Parking13.8614.946.9625.86
Electrical Sub station11.5512.455.8021.55
Underground Tank16.1717.438.1230.17
STP13.8614.946.9625.86
Renewable energy system4.624.982.328.62
Security and fire fighting25.4127.3812.7647.41
Street lighting9.249.964.6417.24

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements20.8847.1630.78
Water Supply System17.4039.3025.65
Sewerage treatment & garbage disposal11.6026.2017.10
Electricity Supply System4.6410.486.84
Storm Water Drainage9.2820.9613.68
Parks and Playgrounds1.162.621.71
Clubhouse/community centres000
Shopping area000
Other000
Rain Water Harvesting3.487.865.13
Electrical Sub station5.8013.108.55
Parking6.9615.7210.26
Street lighting4.6410.486.84
Security and fire fighting12.7628.8218.81
Renewable energy system2.325.243.42
STP6.9615.7210.26
Underground Tank8.1218.3411.97












Particulars Remarks, if any
i. No. of Flats/Apartments constructed1098To be Constructed
ii. No. of Flats/ Apartments booked632
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter35505.28 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter33663.17 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter1842.11 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter1842.11 Lakhs
vii. Amount invested in the project upto the date of application32468.48 Lakhs
Land cost (If any)15100.13 Lakhs
Apartments5349.60 Lakhs
Infrastructure228.06 Lakhs
EDC/ Taxes Etc.11790.69 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession30873.52 Lakhs
(a) In respect of existing allottees17770.55 Lakhs
(b) In respect of rest of the project13102.97 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
11580.00 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 11580.00 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS450.00100.00
II. WATER SUPPLY SYSTEM375.00100.00
III. STORM WATER DRAINAGE200.000
IV. ELECTRICITY SUPPLY SYSTEM100.000
V. SEWAGE TREATMENT & GARBAGE DISPOSAL250.000
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.25.000
XIII. COVERED PARKING15028.06
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM275.000
XVII. OTHER FACILITIES AS PER PROJECT REPORT675.000









Yes
Yes
HDFC BANK LTD. , FIRST INDIA PLACE, M.G.ROAD, GURUGRAM HARYANA-122002.
02800350000419
HDFC0000280
110240037
0280
Mr. Anil Bhalla-Hyde Park, Prakrati Marg, Sultanpur Farms, Gadaipur, South Delhi, Delhi 110030 Mr. Gautam Bhalla-LCG05 PHB, The Laburnam, Nathupur (67),Nathupur Gurgaon,Gurgaon, Haryana 122002 Mr. K. V. George-Flat No. 1504, Mohinder Apartment, Plot No 17, Sector 12, Dwarka, South West Delhi, Delhi 110075 Ms. Veena Bhoomia-C1/577B,Rear Block,1st Floor, Near Euro Kids School,Palam Vihar,Choma (62), Gurgaon, Haryana 122017
Uploaded











Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LAY OUT PLANALREADY BEEN OBTAINED18-05-2017
II. ZONING PLANALREADY BEEN OBTAINED07-08-2015
III. BUILDING PLANALREADY BEEN OBTAINED18-05-2017
IV. SITE PLANALREADY BEEN OBTAINED18-05-2017
V. FLOOR PLANALREADY BEEN OBTAINED18-05-2017
VI. APARTMENT PLANSALREADY BEEN OBTAINED18-05-2017
VII. ELEVATION SECTIONALREADY BEEN OBTAINED18-05-2017
VIII. DETAIL OF PERMISSIBLE FARALREADY BEEN OBTAINED18-05-2017
IX. DETAIL OF COVERED AREA ACHIEVED FAR.ALREADY BEEN OBTAINED18-05-2017








Yes


Yes


Provided







NIL - THIS IS THE FIRST PROJECT OF THE COMPANY
0
0
0
0
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
000
Cost of the apartments000
Cost of the infrastructure000
Others costs000


0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
19-09-2022
19-09-2022










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSECOMBINATION OF MATERIALS SUCH AS STONE, HIGH QUALITY TILES IN COMMON AREAS
2WALL FINISHING DETAILSCOMBINATION OF TILES & PAINT IN COMMON AREAS.
3KITCHEN DETAILSNOT APPLICABLE
4BATHROOM FITTINGSSANITARY WARE OF STANDARD MAKE AND BRANDS FOR COMMON TOILETS.
5WOOD WORK ETCNOT APPLICABLE
6DOORS AND WINDOS FRAMESNOT APPLICABLE
7GLASS WORKNOT APPLICABLE
8ELECTRIC FITTINGSNOT APPLICABLE
9CONDUCTING AND WIRING DETAILSIS COMPLIANT WIRING IN COMMON AREAS.
10CUPBOARD DETAILSNOT APPLICABLE
11WATER STORAGEOHT & UG TANKS
12LIFT DETAILSPASSENGER ELEVATORS DESIGNED TO CATER FOR THE EXPECTED TRAFFIC WITH HIGH QUALITY FINISHES. DEDICATED SERVICE LIFT FOR MOVEMENT OF GOODS AND MATERIALS ONE PER BLOCK
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSGLAZED ALUMINUM WINDOWS AND FENESTRATION ALONG WITH CURTAIN GLASS IN LOCATIONS
14DOORSNA
14.1MAIN DOORSNOT APPLICABLE
14.2INTERNAL DOORSNOT APPLICABLE
15AIR CONDITIONINGOFFICE SPACE SHALL BE AIR-CONDITIONED THROUGH HIGHLY ENERGY EFFICIENT CENTRAL A.C. SYSTEM WITH BMS
16ELECTRICAL FITTINGSIS COMPLIANT PROVISIONING FOR CRITICAL LIGHTING IN AREAS OF CIRCULATION AND EMERGENCY USAGE
17CNG PIPE LINENOT APPLICABLE
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE
19EXTERNAL FINISHING/COLOUR SCHEMEA COMBINATION OF MATERIALS OF INTERNATIONAL STANDARDS SUCH AS CLADDING, HIGH QUALITY PAINT ETC
20INTERNAL FINISHINGCOMBINATION OF MATERIALS SUCH AS STONE, HIGH QUALITY TILES, WALL AND CEILING FINISHES FOR COMMON AREAS
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNOT APPLICABLE
1 . 2 WALLSNOT APPLICABLE
1 . 3 CEILINGNOT APPLICABLE
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNOT APPLICABLE
2 . 2 WALLSNOT APPLICABLE
2 . 3 CEILINGNOT APPLICABLE
2 . 4 MODULAR WARDROBESNOT APPLICABLE
3 . MASTER TOILET
3 . 1 FLOORNOT APPLICABLE
3 . 2 WALLSNOT APPLICABLE
3 . 3 CEILINGNOT APPLICABLE
3 . 4 COUNTERSNOT APPLICABLE
3 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
3 . 6 FITTING/FIXTURESNOT APPLICABLE
4 . BED ROOMS
4 . 1 FLOORNOT APPLICABLE
4 . 2 WALLSNOT APPLICABLE
4 . 3 CEILINGNOT APPLICABLE
4 . 4 WARDROBESNOT APPLICABLE
5 . TOILET
5 . 1 FLOORNOT APPLICABLE
5 . 2 WALLSNOT APPLICABLE
5 . 3 CEILINGNOT APPLICABLE
5 . 4 COUNTERSNOT APPLICABLE
5 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
5 . 6 FIXTURESNOT APPLICABLE
6 . KITCHEN
6 . 1 FLOORNOT APPLICABLE
6 . 2 WALLSNOT APPLICABLE
6 . 3 CEILINGNOT APPLICABLE
6 . 4 COUNTERSNOT APPLICABLE
6 . 5 FIXTURESNOT APPLICABLE
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNOT APPLICABLE
7 . 2 WALLS & CEILINGNOT APPLICABLE
7 . 3 TOILETNOT APPLICABLE
7 . 4 BALCONYNOT APPLICABLE
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE
8 . 2 WALLS & CEILINGNOT APPLICABLE
8 . 3 RAILINGSNOT APPLICABLE
8 . 4 FIXTURESNOT APPLICABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.12-02-2020 View Document
2DETAIL OF AUTHORISED SIGNATORY12-02-2020 ------
3FIRE FIGHTING SCHEME12-02-2020 ------
4CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT12-02-2020 View Document
5FOREST NOC12-02-2020 ------
6CASH FLOW STATEMENT OF THE PROPOSED PROJECT12-02-2020 View Document
7LC-IV AND BILATERAL AGREEMENT12-02-2020 ------
8ENVIRONMENT CLEARANCE12-02-2020 ------
9DETAILS OF UNITS WITH CONSTRUCTION STAGES20-02-2020 ------
10DETAILS OF SEPARATE BANK ACCOUNT11-03-2020 ------
11A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS21-12-2019 View Document
12ZONING PLAN21-12-2019 View Document
13IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN21-12-2019 View Document
14IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN21-12-2019 View Document
15NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT21-12-2019 View Document
16BLOCK 3 ELEVATION ABCD13-01-2020 ------
17LICENSE NO 05 OF 201511-01-2020 ------
18LIST OF ARCHITECT ENGINEER ETC11-01-2020 ------
19BASEMENT 1 FLOOR PLAN AREA CALCULATION13-01-2020 ------
20BLOCK 4 6TH 7TH SERVICE FLOOR PLANS13-01-2020 ------
21ENARGY CENTER 2ND MAZZENINE FLOOR PLANS13-01-2020 ------
22CA CERTIFICATE11-01-2020 ------
23BLOCK 4 ELE 1 AND 313-01-2020 ------
24BLOCK 3 2ND 3RD 4TH FLOOR PLANS13-01-2020 ------
25BLOCK 2 TERRACE AND LMR FLOOR PLAN13-01-2020 ------
26ENARGY CENTER13-01-2020 ------
27ANNEXURE-3.3 (DEVELOPMENT PLAN)11-01-2020 ------
28BLOCK 5 ELEVATION ABCD13-01-2020 ------
29BLOCK 5 5TH 6TH FLOOR PLANS13-01-2020 ------
30REP I (OLD)11-01-2020 ------
31BLOCK 5 AREA CALCULATION AL FLOOR PLAN13-01-2020 ------
32BLOCK 4 ELE 2 AND 4 SEC A AND B13-01-2020 ------
332 REGISTRATION CERTIFICATE11-01-2020 ------
34BALANCE SHEET11-01-2020 ------
35AKS SHEJRA WITH LAND DETAILS11-01-2020 ------
36AGREEMENT FOR SALE11-01-2020 ------
37LOCATION PLAN11-01-2020 ------
38DETAIL OF PARKING11-01-2020 ------
39AFS COMMERCIAL FINAL11-01-2020 ------
40SECTORIAL MAP11-01-2020 ------
419 REVENUE RECORDS SALE DEED ETC11-01-2020 ------
42SITE PLAN11-01-2020 ------
43ENCUMBRANCES11-01-2020 ------
44BLOCK 5 TERRACE AND LMR FLOOR PLAN13-01-2020 ------
45SHAREHOLDERS11-01-2020 ------
46BUILDING PLAN11-01-2020 ------
47DEATIL OF UNIT11-01-2020 ------
48BOOKING APPLICATION FORM11-01-2020 ------
49BLOCK 4 GF 1ST FLOOR PLANS13-01-2020 ------
50BLOCK 3 TERRACE AND LMR FLOOR PLAN13-01-2020 ------
51MOA AND AOA11-01-2020 ------
52ARCHITECT AND ENGINEER CERTIFICATE11-01-2020 ------
53BLOCK 2 2ND 5TH FLOOR PLANS13-01-2020 ------
54TIME PERIOD COMMITED TO ALLOTTEE11-01-2020 ------
55BLOCK 2 ELE 1 AND 313-01-2020 ------
56REP II11-01-2020 ------
57SERVICE PLAN11-01-2020 ------
58COLLECTION STATEMENT11-01-2020 ------
59CONVEYANCE DEED11-01-2020 ------
60BLOCK 2 ELE 2 AND 4 SEC 1 AND 213-01-2020 ------
61BLOCK 3 5TH 6TH FLOOR PLANS13-01-2020 ------
6229 CASH FLOW STATMENT13-01-2020 ------
63BLOCK 4 TERRACE AND LMR FLOOR PLAN13-01-2020 ------
64PAN CARD11-01-2020 ------
65BASEMENT 3 FLOOR PLAN AREA CALCULATION13-01-2020 ------
66BASEMENT 2 FLOOR PLAN AREA CALCULATION13-01-2020 ------
67ZONING PLAN11-01-2020 ------
68ALLOTTMENT LETTER RESIDENTIAL11-01-2020 ------
69BLOCK 2 AREA CALCULATION AL FLOOR PLAN13-01-2020 ------
70BLOCK 3 SEC AA AND BB13-01-2020 ------
71BLOCK 4 AREA CALCULATION AL FLOOR PLAN13-01-2020 ------
72ENERGY CENTER ELE A SEC 113-01-2020 ------
73BLOCK 2 GF 1ST FLOOR PLANS13-01-2020 ------
74BLOCK 2 6TH 7TH FLOOR PLANS13-01-2020 ------
75DEVELOPMENT WORK PLAN11-01-2020 ------
76BLOCK 4 2ND 3RD 4TH 5TH FLOOR PLANS13-01-2020 ------
77BLOCK 5 SEC AA AND BB13-01-2020 ------
78BLOCK 5 GF 1ST FLOOR PLANS13-01-2020 ------
79NON TOWER SECTION13-01-2020 ------
80ENERGY CENTER AREA CALCULATION AL FLOOR PLAN13-01-2020 ------
81ENARGY CENTER GF 1ST FLOOR PLANS13-01-2020 ------
8219 PROJECT REPORT13-01-2020 ------
83LIST OF DIRECTORS11-01-2020 ------
84RESOLUTION FOR AUTHORISED SIGNATORY11-01-2020 ------
85ADVERTISEMENT11-01-2020 ------
86BLOCK 3 AREA CALCULATION AL FLOOR PLAN13-01-2020 ------
87BLOCK 5 2ND 3RD 4TH FLOOR PLANS13-01-2020 ------
88LOI - 12.13125 ACRES12-02-2020 ------
89COPY OF LICENSE ALONG WITH SCHEDULE OF LAND12-02-2020 View Document
90AIRPORT HEIGHT CLEARANCE NOC12-02-2020 ------












Sr. No.Document DescriptionDate of Document UploadView Document
1 Occupation Certificate 28-07-2023 View Document