HRERA GurugramTemp Project Id : RERA-GRG-PROJ-2141-2025
Submission Date : 22-12-2025 01:40:06 PM
Applicant Type : Company
Project Type: ONGOING




SIGNATTUREGLOBAL HOMES LIMITED
UNIT NO.101,GROUND FLOOR, TOWER-A, SIGNATURE TOWER SOUTH CITY-1, GURUGRAM, HARAYNA-122001
911244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
Https://www.signatureglobal.in
XXXX888R
U70100DL2008PLC176641
 
 


 
 


 
 


 
 







SIGNATURE GLOBAL PARK-I (2)
VILLAGE-DUNELA, SECTOR-36, SOHNA, GURUGRAM
SOHNA
GURUGRAM
911244908200
9250785681 (Number Shared by Promoter in Public)
compliance@sigantureglobal.in
RAVI AGGARWAL
911244908200
9250785681 (Number Shared by Promoter in Public)
compliance@signatureglobal.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
139642390968131-01-202618ICICI BANKHRERA Gurugram
25352007920218-12-2025116434YES BANKHRERA Gurugram







1.031 (Acre)
2.64
2.64
5 (Acre)
18 of 2021 Dated 16.04.2021
Yes







8168.27 Lakhs
485.31 Lakhs
6000 Lakhs
0 Lakhs
1682.96 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0.971
3CONSTRUCTION OF ROADS 0.06
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
Total1.031




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVP (CONNECTED)No
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVP (OWN ARRANGEMENT)No




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS0YET TO BE PREPARED
2WATER SUPPLY SYSTEM0YET TO BE PREPARED
3STORM WATER DRAINAGE0YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL0YET TO BE PREPARED
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


19-11-2024 (date)
15-12-2022 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartments Total number of plots/apartments in the project Total size of the plots/carpet area of the apartments Plots/apartments booked/ sold upto the date of application Yet to be sold/ booked No. of towers to be/ being constructed for booked apartments
1 APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-M1 35.25 16 564 7 9 4
2 APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-M2 64.24 8 513.92 0 8 2
3 APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-B 64.86 100 6486 98 2 25
4 APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-A 89.06 20 1781.2 19 1 5
Total1449345.121242036






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
TYPE M17PERT CHART ATTACHED
TYPE M20PERT CHART ATTACHED
TYPE-B98PERT CHART ATTACHED
TYPE-A19PERT CHART ATTACHED


01-01-2023
30-03-2026
30-03-2026
01-01-2023
32
30-03-2026
ATTACHED
ATTACHED


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
01-01-2023
32
30-12-2025
ATTACHED
ATTACHED


0
144
0
0
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments1940.89
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0002000
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2059.11000
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter (2027)
Apr-JuneJuly-SepOct-DecJan-Mar












Particulars Remarks, if any
i. No. of Flats/Apartments constructed144
ii. No. of Flats/ Apartments booked124
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter12698.19 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter9584.74 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter4773.89 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter4773.89 Lakhs
vii. Amount invested in the project upto the date of application3585.88 Lakhs
Land cost (If any)485.31 Lakhs
Apartments1940.89 Lakhs
Infrastructure0 Lakhs
EDC/ Taxes Etc.1159.68 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession4582.39 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS00
II. WATER SUPPLY SYSTEM00
III. STORM WATER DRAINAGE00
IV. ELECTRICITY SUPPLY SYSTEM00
V. SEWAGE TREATMENT & GARBAGE DISPOSAL00
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.00
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
STANDARD CHARTERED BANK LIMITED, DLF GURGAON BUILDING NO. 7A, GROUND FLOOR, DLF CYBER CITY, PHASE-3, SECTOR 24/25/25A, GURUGRAM, HARYANA-122002
53105107527
SCBL0036025
110036006
036025
Master collection account namely Signatureglobal Home Pvt Ltd SG Park II Collection A/c will be operated by Mr. Pradeep Kumar Aggarwal and Lalit Aggarwal R/o Aashirwad, Palam Farm 6, Salahapur, Bijwasan, South West Delhi-110061
Attached











Yes
Yes
Yes
Yes
Yes
Yes
No
No
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO. 18 OF 2021ALREADY BEEN OBTAINED16-04-2021
II. LOIALREADY BEEN OBTAINED29-10-2020
III. LC-IVALREADY BEEN OBTAINED16-04-2021
IV. LAYOUT PLANALREADY BEEN OBTAINED19-11-2024
V. DEMARCATION CUM ZONING ALREADY BEEN OBTAINED17-12-2024
VI. ENVIRONMENT CLEARANCE (EC)ALREADY BEEN OBTAINED07-12-2021
VII. FOREST NOCALREADY BEEN OBTAINED13-11-2020
VIII. SPEALREADY BEEN OBTAINED13-02-2023
IX. ELECTRICAL LOAD AVAILABILTYALREADY BEEN OBTAINED13-02-2023
X. BUILDING PLAN APPROVALALREADY BEEN OBTAINED15-12-2022
XI. BUILDING PLAN APPROVALALREADY BEEN OBTAINED28-01-2025








Yes


Yes


As per RERA norms







SIGNATURE GLOBAL PARK-I (1), LOCATEDAT VILLAGE-DUNELA, SEC-36, GURUGRAM
3.91
116
0
115
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
7986.2605341.78
Cost of the apartments480002929.99
Cost of the infrastructure472.9000
Others costs2713.3602411.70


6680.92 Lakhs
98.74 Lakhs
0 Lakhs
0 Lakhs
No
29-10-2026
29-10-2026




SIGNATURE GLOBAL PARK-II, LOCATED ATVILLAGE-DUNELA, SEC-36, GURUGRAM
8.26
368
0
368
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
13940.49013940.49
Cost of the apartments849708500.97
Cost of the infrastructure1022.6001022.58
Others costs4420.8904416.94


16402.35 Lakhs
1601.42 Lakhs
0 Lakhs
0 Lakhs
No
30-12-2023
30-12-2023




SIGNATURE GLOBAL PARK-III, LOCATED ATVILLAGE-DUNELA, SEC-36, GURUGRAM
4.74
224
0
208
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
8615.5608621.25
Cost of the apartments507605075.93
Cost of the infrastructure597.700597.70
Others costs2941.8602947.62


9993.07 Lakhs
1259.49 Lakhs
0 Lakhs
0 Lakhs
No
30-12-2023
30-12-2023




SIGNATURE GLOBAL PARK-III EXT. (PHASE-1), LOCATED AT VILLAGE-DUNELA, SEC-36,GURUGRAM
3.35
152
0
152
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
4466.5904145.17
Cost of the apartments240002785.6
Cost of the infrastructure384.1300
Others costs1682.4601359.57


6374.28 Lakhs
351.09 Lakhs
0 Lakhs
0 Lakhs
No
29-12-2025
29-12-2025










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSE KAJARIA/ORIENT BELL/SIMPOLO/SOMANY OR EQUIVALENT
2WALL FINISHING DETAILS KAJARIA/ORIENT BELL/SIMPOLO/SOMANY OR EQUIVALENT
3KITCHEN DETAILS OPEN KITCHEN
4BATHROOM FITTINGS AS PER ISI STANDARD
5WOOD WORK ETC RED MERANDI / HARDWOOD FRAME
6DOORS AND WINDOS FRAMES LAMINATED FLUSH DOOR SHUTTER & RED MERANDI / HARDWOOD FRAME
7GLASS WORK AS / VENDOR SELECTION
8ELECTRIC FITTINGS AS PER ISI STANDARD
9CONDUCTING AND WIRING DETAILSISI, HMS
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSBRANDED MAKE
13EXTERNAL GLAZINGSUPVC / ALUMINIUM
13.1WINDOWS/GLAZINGSUPVC / ALUMINIUM
14DOORS LAMINATED FLUSH DOOR SHUTTER & RED MERANDI / HARDWOOD FRAME
14.1MAIN DOORS LAMINATED FLUSH DOOR
14.2INTERNAL DOORS LAMINATED FLUSH DOOR
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGS AS PER ISI STANDARD
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED / CERAMIC TILE
1 . 2 WALLSOBD PAINT
1 . 3 CEILINGOBD PAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED / CERAMIC TILE
2 . 2 WALLSOBD PAINT
2 . 3 CEILINGOBD PAINT
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORVITRIFIED / CERAMIC / ANTISKID TILE
3 . 2 WALLSOBD PAINT
3 . 3 CEILINGOBD PAINT
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORVITRIFIED / CERAMIC TILE
4 . 2 WALLSOBD PAINT
4 . 3 CEILINGOBD PAINT
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORVITRIFIED / CERAMIC / ANTISKID TILE
5 . 2 WALLSOBD PAINT
5 . 3 CEILINGOBD PAINT
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORVITRIFIED / CERAMIC TILE
6 . 2 WALLSOBD PAINT
6 . 3 CEILINGOBD PAINT
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORVITRIFIED / CERAMIC TILE
7 . 2 WALLS & CEILINGOBD PAINT
7 . 3 TOILETVITRIFIED / CERAMIC / ANTISKID TILE
7 . 4 BALCONYVITRIFIED / CERAMIC / ANTISKID TILE
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 22-12-2025 View Document
2 DEMARCATION PLAN 22-12-2025 View Document
3 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 22-12-2025 View Document
4 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 22-12-2025 View Document
5 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 22-12-2025 View Document
6 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 22-12-2025 View Document
7 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 22-12-2025 View Document
8 ZONING PLAN 22-12-2025 View Document
9 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 22-12-2025 View Document
10 JAMBANDI-MUTATION 16-7-25 16-04-2026 View Document
11 PLOT M1B & M1D 16-04-2026 View Document
12 PROJECT REPORT PARK 1 (2) FLOORS 16-04-2026 View Document
13 SG PARK 1 REVALIDATION TYPE A, B- 61 PLOTS_29 OCT 2024 16-04-2026 View Document
14 SALE DEED 16-04-2026 View Document
15 AFFIDAVIT FROM DIRECTOR 16-04-2026 View Document
16 SG PARK 1 EXT APPROVED DEMARCATION 16-04-2026 View Document
17 PLOT M2A 16-04-2026 View Document
18 TYPE-B+ 16-04-2026 View Document
19 LOI 16-04-2026 View Document
20 TYPE-B_ 16-04-2026 View Document
21 CA CERTIFICATE FOR LAND COST AND COST INCURRED 16-04-2026 View Document
22 PLOT M1A & M1C 16-04-2026 View Document
23 PLOT M2B 16-04-2026 View Document
24 SIZRA 16-07-25 16-04-2026 View Document
25 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 16-04-2026 View Document
26 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 16-04-2026 View Document
27 TYPE A 16-04-2026 View Document
28 TYPE A_ 16-04-2026 View Document
29 TYPE B 16-04-2026 View Document
30 TYPE-B 16-04-2026 View Document
31 NON ENCUMBRANCE-LIC-18 DT 17-07-25 16-04-2026 View Document
32 REVNEUE INFOR LIC 18 16-04-2026 View Document
33 AFFIDAVIT FOR 2 PLOTS 16-04-2026 View Document
34 AFFIDAVIT FOR NO LOAN PARK 1 (2) 16-04-2026 View Document
35 APPROVED LAYOUT PARK-1 EXT 16-04-2026 View Document
36 CA CERTIFICATE FOR NETWORTH 16-04-2026 View Document
37 DEMARCATION CUM ZONING PLAN 16-04-2026 View Document
38 LC-IV-5 ACRES-HOMES 16-04-2026 View Document
39 NOC_S UNDERTAKING 16-04-2026 View Document
40 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 16-04-2026 View Document