HRERA GurugramTemp Project Id : RERA-GRG-PROJ-458-2019
Submission Date : 16-12-2019 05:34:24 AM
Applicant Type : Company
Project Type: ONGOING




DREAMHOME INFRASTRUCTURE PVT LTD
10TH FLOOR, TOWER D, GLOBAL BUSINESS PARK, MG ROAD, GURUGRAM - 122002
01242803000
9810030178 (Number Shared by Promoter in Public)
sanjay.rastogi@conscient.in
http://www.conscient.in/heritagemax/index.html
XXXX564Q
U70100DL2011PTC215170
 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 







HERITAGE MAX - TOWER F
VILLAGE DHANKOT, SECTOR 102, GURUGRAM
GURGAON
GURUGRAM
01242803000
9810030178 (Number Shared by Promoter in Public)
sanjay.rastogi@conscient.in
SANJAY RASTOGI
01242803000
9810030178 (Number Shared by Promoter in Public)
sanjay.rastogi@conscient.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
153577420-12-2017130000ICICI BANK LIMITEDHRERA Gurugram
253808821-03-201865000ICICI BANK LIMITEDHRERA Gurugram







1.579 (Acre)
78319
100
11.25 (Acre)
104 of 2011 dated 11 Dec 2011
Yes







6701.34 Lakhs
1146 Lakhs
3863.80 Lakhs
1088 Lakhs
603.54 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS390.710
3CONSTRUCTION OF ROADS1501
4PAVEMENTS0
5PARKS AND PLAYGROUNDS2288.60
6GREEN BELTS0
7VEHICLE PARKINGS212.5
8ELECTRICITY SUB-STATION0
9CLUB HOUSE932.302
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES842
12ANY OTHER222.89
Total6390.002




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPYes
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS15.88AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM43.21AS PER PROJECT REPORT
3STORM WATER DRAINAGE27.7AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM342.6AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL6.84AS PER PROJECT REPORT
6STREET LIGHTING1.26AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING28.2AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS15AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE462.4AS PER PROJECT REPORT
10SHOPPING AREA33.8AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM2.58AS PER PROJECT REPORT
12SCHOOL108.8AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT


NA (date)
NA (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type 4BHK142.055138131






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
4BHK38100 % COMPLETE


12-07-2013
31-12-2020
31-12-2020
12-07-2013
55
31-12-2020


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
12-07-2013
55
31-12-2020


102
0
0
17
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments2653.18
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments7199397.06179
Shops0000
Plots0000

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments193.3121.9913.5627.14
Shops0000
Plots0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments27.1427.1427.1427.14
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements15.88
Water Supply System0
Sewerage treatment & garbage disposal6.84
Electricity Supply System66.5
Storm Water Drainage4.76
Parks and Playgrounds5
Clubhouse/community centres462.4
Shopping area20
Other13.84

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System23.111.848.30
Sewerage treatment & garbage disposal0000
Electricity Supply System606083.620
Storm Water Drainage01012.940
Parks and Playgrounds5500
Clubhouse/community centres0000
Shopping area6.96.900
Other56.2612.385

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System18.533.9900
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other6.820.8454.416.32












Particulars Remarks, if any
i. No. of Flats/Apartments constructed51Apartments in Tower F
ii. No. of Flats/ Apartments booked38Tower F
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter6133 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter3150 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter2983 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter0 Lakhs
vii. Amount invested in the project upto the date of application4845 Lakhs
Land cost (If any)1146 Lakhs
Apartments2653.18 Lakhs
Infrastructure595.22 Lakhs
EDC/ Taxes Etc.450.60 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession1856.34 Lakhs
(a) In respect of existing allottees1383.16 Lakhs
(b) In respect of rest of the project473.18 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
1695 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 1856.34 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS15.915.9
II. WATER SUPPLY SYSTEM43.20
III. STORM WATER DRAINAGE27.74.8
IV. ELECTRICITY SUPPLY SYSTEM342.666.5
V. SEWAGE TREATMENT & GARBAGE DISPOSAL6.86.8
VI. CLUB HOUSE/COMMUNITY CENTRE462.4462.4
VII. SCHOOL108.80
VIII. ANY OTHER18.87.58
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING33.820
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.00
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM28.211.3
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
ICICI BANK LIMITED ; BRANCH : SOLITAIRE PLAZA, M.G ROAD, GURUGRAM
245105000304
ICIC0002451
110229222
002451
Lalit Jain, Ajay Kumar Agrawal, Rajesh Agarwal and Sumeet Kumar
Uploaded











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO. 104 OF 2011ALREADY BEEN OBTAINED12-12-2011
II. FOREST NOCALREADY BEEN OBTAINED17-08-2012
III. AIRPORT HEIGHT CLEARANCE ALREADY BEEN OBTAINED27-03-2012
IV. WATER CONNECTIONALREADY BEEN OBTAINED31-07-2017
V. ELECTRICAL LOAD AVAILABILITY ALREADY BEEN OBTAINED12-01-2017
VI. ENVIRONMENTAL CLEARANCE ALREADY BEEN OBTAINED12-07-2013
VII. CONSENT TO ESTABLISH ALREADY BEEN OBTAINED22-05-2014
VIII. FIRE SCHEME APPROVALALREADY BEEN OBTAINED29-12-2012








Yes


Yes


Gist of Important clauses is uploaded seperately







NO OTHER PROJECT LAUNCHED IN LAST 5 YEARS
0
0
0
0
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
000
Cost of the apartments000
Cost of the infrastructure000
Others costs000


0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
12-07-2013
31-12-2020










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEIMPORTED STONE FLOORING IN LIVING & DINNING, WOODEN FLOORING IN BEDROOMS AND TILE IN TOILET, KITCHEN, UTILITY AREA AND BALCONY.
2WALL FINISHING DETAILSINTERNAL PAINT - PLASTIC EMULSION, OBD AND WHITE WASH. TOWER EXTERNAL WALLS - STONE CLADDING UP TO 1ST FLOOR LVL. & EXTERIOR EMULSION PAINT ON REMAINING AREAS.
3KITCHEN DETAILSSTONE COUNTER TOP WITH 2FEET HIGH CERAMIC TILES ABOVE THE COUNTER AND CERAMIC TILE ON FLOOR 396 X 396 MM.
4BATHROOM FITTINGSISI MARKED CP FITTINGS AND FIXTURES.
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESDOOR FRAMES - WOODEN WINDOW FRAMES - UPVC.
7GLASS WORKFIXED GLASS - 4MM, 5 MM
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSPVC CONDUITS WITH PVC INSULATED WIRING.
10CUPBOARD DETAILSNA
11WATER STORAGEUNDERGROUND TANKS (RAW+TREATED + FIRE) + OVERHEAD TANKS (TREATED + FIRE )
12LIFT DETAILSTOTAL 17 NOS LIFTS , 07 ARE STRETCHER LIFTS AND 10 ARE PASSENGER LIFTS.
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSUPVC GLAZED WINDOW.
14DOORSDOOR FRAMES - RED MARANTI SEASONED WOOD WITH ANTI-TERMITE & BLACK JAPAN DOOR SHUTTERS - COMMERCIAL FLUSH DOOR SHUTTER FINISHED WITH PAINT AND POLISH.
14.1MAIN DOORSDOOR FRAMES - RED MARANTI SEASONED WOOD WITH ANTI-TERMITE & BLACK JAPAN. SHUTTER - DOOR SHUTTER WITH MASONITE HDF SKIN WITH POLISH.
14.2INTERNAL DOORSDOOR FRAMES - RED MARANTI SEASONED WOOD WITH ANTI-TERMITE & BLACK JAPAN. SHUTTER - FLUSH DOOR SHUTTER WITH BOTH SIDE ENAMEL PAINT.
15AIR CONDITIONINGSPLIT AC
16ELECTRICAL FITTINGSISI MARKED
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYWIFI - NOT PROVIDED. BROADBAND FACILITY - PROVIDED.
19EXTERNAL FINISHING/COLOUR SCHEMETOWER EXTERNAL WALLS - STONE CLADDING UP TO 1ST FLOOR LVL. & REMAINING EXTERIOR EMULSION PAINT.
20INTERNAL FINISHINGPLASTIC EMULSION, OBD, ENAMEL & WHITE WASH.
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORIMPORTED STONE FLOORING.
1 . 2 WALLSPLASTIC EMULSION PAINT.
1 . 3 CEILINGPLASTIC EMULSION PAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORWOODEN FLOORING
2 . 2 WALLSPLASTIC EMULSION PAINT
2 . 3 CEILINGPLASTIC EMULSION PAINT
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILE - 396 X 396 MM
3 . 2 WALLSCERAMIC TILE - 396 X 396 MM UP TO THE BOTTOM OF GRID CEILING AND REMAINING AREA WHITE WASH.
3 . 3 CEILINGGRID CEILING.
3 . 4 COUNTERSCOMPOSITE STONE COUNTER.
3 . 5 SANITARY WARE/CP FITTINGSWASH BASIN , WC,SHOWER,DIVERTOR, DUAL FLUSH CISTERN, SPOUT, HEALTH FAUCET, ANGLE VALVE.
3 . 6 FITTING/FIXTURESISI MARKED FITTING / FIXTURES.
4 . BED ROOMS
4 . 1 FLOORWOODEN FLOORING
4 . 2 WALLSPLASTIC EMULSION PAINT.
4 . 3 CEILINGPLASTIC EMULSION PAINT.
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOOR396 X 396 MM CERAMIC TILE
5 . 2 WALLSCERAMIC TILE - 396 X 396 MM UP TO THE BOTTOM OF GRID CEILING AND REMAINING AREA WHITE WASH.
5 . 3 CEILINGGRID CEILING
5 . 4 COUNTERSGRANITE STONE COUNTER.
5 . 5 SANITARY WARE/CP FITTINGSWASH BASIN , WC,SHOWER,DIVERTOR, DUAL FLUSH CISTERN, SPOUT, HEALTH FAUCET,ANGLE VALVE.
5 . 6 FIXTURESISI MARKED FITTING / FIXTURES.
6 . KITCHEN
6 . 1 FLOOR396 X 396 CERAMIC TILE
6 . 2 WALLSCERAMIC TILE - 396 X 396 MM UP TO 2 FEET HIGH ABOVE COUNTER AND REMAINING AREA PLASTIC EMULSION PAINT.
6 . 3 CEILINGPLATIC EMULSION PAINT
6 . 4 COUNTERSGRANITE STONE COUNTER.
6 . 5 FIXTURESISI MARKED FITTING / FIXTURES
6 . 6 KITCHEN APPLIANCESHOB AND HOOD
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILE - 300 X 300 MM
7 . 2 WALLS & CEILINGOBD PAINT ON WALL & CEILING
7 . 3 TOILETFLOOR - 300 X 300 MM CERAMIC TILE. WALL - 300 X 300 MM CERAMIC TILE UP TO 1.0 MTR HEIGHT AND REST IS OBD. CEILING - OBD PAINT.
7 . 4 BALCONYFLOOR - 300 X 300 MM CERAMIC TILE. RAILING - M.S. RAILING WITH GLASS. CEILING - EXTERIOR EMULSION PAINT.
8 . SIT-OUTS
8 . 1 FLOORTILES, STONES
8 . 2 WALLS & CEILINGPAINT
8 . 3 RAILINGSMS RAILING
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1FLOOR PLAN & AREA DIAGRAM BLK-B, A-1722-02-2020 ------
2SECTION BLK-F, A-3622-02-2020 ------
3SITE PLAN PARKING CALCULATION A-0222-02-2020 ------
4ELEVATION BLK-F, A-3422-02-2020 ------
5SECTION BLK-A, A-1622-02-2020 ------
6SITE PLAN22-02-2020 ------
7ELEVATION BLK-E A-3122-02-2020 ------
8FLOOR PLAN & AREA DIAGRAM BLK-A, A-1222-02-2020 ------
9ELEVATION BLK-E, A-3022-02-2020 ------
10DEMARCATION PLAN22-02-2020 View Document
11ELEVATION BLK-B A-2122-02-2020 ------
12SECTION BLK-E, A-3222-02-2020 ------
13ELEVATION BLK C & D A-2722-02-2020 ------
14FLOOR PLAN, AREA DIAGRAM BLK-E A-29A22-02-2020 ------
15SECTION BLK C & D A-2822-02-2020 ------
16FLOOR PLAN, AREA DIAGRAM BLK C & D A-2422-02-2020 ------
17SITE PLAN A-0122-02-2020 ------
18FLOOR PLAN & AREA DIAGRAM BLK-A, A-1322-02-2020 ------
19FLOOR PLAN, AREA DIAGRAM BLK-E A-29B22-02-2020 ------
20ELEVATION BLK-F A-3522-02-2020 ------
21BASEMENT-2 FLOOR PLAN-A-0422-02-2020 ------
22SERVICE PLAN DRAWING-IRRIGATION SYSTEM22-02-2020 ------
23FLOOR PLAN & AREA DIAGRAM BLK-A, A-1122-02-2020 ------
24SERVICE PLAN DRAWING-SEWER LAYOUT22-02-2020 ------
25SECTION ELEVATION- EWS A-3822-02-2020 ------
26FLOOR PLAN, AREA DIAGRAM BLK-F A-33B22-02-2020 ------
27FLOOR PLANS, SEC, ELEV. N.SCHOOL.A-4122-02-2020 ------
28LC-IV22-02-2020 ------
29SERVICE PLAN DRAWING-STORM WATER22-02-2020 ------
30FLOOR PLAN, AREA DIAGRAM BLK-F A-33A22-02-2020 ------
31ELEVATION BLK-A, A-1522-02-2020 ------
32PLAN SECTION ELEVATION- B WALL A-0522-02-2020 ------
33LOI22-02-2020 ------
34SERVICE PLAN DRAWING- FIRE FIGHTING22-02-2020 ------
35SERVICE PLAN APPROVAL LETTER22-02-2020 ------
36SERVICE PLAN ESTIMATE22-02-2020 ------
37BASEMENT-I FLOOR PLAN A-0322-02-2020 ------
38ELEVATION BLK-A, A-1422-02-2020 ------
39ELEVATION BLK-B A-2022-02-2020 ------
40FLOOR PLAN, AREA DIAGRAM BLK C & D A-2322-02-2020 ------
41ELEVATION BLK-C & D A-2622-02-2020 ------
42FLOOR PLAN, AREA DIAGRAM BLK C & D A-2522-02-2020 ------
43SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN22-02-2020 View Document
44COPY OF LICENSE ALONG WITH SCHEDULE OF LAND12-12-2019 View Document
45IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN12-12-2019 View Document
46NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT12-12-2019 View Document
47CONSENT TO ESTABLISH DATED 22.05.14 12-12-2019 ------
48DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.12-12-2019 View Document
49AIRPORT AUTHORITY APPROVAL DATED 27.03.1212-12-2019 ------
50CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT16-12-2019 View Document
51ARAVALI NOC DATED 02.05.1412-12-2019 ------
52ENVIRONMENT CLEARANCE DATED 12.07.1312-12-2019 ------
53A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS12-12-2019 View Document
54FIRE SCHEME APPROVAL DATED 29.12.1212-12-2019 ------
55ELECTRICITY LOAD SANCTION DATED 12.01.1712-12-2019 ------
56FOREST NOC DATED 17.08.1212-12-2019 ------
57WATER CONNECTION DATED 31.07.1712-12-2019 ------
58IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN12-12-2019 View Document
59GIST OF IMPORTANT PROVISIONS OF BUYERS AGREEMENT16-12-2019 ------
60CASH FLOW STATEMENT OF THE PROPOSED PROJECT16-12-2019 View Document
61FLOOR PLAN, AREA DIAGRAM EWS, A-3722-02-2020 ------
62FLOOR PLAN & AREA DIAGRAM BLK-B, A-1822-02-2020 ------
63SECTION BLK-B A-2222-02-2020 ------
64FLOOR PLANS, SEC, ELEV. COMMRL.BLDG.A-4022-02-2020 ------
65FLOOR PLAN & AREA DIAGRAM BLK-B, A-1922-02-2020 ------