Quarterly Schedules

HRERA Gurugram
Project Registration Number : GGM/393/125/2020/09 DATED 10.02.2020
Project Name : GODREJ MERIDIEN PHASE III
Project Number : RERA-GRG-517-2019
Project Type : NEW
S.No.ParticularsAmount
(In Lakhs)
1Cost of the land (if included in the estimated cost)51
2Estimated cost of construction of apartments31874.87
3Estimated cost of infrastructure & other structure947.27
4Other cost including EDC taxes, levies, etc2822
Total2873



Name of the approvalStatusDate
Demarcation PlanHave not applied till dateN/A
Zoning PlanObtained Approval on25-10-2016
Service PlansObtained Approval on25-06-2018
Electricity PlansHave not applied till dateN/A
Site PlansObtained Approval on21-03-2018
Building PlansObtained Approval on21-03-2018
FIre NOCHave not applied till dateN/A
Total Expenditure on the project947
Expenditure made upto the date of Registration0



EDC due as on the date of Registration0

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance14342.09
2Amount collected from allottees against booked plots and/or apartments1069.98
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total15412.07



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc147.15
Total147.15
Balance2725.85



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter41.18034588
2Amount deposited in Escrow Account74.89846756
3Amount withdrawn during the quarter93.367
4Balance at the end of the quarter22.71181344
Total Apartments in the colony428
Apartments sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
11BHK + STUDY (REFUGE0
22BHK1
32BHK TYPE A0
42BHK TYPE B (REFUGE FLOOR)0
52BHK TYPE C0
63BHK + UTILITY TYPE A5
73BHK+UTILITY TYPE B0
83BHK TYPE A8
93BHK TYPE B1
103BHK TYPE C0
113RHK + UTILITY2
124BHK + UTILITY4
13TYPE A - PENTHOUSE A/5 BHK + UTILITY0
14TYPE B - PENTHOUSE B/5 BHK + UTILITY0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NOT AVAILABLE 0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments571
3EDC, IDC, etc835.1
4Others Expenditure19170



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date2992
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-07-2020  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-07-2020  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-07-2020  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-07-2020  View 
5 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-07-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance15412.07
2Amount collected from allottees against booked plots and/or apartments996.86
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total16480.93



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments98.01
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc182.53
Total280.55
Balance1883.45



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter227.1181344
2Amount deposited in Escrow Account697.8049414
3Amount withdrawn during the quarter722.85
4Balance at the end of the quarter202.0730758
Total Apartments in the colony428
Apartments sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
11BHK + STUDY (REFUGE)0
22BHK0
32BHK TYPE A0
42BHK TYPE B (REFUGE FLOOR)0
52BHK TYPE C0
63BHK + UTILITY TYPE A3
73BHK+UTILITY TYPE B0
83BHK TYPE A1
93BHK TYPE B0
103BHK TYPE C0
113RHK + UTILITY2
124BHK + UTILITY1
13TYPE A - PENTHOUSE A/5 BHK + UTILITY1
14TYPE B - PENTHOUSE B/5 BHK + UTILITY2
152BHK0
162BHK TYPE A0
172BHK TYPE B (REFUGE FLOOR)0
182BHK TYPE C0
193BHK + UTILITY TYPE A3
203BHK+UTILITY TYPE B0
213BHK TYPE A1
223BHK TYPE B0
233BHK TYPE C0
243RHK + UTILITY2
254BHK + UTILITY1
26TYPE A - PENTHOUSE A/5 BHK + UTILITY1
27TYPE B - PENTHOUSE B/5 BHK + UTILITY2



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NIL0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0.00
2Apartments669.24
3EDC, IDC, etc835.10
4Others Expenditure0.00



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date835.10
2EDC due as on date0.00
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-10-2020  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-10-2020  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-10-2020  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-10-2020  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-10-2020  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance16408.93
2Amount collected from allottees against booked plots and/or apartments528.81
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total16937.75



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments435.31
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc108.22
Total543.53
Balance3651.93



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter15.1230758000001
2Amount deposited in Escrow Account363.8697107
3Amount withdrawn during the quarter370.51
4Balance at the end of the quarter8.48278650000006
Total Apartments in the colony428
Apartments sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1GODMET4-11011
2GODMET4-04031
3GODMET4-32041
4GODMET7-10021
5GODMET7-06051
6GODMET4-12041
7GODMET4-16041
8GODMET4-15041
9GODMET4-15041



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1NOT APPLICABLE0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments790.66
3EDC, IDC, etc835.10
4Others Expenditure5849.46



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date835.10
2EDC due as on date835.10
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-02-2021  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-02-2021  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-02-2021  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-02-2021  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-02-2021  View