HRERA GurugramTemp Project Id : RERA-GRG-PROJ-805-2021
Submission Date : 05-02-2021 02:24:55 PM
Applicant Type : Firm
Project Type: ONGOING


GODREJ HIGHVIEW LLP
3RD FLOOR, UM HOUSE, TOWER A, PLOT 35, SECTOR 44 GURUGRAM
01244956150
9219315299 (Number Shared by Promoter in Public)
natureplus1rera@godrejproperties.com
AAH5060
AAQFG1519A













GODREJ NATURE PLUS
SECTOR 33, SOHNA, GURGAON
SOHNA
GURUGRAM
01244956150
9219315299 (Number Shared by Promoter in Public)
natureplus1rera@godrejproperties.com
DEEPENDRA SINGH
01244956150
9219315299 (Number Shared by Promoter in Public)
deependra.singh@godrejproperties.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques/Online Banking:-

Drafts/ Banker’s Cheques

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
151411624-02-2021598496ICICI BANKHRERA Gurugram
251411724-02-2021591372ICICI BANKHRERA Gurugram
351411824-02-20211496240ICICI BANKHRERA Gurugram
451411908-03-2021647496ICICI BANKHRERA Gurugram

Online Banking








18.744 (Acre)
1.750
1.747
18.744 (Acre)
DTCP granted Licence no. 01 of 2014 dated 03.01.2014 (02.01.2025)
No
Address     902 A , 9TH FLOOR D-MALL, NETA JI SUBHASH PLACE PIATMPURA NEW DELHI, 110034
Annexure-B- DEVELOPMENT AGREEMENT AND POA ADDED IN FOLDER B
AFTER THE GRANT OF LICENSE
Yes
GENERAL POWER OF ATTORNEY DATED 22.09.2017 BEARING DOCUMENT NO. 71 REGISTERED AT TEHSIL SOHNA DEVELOPMENT AGREEMENT DATED 22.09.2017 BEARING NUMBER 2224 REGISTERED WITH TEHSIL SOHNA.
No
Yes
Yes







97749.0 Lakhs
8212.3 Lakhs
41983.3 Lakhs
8846.08 Lakhs
38691.39 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 10295.54
3CONSTRUCTION OF ROADS 0
4PAVEMENTS 14239.37
5PARKS AND PLAYGROUNDS 38321.61
6GREEN BELTS 0
7VEHICLE PARKINGS 5107
8ELECTRICITY SUB-STATION 194.56
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
13COMMERCIAL 356.189
14COMMUNITY FACILITY 2336.47
15NURSERY SCHOOL 809.37
16PRIMARY SCHOOL 4046.85
17AV ROOM 58.83
18RAIN WATER HARVESTING 88.37
Total75854.159




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDA/GMDAYes
WATER SUPPLYHUDA/GMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHUDA/GMDAYes
STORM WATER DRAINAGEHUDA/GMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS1092.95AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM373.75AS PER PROJECT REPORT
3STORM WATER DRAINAGE120.78AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM2704.65AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL310.28AS PER PROJECT REPORT
6STREET LIGHTING71.92AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING2052.37AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS454.50AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0AS PER PROJECT REPORT
15RENEWABLE ENERGY SYSTEM21.07AS PER PROJECT REPORT
16PARKING162.42AS PER PROJECT REPORT
17STP94.82AS PER PROJECT REPORT
18UNDERGROUND WATER TANK134.38AS PER PROJECT REPORT
19RAIN WATER HARVESTING66.37AS PER PROJECT REPORT
20ELECTRICAL SUB STATION154.21AS PER PROJECT REPORT
21HORTICULTURE14.11AS PER PROJECT REPORT


29-01-2021 (date)
29-01-2021 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartments Total number of plots/apartments in the project Total size of the plots/carpet area of the apartments Plots/apartments booked/ sold upto the date of application Yet to be sold/ booked No. of towers to be/ being constructed for booked apartments
1 APARTMENT/SHOPS/OTHER BUILDINGS Type 2BHK-TYPE A 6867.84 96 659312.64 0 96 2
2 APARTMENT/SHOPS/OTHER BUILDINGS Type 2BHK-TYPE C 3657 50 182850 0 50 2
3 APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK 9018 100 901800 0 100 2
4 APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK 181.02 2 362.04 0 2 2
5 APARTMENT/SHOPS/OTHER BUILDINGS Type 2BHK SUITE WITH PRIVATE DECK / TERRACE 366.80 4 1467.2 0 4 2
6 APARTMENT/SHOPS/OTHER BUILDINGS Type 2BHK WITH PRIVATE DECK / TERRACE 4341.68 56 243134.08 30 26 5
7 APARTMENT/SHOPS/OTHER BUILDINGS Type 2BHK 16816.80 220 3699696 192 28 5
8 APARTMENT/SHOPS/OTHER BUILDINGS Type 2BHK-TYPE B 3311.44 44 145703.36 0 44 2
9 APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK + UTILITY 12318.84 114 1404347.76 0 114 3
10 APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK 9577.44 108 1034363.52 0 108 3
11 APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK/3RHK WITH UTILITY TYPE - A 10339.20 96 992563.2 82 14 2
12 APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK/3RHK WITH UTILITY TYPE - B 4494.0 42 188748 40 2 2
13 APARTMENT/SHOPS/OTHER BUILDINGS Type 3RHK(2BED ROOM WITH KIDS/STUDY/UTILITY ROOM) 13760 160 2201600 128 32 5
14 APARTMENT/SHOPS/OTHER BUILDINGS Type 3RHK 158.38 2 316.76 0 2 2
Total109411656264.5647262239






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
2BHK 192ANNEXED
2BHK WITH PRIVATE DECK / TERRACE30ANNEXED
3BHK/3RHK WITH UTILITY (TYPE - A)82ANNEXED
3BHK/3RHK WITH UTILITY (TYPE - B)40ANNEXED
3RHK (2BED ROOM WITH KIDS/STUDY/UTILITY ROOM)128ANNEXED
2BHK WITH PRIVATE DECK / TERRACE30ANNEXED
3BHK/3RHK WITH UTILITY (TYPE - A)82ANNEXED
3BHK/3RHK WITH UTILITY (TYPE - B)40ANNEXED
3RHK (2BED ROOM WITH KIDS/STUDY/UTILITY ROOM)128ANNEXED
COMMERCIAL19ANNEXED


28-02-2018
30-01-2028
30-01-2026
14-08-2018
28
30-01-2026
WE ARE LAUNCHING SOME NEW TOWERS AND WITH GREATER TRACTION IN REAL ESTATE POST COVID-19 SENTIMENTS, WE EXPECT A GREAT LAUNCH. OUR CURRENT SOLD INVENTORY OF LAUNCH TOWERS IS AN IMPRESSIVE 82 %, THUS GIVING US A HEALTHY CASHFLOW. OUR CONSTRUCTION IS GOING AT A GREAT PACE AND WE EXPECT TO COMPLETE THE ENTIRE SUPERSTRUCTURE OF LAUNCHED TOWERS BY JAN-22. THE MICRO MARKET IS GAINING FURTHER TRACTION DUE TO GREAT INFRASTRUCTURE DEVELOPMENT (EXPANSION OF SOHNA ROAD OF 160MTR WIDE 8 LANES, 5KM ELEVATED CORRIDOR FROM SUBHASH CHAUK.


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
10-01-2022
0
30-09-2025
NA
NA


235
0
1000
415
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments7216.74
Shops0
Plots0
Cost of Construction of Community15.20
EDC5897.0
IDC542.98
Land Cost1920.8
Other Cost4714.36

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1159115911592318
Shops0000
Plots0000
Other Cost1445144514451445

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2318231823182318
Shops0000
Plots0000
Cost of Construction of Community201201201201
Land Cost483566301
Other Cost144514451445144555555
IDC2929

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2318173817381738
Shops0000
Plots0000
Other Cost1445144514451445
Land Cost460522522522
Cost of Construction of Community201
IDC29

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1738173817381738
Shops0000
Plots0000
Land Cost627627627279
Other Cost1445144514451445

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1738173817380
Shops0000
Plots0000
Other Cost144514451445
Land Cost279209269

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System17
Sewerage treatment & garbage disposal0
Electricity Supply System93
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres15.2
Shopping area0
Other0
Security and Fire Fighting57

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Underground Water Tank18.81
STP13.27

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements036.9437.9632.95
Water Supply System04.3527.6820.19
Sewerage treatment & garbage disposal15.5115.5127.9315.51
Electricity Supply System0461.2460.0152.0
Storm Water Drainage0012.0812.08
Parks and Playgrounds039.8159.8970.50
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Light3.563.563.05
Electrical Sub Station22.1122.1133.94
Parking10.8313.6932.32
Underground Water Tank20.1617.4745.9216.13
STP15.1711.3839.1615.83
Security and Fire Fighting45.8943.9068.23
Rain Water Harvesting21.9022.64
Horticulture0.79

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements38.3819.8898.3732.79
Water Supply System26.5420.6820.3727.47
Sewerage treatment & garbage disposal31.0331.0331.033.10
Electricity Supply System313.40154.0900
Storm Water Drainage12.0812.0812.080
Parks and Playgrounds31.82104.1462.030
Clubhouse/community centres0000
Shopping area0000
Other0000
Electrical Sub Station44.7231.3300
Parking27.74000
Horticulture1.011.051.181.18
Rain Water Harvesting0000
Underground Water Tank16.13000
STP0000
Security and Fire Fighting75.1129.2288.59492.89
Renewable Energy System2.117.022.110
Street Light2.06000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements37.9658.26185.80142.08
Water Supply System26.5420.6820.3735.18
Sewerage treatment & garbage disposal31.0315.5131.0315.51
Electricity Supply System261.12182.82156.70104.47
Storm Water Drainage0012.0812.08
Parks and Playgrounds00031.82
Clubhouse/community centres0000
Shopping area0000
Other0000
Parking005.6237.69
Horticulture1.291.311.311.31
Rain Water Harvesting0000
Underground Water Tank0000
STP0000
Security and Fire Fighting233.72159.63299.31159.63
Renewable Energy System02.111.472.11
Street Light010.078.6310.79
Electrical Sub Station0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements185.80185.4000
Water Supply System41.3565.4100
Sewerage treatment & garbage disposal15.5131.0300
Electricity Supply System104.47261.1700
Storm Water Drainage12.0824.1600
Parks and Playgrounds31.8222.7300
Clubhouse/community centres0000
Shopping area0000
Other0000
Renewable Energy System2.112.1100
Street Light10.0720.1400
Electrical Sub Station0000
Parking34.530
Horticulture1.311.3100
Underground Water Tank0000
Rain Water Harvesting21.90000
STP0000
Security and Fire Fighting79.81219.4900

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000








Cash Flow in each quarter (In Lakhs)












Particulars Remarks, if any
i. No. of Flats/Apartments constructed578
ii. No. of Flats/ Apartments booked491
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter42248.07 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter14415.83 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter27832.24 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter100.53 Lakhs
vii. Amount invested in the project upto the date of application20474.8 Lakhs
Land cost (If any)1920.8 Lakhs
Apartments7216.74 Lakhs
Infrastructure167.00 Lakhs
EDC/ Taxes Etc.11170.00 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession77257.00 Lakhs
(a) In respect of existing allottees27835.0 Lakhs
(b) In respect of rest of the project58157.0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
20480.17 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 832.17 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS1092.950
II. WATER SUPPLY SYSTEM373.7517
III. STORM WATER DRAINAGE120.780
IV. ELECTRICITY SUPPLY SYSTEM2704.6593
V. SEWAGE TREATMENT & GARBAGE DISPOSAL310.280
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.454.500
XIII. COVERED PARKING162.420
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT3063.7557









Yes
Yes
Account Details
ICICI DLF QUTUB PLAZA, DLF PHASE 1, GURGAON , 122002
017705010059
ICIC0000177
110229030
0177
Mr. Sushil Kumar Sharma, BAH (391), Mandi Himachal Pradesh – 175049
Attached











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. ELECTRICITY ASSURANCE ALREADY BEEN OBTAINED17-10-2014
II. WATER ASSURANCE ALREADY BEEN OBTAINED27-09-2017
III. SEWERAGE ASSURANCE ALREADY BEEN OBTAINED27-09-2017
IV. FIRE SCHEMEALREADY BEEN OBTAINED26-03-2021
V. OLD BUILDING PLANALREADY BEEN OBTAINED11-11-2014
VI. MINING PERMISSION ALREADY BEEN OBTAINED13-11-2017
VII. MINING RENEWAL PERMISSION ALREADY BEEN OBTAINED25-10-2019
VIII. MINING RENEWAL PERMISSION ALREADY BEEN OBTAINED04-02-2020
IX. ENVIRONMENT CLEARANCE ALREADY BEEN OBTAINED20-04-2021
X. CTE ALREADY BEEN OBTAINED05-02-2018
XI. SERVICE PLAN ESTIMATES ALREADY BEEN OBTAINED06-04-2021
XII. REVISED BUILDING PLAN ALREADY BEEN OBTAINED29-01-2021
XIII. LOIALREADY BEEN OBTAINED21-06-2013
XIV. LICENCE ALREADY BEEN OBTAINED03-01-2014
XV. ZONING PLAN ALREADY BEEN OBTAINED06-01-2014
XVI. CHANGE OF DEVELOPER ALREADY BEEN OBTAINED31-10-2017
XVII. FOREST NOC ALREADY BEEN OBTAINED07-02-2013
XVIII. ARAVALI NOC ALREADY BEEN OBTAINED04-03-2014
XIX. AAI ALREADY BEEN OBTAINED11-09-2014
XX. HUDA NOC FOR CONSTRUCTIONALREADY BEEN OBTAINED17-10-2014
XXI. AAI RENEWALALREADY BEEN OBTAINED06-09-2019








Yes


Yes


Possession Date as per RERA Certificate













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSETOWER E,F,G,H,J,T3&T4; I. LIVING ROOM & DINING ROOM-VITRIFIED TILES BED ROOMS-LAMINATED WOODEN FLOOR TOILETS WITH BEDROOMS-ANTI SKID CERAMIC TILE KITCHEN-VITRIFIED TILES BALCONY-ANTI SKID TILES UTILITY ROOM-CERAMIC TILES TOWER A,B,C,D1&D2; I. LIVING ROOM & DINING ROOM-VITRIFIED TILES ,BED ROOMS-LAMINATED WOODEN FLOOR TOILETS WITH BEDROOMS-VITRIFIED TILES KITCHEN-VITRIFIED TILES BALCONY-ANTI SKID CERAMIC TILES UTILITY ROOM-ANTI SKID CERAMIC TILES
2WALL FINISHING DETAILSTOWER E,F,G,H,J,T3&T4; LIVING ROOM & DINING ROOM,BEDROOMS-ACRYLIC EMULSION TOILETS WITH BEDROOMS-CERAMIC TILES TILL 7'-0" ON ALL SIDES KITCHEN-CERAMIC TILES 2'-0" ABOVE COUNTER. UTILITY ROOM-OIL BOUND DISTEMPER TOWER A,B,C,D1&D2; I. LIVING ROOM & DINING ROOM-OIL BOUND DISTEMPER BEDROOMS-OIL BOUND DISTEMPER TOILETS WITH BEDROOMS-CERAMIC TILES TILL 7'-0" ON ALL SIDES KITCHEN-CERAMIC TILES 2'-0" ABOVE COUNTER. UTILITY ROOM-OIL BOUND DISTEMPER
3KITCHEN DETAILSTOWER E,F,G,H,J,T3&T4; FLOORS-VITRIFIED TILES EXTERNAL DOORS & WINDOWS-ANODIZED/POWDER COATED ALUMINUM / UPVC INTERNAL WALLS-CERAMIC TILES 2'-0" ABOVE COUNTER. FIXTURES AND FITTINGS-GRANITE TOP WITH STAINLESS STEEL SINK WITH DRAIN BOARD TOWER A,B,C,D1&D2; FLOORS-VITRIFIED TILES EXTERNAL DOORS & WINDOWS-POWDER COATED ALUMINUM INTERNAL WALLS-CERAMIC TILES 2'-0" ABOVE COUNTER. FIXTURES AND FITTINGS-GRANITE TOP WITH STAINLESS STEEL SINK WITH DRAIN BOARD
4BATHROOM FITTINGSTOWER E,F,G,H,J,T3&T4; ALL PROVIDED OF STANDARD COMPANY MAKE TOWER A,B,C,D1&D2; I. ALL PROVIDED OF STANDARD COMPANY MAKE
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESTOWER E,F,G,H,J,T3&T4; WOODEN FRAME/ANODIZED/POWDER COATED ALUMINUM / UPVC TOWER A,B,C,D1&D2; WOODEN FRAME/ANODIZED/POWDER COATED ALUMINUM / UPVC
7GLASS WORKTOWER E,F,G,H,J,T3&T4; I. HALF GLASS PARTITION IN SHOWER AREA TOWER A,B,C,D1&D2; II. N/A
8ELECTRIC FITTINGSTOWER E,F,G,H,J,T3&T4; ALL PROVIDED OF STANDARD COMPANY MAKE TOWER A,B,C,D1&D2; ALL PROVIDED OF STANDARD COMPANY MAKE
9CONDUCTING AND WIRING DETAILSTOWER E,F,G,H,J,T3&T4; ISI MARED AND STANDARD MAKE TOWER A,B,C,D1&D2; ISI MARED AND STANDARD MAKE
10CUPBOARD DETAILSN/A
11WATER STORAGETOWER E,F,G,H,J,T3&T4; I. AS PER BUILDING CODE TOWER A,B,C,D1&D2; I. AS PER BUILDING CODE
12LIFT DETAILSTOWER E,F,G,H,J,T3&T4; I. INSTALLED AS PER STANDARD MAKE TOWER A,B,C,D1&D2; I. INSTALLED AS PER STANDARD MAKE
13EXTERNAL GLAZINGSYES
13.1WINDOWS/GLAZINGSTOWER E,F,G,H,J,T3&T4; ANODIZED/POWDER COATED ALUMINUM / UPVC TOWER A,B,C,D1&D2; I. POWDER COATED ALUMINUM / UPVC
14DOORS YES
14.1MAIN DOORSFOR TOWER -G,H,J,E,F,T3 &T4;(VENEER FINISH FLUSH DOORS/MOULDED SHUTTER WITH HARDWOOD FRAME)FOR TOWERS-A,B,C,D1&D2;(PREHUNG- LVL WITH VENEER)
14.2INTERNAL DOORSFOR TOWER -G,H,J,E,F,T3 &T4;(LAMINATE FINISH FLUSH DOORS/MOULDED SHUTTER WITH HARDWOOD FRAME)FOR TOWERS-A,B,C,D1&D2;(PREHUNG- LVL WITH LAMINATE)
15AIR CONDITIONINGN/A
16ELECTRICAL FITTINGSTOWER E,F,G,H,J,T3&T4; ALL PROVIDED OF STANDARD COMPANY MAKE TOWER A,B,C,D1&D2; I. ALL PROVIDED OF STANDARD COMPANY MAKE
17CNG PIPE LINETOWER E,F,G,H,J,T3&T4; I. PROVISION ONLY TOWER A,B,C,D1&D2; I. PROVISION ONLY
18PROVISION OF WIFI AND BROADBAND FACILITYTOWER E,F,G,H,J,T3&T4; I. YES TOWER A,B,C,D1&D2; I. YES
19EXTERNAL FINISHING/COLOUR SCHEMETOWER E,F,G,H,J,T3&T4; I. EXTERNAL GRADE TEXTURE PAINT TOWER A,B,C,D1&D2; II. EXTERIOR GRADE ACRYLIC EMULSION PAINT
20INTERNAL FINISHINGTOWER E,F,G,H,J,T3&T4; I. ACRYLIC EMULSION ON WALLS AND OIL BOUND DISTEMPER ON CEILING TOWER A,B,C,D1&D2; I. OIL BOUND DISTEMPER ON WALL & CELING
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORTOWER E,F,G,H,J,T3&T4; I. VITRIFIED TILES TOWER A,B,C,D1&D2; I. VITRIFIED TILES
1 . 2 WALLSTOWER E,F,G,H,J,T3&T4; I. ACRYLIC EMULSION TOWER A,B,C,D1&D2; II. OIL BOUND DISTEMPER
1 . 3 CEILINGTOWER E,F,G,H,J,T3&T4; I. OIL BOUND DISTEMPER TOWER A,B,C,D1&D2; I. OIL BOUND DISTEMPER
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORTOWER E,F,G,H,J,T3&T4; LAMINATED WOODEN FLOOR TOWER A,B,C,D1&D2; LAMINATED WOODEN FLOOR
2 . 2 WALLSTOWER E,F,G,H,J,T3&T4; I. ACRYLIC EMULSION TOWER A,B,C,D1&D2; II. OIL BOUND DISTEMPER
2 . 3 CEILINGTOWER E,F,G,H,J,T3&T4; I. OIL BOUND DISTEMPER TOWER A,B,C,D1&D2; I. OIL BOUND DISTEMPER
2 . 4 MODULAR WARDROBESN/A
3 . MASTER TOILET
3 . 1 FLOORTOWER E,F,G,H,J,T3&T4; I. ANTI SKID CERAMIC TILE TOWER A,B,C,D1&D2; I. ANTI SKID CERAMIC TILES
3 . 2 WALLSTOWER E,F,G,H,J,T3&T4; I. TILL 7'-0" ON ALL SIDES & OIL BOUND DISTEMPER TOWER A,B,C,D1&D2; TILL 7'-0" ON ALL SIDES & OIL BOUND DISTEMPER
3 . 3 CEILINGTOWER E,F,G,H,J,T3&T4; GRID CEILING TOWER A,B,C,D1&D2; I. GRID CEILING
3 . 4 COUNTERSTOWER E,F,G,H,J,T3&T4; I. GRANITE TOWER A,B,C,D1&D2; I. GRANITE
3 . 5 SANITARY WARE/CP FITTINGSTOWER E,F,G,H,J,T3&T4; I. ALL PROVIDED OF STANDARD COMPANY MAKE TOWER A,B,C,D1&D2; I. ALL PROVIDED OF STANDARD COMPANY MAKE
3 . 6 FITTING/FIXTURESTOWER E,F,G,H,J,T3&T4; I. ALL PROVIDED OF STANDARD COMPANY MAKE TOWER A,B,C,D1&D2; I. ALL PROVIDED OF STANDARD COMPANY MAKE
4 . BED ROOMS
4 . 1 FLOORTOWER E,F,G,H,J,T3&T4; LAMINATED WOODEN FLOOR TOWER A,B,C,D1&D2; LAMINATED WOODEN FLOOR
4 . 2 WALLSTOWER E,F,G,H,J,T3&T4; ACRYLIC EMULSION TOWER A,B,C,D1&D2; I. OIL BOUND DISTEMPER
4 . 3 CEILINGTOWER E,F,G,H,J,T3&T4; OIL BOUND DISTEMPER TOWER A,B,C,D1&D2; OIL BOUND DISTEMPER
4 . 4 WARDROBESN/A
5 . TOILET
5 . 1 FLOORTOWER E,F,G,H,J,T3&T4; ANTI SKID CERAMIC TILE TOWER A,B,C,D1&D2; I. ANTI SKID CERAMIC TILE
5 . 2 WALLSTOWER E,F,G,H,J,T3&T4; TILL 7'-0" ON ALL SIDES & ACRYLIC EMULSION TOWER A,B,C,D1&D2; TILL 7'-0" ON ALL SIDES & OIL BOUND DISTEMPER
5 . 3 CEILINGTOWER E,F,G,H,J,T3&T4; GRID CEILING TOWER A,B,C,D1&D2; I. GRID CEILING
5 . 4 COUNTERSTOWER E,F,G,H,J,T3&T4; I. GRANITE TOWER A,B,C,D1&D2; I. GRANITE
5 . 5 SANITARY WARE/CP FITTINGSTOWER E,F,G,H,J,T3&T4; I. ALL PROVIDED OF STANDARD COMPANY MAKE TOWER A,B,C,D1&D2; I. ALL PROVIDED OF STANDARD COMPANY MAKE
5 . 6 FIXTURESTOWER E,F,G,H,J,T3&T4; I. ALL PROVIDED OF STANDARD COMPANY MAKE TOWER A,B,C,D1&D2; I. ALL PROVIDED OF STANDARD COMPANY MAKE
6 . KITCHEN
6 . 1 FLOORTOWER E,F,G,H,J,T3&T4; I. VITRIFIED TILES TOWER A,B,C,D1&D2; I. VITRIFIED TILES
6 . 2 WALLSTOWER E,F,G,H,J,T3&T4; I. CERAMIC TILES 2'-0" ABOVE COUNTER & ACRYLIC EMULSION TOWER A,B,C,D1&D2; II. CERAMIC TILES 2'-0" ABOVE COUNTER & OIL BOUND DISTEMPER
6 . 3 CEILINGTOWER E,F,G,H,J,T3&T4; OIL BOUND DISTEMPER TOWER A,B,C,D1&D2; OIL BOUND DISTEMPER
6 . 4 COUNTERSTOWER E,F,G,H,J,T3&T4; I. GRANITE TOP TOWER A,B,C,D1&D2; I. GRANITE TOP
6 . 5 FIXTURESTOWER E,F,G,H,J,T3&T4; I. ALL PROVIDED OF STANDARD COMPANY MAKE TOWER A,B,C,D1&D2; ALL PROVIDED OF STANDARD COMPANY MAKE
6 . 6 KITCHEN APPLIANCESTOWER E,F,G,H,J,T3&T4; STAINLESS STEEL SINK WITH DRAIN BOARD TOWER A,B,C,D1&D2; I. STAINLESS STEEL SINK WITH DRAIN BOARD
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORTOWER E,F,G,H,J,T3&T4; CERAMIC TILES TOWER A,B,C,D1&D2; I. CERAMIC TILES
7 . 2 WALLS & CEILINGTOWER E,F,G,H,J,T3&T4; OIL BOUND DISTEMPER TOWER A,B,C,D1&D2; I. OIL BOUND DISTEMPER
7 . 3 TOILETTOWER E,F,G,H,J,T3&T4; ANTI SKID CERAMIC TILE TOWER A,B,C,D1&D2; ANTI SKID CERAMIC TILE
7 . 4 BALCONYTOWER E,F,G,H,J,T3&T4; I. ANTI SKID TILES TOWER A,B,C,D1&D2; I. ANTI SKID TILES
8 . SIT-OUTS
8 . 1 FLOORTOWER E,F,G,H,J,T3&T4; I. ANTI SKID CERAMIC TILES TOWER A,B,C,D1&D2; I. CERAMIC TILES
8 . 2 WALLS & CEILINGTOWER E,F,G,H,J,T3&T4; ACRYLIC EMULSION/OIL BOUND DISTEMPER TOWER A,B,C,D1&D2; I. OIL BOUND DISTEMPER
8 . 3 RAILINGSTOWER E,F,G,H,J,T3&T4; I. MS RAILING AS PER DESIGN TOWER A,B,C,D1&D2; MS RAILING AS PER DESIGN
8 . 4 FIXTURESTOWER E,F,G,H,J,T3&T4; ALL PROVIDED OF STANDARD COMPANY MAKE TOWER A,B,C,D1&D2; I. ALL PROVIDED OF STANDARD COMPANY MAKE












Sr. No.Document DescriptionDate of Document UploadView Document
1 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 02-02-2021 View Document
2 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 02-02-2021 View Document
3 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 03-02-2021 View Document
4 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 03-02-2021 View Document
5 BASEMENT PLAN 03-02-2021 View Document
6 CHANGE ROOM, AV ROOM & ACTIVITY ROOM(FLOOR PLANS) 03-02-2021 View Document
7 CHANGE ROOM, AV ROOM & ACTIVITY ROOM(FLOOR PLANS)2 03-02-2021 View Document
8 ELEVATIONS & SECTIONS (EWS-BLOCK F) 03-02-2021 View Document
9 ELEVATIONS (TOWER ABC)1 03-02-2021 View Document
10 ELEVATIONS (TOWER ABC)2 03-02-2021 View Document
11 ELEVATIONS (TOWER D1& D2)1 03-02-2021 View Document
12 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 03-02-2021 View Document
13 ELEVATIONS (TOWER D1& D2)2 03-02-2021 View Document
14 PLANS & AREA DEATILS (EWS-BLOCK F) 03-02-2021 View Document
15 PLANS, ELEVATIONS & SECTIONS OF COMMERCIAL (BLOCKD) 03-02-2021 View Document
16 SECTIONS (TOWER ABC)2 03-02-2021 View Document
17 SECTIONS (TOWER D1 ANDD2)2 03-02-2021 View Document
18 SITE PLAN WITH FIRE SERVICES(AFTER APPROVAL) 03-02-2021 View Document
19 TOWER D1&D2; (FLOOR PLANS_AREA DETAILS)3 03-02-2021 View Document
20 TOWER ABC (FLOOR PLANS_AREA DETAILS)1 03-02-2021 View Document
21 TOWER ABC (FLOOR PLANS_AREA DETAILS)2 03-02-2021 View Document
22 TOWER ABC (FLOOR PLANS_AREA DETAILS)3 03-02-2021 View Document
23 TOWER D1&D2; (FLOOR PLANS_AREA DETAILS)1 03-02-2021 View Document
24 TOWER D1&D2; (FLOOR PLANS_AREA DETAILS)2 03-02-2021 View Document
25 TOWER D1&D2; (FLOOR PLANS_AREA DETAILS)4 03-02-2021 View Document
26 WATER SUPLLY SCHEMEATIC DIAGRAM(TOWER ABC) 03-02-2021 View Document
27 WATER SUPLLY SCHEMEATIC DIAGRAM(TOWER D1&D2;) 03-02-2021 View Document
28 WATER SUPPLY SCHEMATIC EWS 03-02-2021 View Document
29 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 04-02-2021 View Document
30 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 18-06-2021 View Document
31 DEMARCATION PLAN 18-06-2021 View Document
32 APARTMENT PLAN 18-06-2021 View Document
33 COPY OF SUPERIMPOSED DEMARCATION PLAN 18-06-2021 View Document
34 ELECTRICITY PLAN 18-06-2021 View Document
35 ELEVATION PLAN 18-06-2021 View Document
36 FIRE SCHEMES 18-06-2021 View Document
37 FLOOR PLAN 18-06-2021 View Document
38 LAND ESCAPE PLAN 18-06-2021 View Document
39 LAYOUT PLAN 18-06-2021 View Document
40 PARKING PLAN 18-06-2021 View Document
41 ROAD AND PAVEMENT PLANS 18-06-2021 View Document
42 SERVICE ESTIMATES 18-06-2021 View Document
43 SEWERAGE PLAN 18-06-2021 View Document
44 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 18-06-2021 View Document
45 SOLID WASTAGE PLAN 18-06-2021 View Document
46 STORM WATER PLAN 18-06-2021 View Document
47 STREET LIGHT PLAN 18-06-2021 View Document
48 STRUCTURAL PLAN 18-06-2021 View Document
49 WATER SUPPLY PLAN 18-06-2021 View Document
50 X- SECTION PLAN 18-06-2021 View Document
51 ZONING PLAN 18-06-2021 View Document
52 RENEWAL OF LICENCE NO. 01 OF 2014 (VALID UPTO 02.01.25) 18-06-2021 View Document
53 LOI (21.06.2013) 18-06-2021 View Document
54 BILATERAL AGREEMENT 18-06-2021 View Document
55 LC-IV 18-06-2021 View Document
56 DEVELOPMENT AGREEMENT 18-06-2021 View Document
57 GENERAL POWER OF ATTORNEY 18-06-2021 View Document
58 SALE DEED 18-06-2021 View Document
59 JAMABANDI AND MUTATION 18-06-2021 View Document
60 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 18-06-2021 View Document
61 TITLE SEARCH REPORT 18-06-2021 View Document
62 MINING PERMISSION (13.11.17) 18-06-2021 View Document
63 PAYMENT PLAN 18-06-2021 View Document
64 EC 18-06-2021 View Document
65 AAI RENEWAL VALID TILL 11.09.2022 18-06-2021 View Document
66 AAI 18-06-2021 View Document
67 APPROVAL OF FIRE SCHEME SOHNA 18-06-2021 View Document
68 APPROVAL OF REVISED FIRE SCHEME REVISED 18-06-2021 View Document
69 APPROVAL OF BUILDING PLAN (11.11.14) 18-06-2021 View Document
70 APPROVAL OF SERVICE ESTIMATES, SECT. 33 (07.02.20) 18-06-2021 View Document
71 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 18-06-2021 View Document
72 APPROVAL OF REVALIDATION BP (25.06.20) 18-06-2021 View Document
73 BR-III 18-06-2021 View Document
74 APPROVAL OF REVISED SERVICE PLAN 18-06-2021 View Document
75 LOAD ASSURANCE 18-06-2021 View Document
76 FOREST NOC 18-06-2021 View Document
77 REPORT ON NATURAL CONSERVATION ZONE 18-06-2021 View Document
78 TREE FELLING PERMISSION (08.08.18) 18-06-2021 View Document
79 TREE CUTTING 18-06-2021 View Document
80 FOREST DIVERSION PERMISSION 18-06-2021 View Document
81 FOREST LAND DIVERSION MAP 18-06-2021 View Document
82 NOC FOR CONSTRUCTION (17.10.14) 18-06-2021 View Document
83 LETTER POWER LINE DECLARATION 18-06-2021 View Document
84 SEWERAGE ASSURANCE- SOHNA 18-06-2021 View Document
85 MINING APPROVAL FOR NATURE PLUS (EXTENDED UPTO 19.02.20) 18-06-2021 View Document
86 RENEWAL OF MINING APPROVAL FOR NATURE PLUS (VALID UPTO 25.01.20).PDF 18-06-2021 View Document
87 PERT CHART 2 18-06-2021 View Document