| 24-Dec-2025 |
272.8 |
Continuation of registration of project under section 7(3) of the RERA Act. 2016. FBD Real Grow Pvt. Ltd. |
Adjourned |
--- |
| 08-Oct-2025 |
272.8 |
Continuation of registration of project under section 7(3) of the RERA Act. 2016. FBD Real Grow Pvt. Ltd. |
Adjourned |
View Order |
| 30-Jul-2025 |
272.8 |
Continuation of registration of project under section 7(3) of the RERA Act. 2016. FBD Real Grow Pvt. Ltd. |
Adjourned |
View Order |
| 23-Apr-2025 |
272.8 |
Continuation of registration of project under section 7(3) of the RERA Act. 2016. FBD Real Grow Pvt. Ltd. |
Adjourned |
View Order |
| 05-Feb-2025 |
272.8 |
Continuation of registration of project under section 7(3) of the RERA Act. 2016. FBD Real Grow Pvt. Ltd. |
Adjourned |
View Order |
| 11-Dec-2024 |
272.8 |
Continuation of registration of project under section 7(3) of the RERA Act. 2016. FBD Real Grow Pvt. Ltd. |
First Hearing |
View Order |
| 12-Feb-2024 |
235.13 |
First Extension of registration under Section-6 of RERA Act, 2016. |
Adjourned |
--- |
| 12-Feb-2024 |
232.7 |
First Extension of registration under Section-6 of RERA Act, 2016. |
Adjourned |
--- |
| 12-Feb-2024 |
232.7 |
First Extension of registration under Section-6 of RERA Act, 2016. |
Adjourned |
--- |
| 11-Dec-2023 |
235.13 |
First Extension of registration under Section-6 of RERA Act, 2016. |
First Hearing |
View Order |
| 06-Nov-2023 |
232.7 |
First Extension of registration under Section-6 of RERA Act, 2016. |
First Hearing |
View Order |