Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
---|---|---|---|---|
Avalon Rangoli, Dharuhera (Phase II) | Revenue Estate of Garhi Alawalpur | REWARI | Dharuhera ST | AVALON PROJECTS (M/s GRJ Distributors & Developers Pvt Ltd) |
Project Registration Number | Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks | Details of Project(Form A-H) |
---|---|---|---|---|---|---|---|---|---|---|---|---|
HRERA-PKL-RWR-351-2022 | RERA-PKL-805-2020 | 22-Jan-2020 | 21-Jan-2020 | APPROVED AND CERTIFICATE UPLOADED | NOT REQUIRED | Not Yet | -- | Listed for hearing after fresh application. | View Form(A-H) |
Project Registration Number | Approval Date | Approval Remarks | View Certificate |
---|---|---|---|
HRERA-PKL-RWR-351-2022 | 15-Sep-2022 | Issued Registration Certificate |
Date of Hearing | Proceedings of the day | Status | Order |
---|---|---|---|
30-May-2022 | Approved for registration. | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | View Order |
02-Aug-2021 | ADJOURNMENT | View Order | |
10-May-2021 | Adjourned to 02.08.2021 | ADJOURNMENT | View Order |
12-Apr-2021 | re-open,Adjourned to 10.05.2021 | RE-OPEN/ADJOURNMENT | View Order |
21-Dec-2020 | Registration Certificate to be issued. | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | View Order |
07-Dec-2020 | Adjourned to 21.12.2020 | ADJOURNMENT | View Order |
23-Nov-2020 | Adjourned to 07.12.2020 | ADJOURNMENT | View Order |
09-Nov-2020 | Adjourned to 23.11.2020 | ADJOURNMENT | View Order |
26-Oct-2020 | Adjourned to 09.11.2020 | OBJECTION | View Order |
05-Oct-2020 | Adjourned to 26.10.2020 | ADJOURNMENT | View Order |
10-Aug-2020 | Adjourned to 05.10.2020 | ADJOURNMENT | View Order |
27-Jan-2020 | ADJOURNMENT | View Order |
Deficiency Date | Deficiency Remarks | Online Compliance Done | Online Compliance Date | Online Compliance Remarks | Compliance Date | Compliance Remarks |
---|---|---|---|---|---|---|
12-Oct-2020 | Adjourned to 26.10.2020 | Not Yet |