| 20-Nov-2023 |
Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the project.
Sh. Anurag Srivastava (AR) is present
on behalf of the promoter and stated that, license of the above said project
has been renewed up to 01.02.2025 and further, OC for the above said project
had been obtained on 25.01.2023 itself and CC had been applied already on
24.02.2023.
It is observed that the promoter
delayed in submission of deficit fees (including late fee) and renewal of
license conveyed during the proceedings dated 20.02.2023. Now, the promoter has
submitted both the deficit fees as well as renewal of license. Further, the
project had got the OC vide memo no ZP-1140/JD(RA)/2023/2462 dated 25.01.2023
and CC had been applied by promoter also dated 24.02.2023. In view of the above
peculiar facts, Authority has decided to grant the extension of registration as
proposed above. |
EXTENSION APPROVED |
--- |
| 25-Sep-2023 |
Sh. Shashank Sharma, Associate
Engineer Executive and Ms. Asha CA, briefed about the facts of the project.
A
request letter for adjournment has been received in the Authority wherein
promoter wants 15 days time to submit the deficit documents left. Therefore, in
view of the same the matter is adjourned, and the next date of hearing will be
conveyed after submission of reply of deficiencies already conveyed.
Further,
if no response is received from the promoter within next 4 week’s time, in that
case the concerned official
to put up the matter on file for issuance of show cause notice as to why their application for extension of
registration of project may not be rejected following the due procedure under
the Act of 2016. |
ADJOURNMENT |
View Order |
| 28-Aug-2023 |
Sh. Shashank Sharma, Associate Engineer Executive briefed
about the facts of the project.
Sh. Anurag Srivastava (GM), Sh. Vedant Batra (CS) and Sh. Ravinder
are present on behalf of the promoter.
The AR of the promoter submits that the deficit fee has been
deposited and after completing the construction of all the units in the
project, OC has already been obtained from DTCP on 25.01.2023 and possession
also offered/handed over to the allottees. Further the renewal of license which
has expired on 01.02.2023 after obtaining OC has already been applied and is
under renewal with the department. Regarding revalidation of building plan, the
same is not required as OC of all the units has already been obtained from
DTCP. Since, the units are already constructed and hence the payment plan
should provide the condition of not taking more than 10% earnest money before
execution of BBA as per section 13 of the Act. The AR is given one opportunity
to submit renewed license within 3 weeks.
The
matter to come up on 25.09.2023. |
ADJOURNMENT |
View Order |
| 14-Aug-2023 |
The coram is not complete. The matter is adjourned and to come up on 28.08.2023. |
ADJOURNMENT |
View Order |
| 17-Jul-2023 |
Sh.
Shashank Sharma, Associate Engineer Executive briefed about the facts of the
project.
Sh. Vedant Batra (CS) and Sh.
Mintu Kumar (AR) are present on behalf of the promoter.
The AR of the promoter requests for four weeks
time to comply with the deficiencies. The Authority grants four weeks time for
submission of deficit documents including deficit of Rs. 52,93,035/- failing
which the application for extension of registration shall be rejected.
The matter
to come up on 14.08.2023 |
ADJOURNMENT |
View Order |
| 26-Jun-2023 |
Sh.
Shashank Sharma, Associate Engineer Executive briefed about the facts of the
project.
Sh.
Anurag Srivastava (Manager) is present on behalf of the promoter.
The AR of
the promoter seeks two weeks’ time to comply with the deficiencies.
The matter
to come up on 17.07.2023. |
ADJOURNMENT |
View Order |
| 07-Jun-2023 |
Sh.
Shashank Sharma, Associate Engineer Executive briefed about the facts of the
project.
Sh. Anurag
Srivastava (GM) and Sh. Vedant Batra (CS) are present on behalf of the
promoter.
The
promoter has submitted an application dated 20.02.2023 for waiver of deficit
fee of Rs. 52,93,035/- and has also submitted certain citations in this regard.
The matter may be put up for decision separately on file within a period of one
week.
The
matter to come up on 26.06.2023. |
ADJOURNMENT |
View Order |
| 05-Jun-2023 |
Coram is not complete. The matter is placed
before the authority and as per the directions of authority the matter is
adjourned to 07.06.2023. |
ADJOURNMENT |
View Order |
| 08-May-2023 |
Sh. Shashank Sharma, Associate Engineer Executive briefed about
the facts of the project.
Sh. Anurag Srivastava is present on
behalf of the promoter and states that UP RERA has granted relief beyond six
months. The promoter is directed to submit a detailed representation along with
copy of order of UP RERA regarding relief beyond six months.
The
matter to come up on 05.06.2023 |
ADJOURNMENT |
View Order |
| 17-Apr-2023 |
Sh.
Shashank Sharma, Associate Engineer Executive briefed about the facts of the
project.
Sh. Anurag Srivastava (GM) and Sh.
Vedant Batra (CS) are present on behalf of the promoter.
The AR of the promoter requested for
three weeks’ time for submission of the deficit documents.
The matter
to come up on 08.05.2023. |
ADJOURNMENT |
View Order |
| 29-Mar-2023 |
Sh. Shashank Sharma, Associate Engineer Executive briefed
about the facts of the project.
None is
present on behalf of the promoter. An application seeking two weeks extension
has been received. Request allowed.
The
matter to come up on 17.04.2023. |
ADJOURNMENT |
View Order |
| 27-Mar-2023 |
The matter is adjourned to 29.03.2023. |
ADJOURNMENT |
View Order |
| 13-Mar-2023 |
Sh. Shashank Sharma, Associate Engineer Executive briefed
about the facts of the project.
Sh. Anurag Srivastava (Manager) is present on behalf
of the promoter.
The applicant has to deposit deficit fee and late fee
for making application under section 6 of the Act which is yet to be deposited.
The AR of the applicant states that delay is on account of force majeure
circumstances and requisite condonation may be made and further stated that the
project was registered under the interim RERA, Panchkula where 9 months period
on account of COVID-19 has been allowed as zero period for deposit of late fee.
The matter was considered and the Authority decided that the period allowed by
HARERA, Gurugram has been applied across the board for all cases and request of
the applicant cannot be allowed. Therefore, the fee demanded has to be
deposited.
The
matter to come up on 27.03.2023. |
ADJOURNMENT |
View Order |
| 20-Feb-2023 |
Sh. Shashank Sharma, Associate Engineer Executive briefed
about the facts of the project.
Sh. Anurag Srivastava is present on behalf of the
promoter.
The time period for which extension is being sought
expires on 20.02.2023.
The AR of the promoter states that OC for the project
has been received on 25.01.2023 and has been placed on record and the promoter
is applying for CC within a week time. Further, a representation has been
submitted by the promoter for waiver of late fee of Rs 41,17,624/- and
additional fee of Rs 11,75,911/-.
The
matter to come up on 13.03.2023. |
ADJOURNMENT |
View Order |
| 14-Feb-2023 |
Sh. Shashank Sharma, Associate Engineer Executive briefed
about the facts of the project.
Sh.
Anurag Srivastava (AR) is present on behalf of the promoter.
The
promoter is directed to rectify the deficiencies and submit the required
documents before the next date of hearing.
The
matter to come up on 20.02.2023. |
ADJOURNMENT |
View Order |
| 31-Jan-2023 |
The matter is adjourned to 14.02.2023. |
ADJOURNMENT |
View Order |
| 17-Jan-2023 |
The authorized representative of the promoter is advised to rectify the deficiencies and submit the deficit fee (if any) along with the deficit documents apart from the filing of information in online detailed project information. The matter is adjourned to 31.01.2023 |
ADJOURNMENT |
View Order |
| 03-Jan-2023 |
The authorized representative of the promoter is advised to rectify the deficiencies and submit the deficit fee (if any) along with the deficit documents apart from the filing of information in online detailed project information. The matter is adjourned to 17.01.2023 |
ADJOURNMENT |
View Order |
| 19-Dec-2022 |
The AR of the promoter is directed to remove the deficiencies. The matter to come up on 03.01.2023 |
ADJOURNMENT |
View Order |
| 05-Dec-2022 |
The
authorized representative of the promoter is advised to rectify the
deficiencies and submit the deficit fee within a week along with the deficit
documents apart from the filing of information in REP-I A to H format and
online detailed project information. Further, if any promoter has an issue
regarding the calculation of the fee, then the same shall be re-conciled with
the concerned official and be submitted in the Authority, otherwise their
matter will not be heard on next date of hearing i.e., 19.12.2022. The matter
to come up on 19.12.2022. (Sanjeev
Kumar Arora)
Member, HARERA, Gurugram
(Ashok Sangwan)
Member,
HARERA, Gurugram
(Vijay
Kumar Goyal)
Member,
HARERA, Gurugram
(Dr. K.K. Khandelwal)
Chairman,
HARERA, Gurugram
|
OBJECTION |
View Order |
| 21-Nov-2022 |
Proceedings dated 21.11.2022
Sh. Shashank Sharma, Associate Engineer Executive briefed
about the facts of the project.
Sh.
Anurag Srivastava (GM) is present on behalf of the promoter.
The
promoter is directed to deposit the deficit fee and other documents as
mentioned above.
The
matter to come up on 05.12.2022.
(Sanjeev
Kumar Arora)
Member, HARERA, Gurugram
(Ashok Sangwan)
Member,
HARERA, Gurugram
(Vijay
Kumar Goyal)
Member,
HARERA, Gurugram
(Dr. K.K. Khandelwal)
Chairman,
HARERA, Gurugram
|
ADJOURNMENT |
View Order |
| 27-Oct-2022 |
The promoter is directed to rectify the deficiencies and submit the deficit fee if any. The matter is adjourned for 21.11.2022. |
ADJOURNMENT |
View Order |
| 26-Oct-2022 |
The coram is not complete. So the matter is adjourned for 27.10.2022. |
OBJECTION |
View Order |
| 11-Oct-2022 |
The major deficiencies are Renewal of
license, Renewal of Building plan approval and Service plan and estimates.
Bank Undertaking. Deficit Fee- Rs.
61,76,435/-. The authorized representative of the promoter is advised to
deposit the deficient fee as mentioned against each within 7 days otherwise
their matter will not be heard on the next date of hearing i.e.,
26.10.2022. The promoter is further
advised to rectify the deficiencies and submit the deficient document apart
from the filing of information in REP-I A to H format and detailed project
information. The matter to come up on
26.10.2022. |
ADJOURNMENT |
View Order |
| 27-Sep-2022 |
Deficiencies have already been conveyed, the promoter is advised to rectify the same. The matter is fixed for further hearing on 11.10.2022. |
ADJOURNMENT |
View Order |
| 05-Sep-2022 |
Proceedings dated 05.09.2022
Sh.
Shashank Sharma, Associate Engineer Executive briefed
about the facts of the project.
Sh.
Anurag Srivastava (GM) is present on behalf of the promoter. The AR submits
that deficit documents have been submitted today and same requires examination
by office. The applicant has also
submitted for waiver of late fee vide letter dated 09.08.2022. No such relief
is admissible. The AR is required to deposit the deficit fees already conveyed
and to be re-checked/reconciled by CA of the Authority.
The
matter to come up on 27.09.2022. |
ADJOURNMENT |
View Order |
| 17-Aug-2022 |
PProceedings dated 17.08.2022Ms.
Geeta Rathee Singh, Sr. Legal Officer and Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the
project.
Sh.
Anurag Srivastava (GM) and Sh. Sukh Pal (Executive Legal Deptt.) are present on
behalf of the promoter.
The
AR request for one week time for submitting the deficit documents and the
balance fees, for which re-checking/reconciliation be made with the CA of the
Authority and to be deposited before the next date of hearing. The request is
allowed.
The matter to come up on 05.09.2022. |
ADJOURNMENT |
View Order |
| 08-Aug-2022 |
Proceedings dated 08.08.2022
Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the
project.
Sh. Ajay Kumar
(Assistant Manager) is present on the behalf of promoter.
The AR has submitted the reply to the deficiencies
conveyed today in the registry of the Authority which be checked by the
concerned Engineering Executive. The calculation of the fee proposed to be
levied be rechecked/ reconciled by the CA of the Authority with the AR of the
promoter. The validity of license has also expired and hence the promoter is
advised to obtain the renewal of licence before the extension is considered.
Further the office is also to check the status of compliances w.r.t. the
existing registered project which has not been completed within the time
declared under 4(2)(l)(C).
The matter to come up on 17.08.2022. |
OBJECTION |
View Order |
| 27-Jul-2022 |
Proceedings dated 27.07.2022
Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the
project.
Sh. Ajay Kumar
(Assistant Manager) is present on the behalf of promoter.
The AR requests for one week for
rectification of the deficiencies and submission of deficit documents as per
above.
The matter to come up on 08.08.2022. |
ADJOURNMENT |
View Order |
| 25-Jul-2022 |
Due to administrative work of the Authority, the matter is adjourned to 27.07.2022 |
EXAMINATION BY AUTHORITY |
View Order |