HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-805-2020
Submission Date : 21-01-2020 04:30:33 AM
Applicant Type : Company
Project Type: ONGOING




AVALON PROJECTS (M/S GRJ DISTRIBUTORS & DEVELOPERS PVT LTD)
64, SCINDIA HOUSE, CONNAUGHT PLACE, NEW DELHI 110001
01244988988
9560691351 (Number Shared by Promoter in Public)
sachin.m@avalongroup.in
https://www.avalongroup.in
XXXX952F
u51396dl1998ptc097177
 
 


 
 


 
 







AVALON RANGOLI, DHARUHERA (PHASE II)
REVENUE ESTATE OF GARHI ALAWALPUR
DHARUHERA ST
REWARI
01244988988
8684826101 (Number Shared by Promoter in Public)
sachin.m@avalongroup.in
KAMLESH KUSHWAH
01244988988
8684826101 (Number Shared by Promoter in Public)
info@avalongroup.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
11010919-10-2019322000HDFC BANK, SOUTH CITY II, GURGAON 122018HRERA Panchkula







36696.952 (Sqr/mtrs)
175
171.11
71715.747 (Sqr/mtrs)
License No. 1 of 2012
No
Address     B-27, FIRST FLOOR, PUSHPANJALI ENCLAVE, PITAMPURA, DELHI 110034
Address     B-27, FIRST FLOOR, PUSHPANJALI ENCLAVE, PITAMPURA, DELHI 110034
Annexure-B- DEVELOPER
COLLABORATION AGREEMENT
No
ARTICLE 2 - PROJECT AND PROJECT LAND
No
No
Yes







10562.5765 Lakhs
2018.6565 Lakhs
6475 Lakhs
804 Lakhs
1264.92 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS5459.767
3CONSTRUCTION OF ROADS13249.464
4PAVEMENTS0
5PARKS AND PLAYGROUNDS10734.737
6GREEN BELTS0
7VEHICLE PARKINGS3359.805
8ELECTRICITY SUB-STATION453.555
9CLUB HOUSE1184.772
10SEWAGE AND SOLID WASTE TREATMENT FACILITY17.503
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES1419.531
12ANY OTHER817.818
Total36696.952




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSYes
WATER SUPPLYYes
ELECTRICITYYes
SEWAGE DISPOSALYes
STORM WATER DRAINAGEYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS198.3AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM168.3AS PER PROJECT REPORT
3STORM WATER DRAINAGE43.59AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM40.59AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL72.22AS PER PROJECT REPORT
6STREET LIGHTING11.91AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING27.31AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS13.76AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


NA (date)
NA (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE A711.20216204123
2APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE B949.12132100322






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
TYPE A - 2 BHK204THE STRUCTURE WORK IS READY. THE COMMON USAGE AREA IS READY AND OPERATIONAL AND CURRENTLY USED BY THE RESIDENTS OF PHASE I. ONLY INTERNAL FINISHING WORK IS REMAINING.
TYPE B - 3 BHK100THE STRUCTURE WORK IS READY. THE COMMON USAGE AREA IS READY AND OPERATIONAL AND CURRENTLY USED BY THE RESIDENTS OF PHASE I. ONLY INTERNAL FINISHING WORK IS REMAINING.


01-07-2013
01-01-2017
01-01-2021
01-07-2013
90
01-01-2021


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
01-07-2013
90
01-01-2021


359
112
471
157
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments5758
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments143.4
Shops0
Plots0

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments143.4143.4143.4143.4
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements120
Water Supply System0
Sewerage treatment & garbage disposal80
Electricity Supply System70
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Fire Fighting50

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2
Water Supply System0
Sewerage treatment & garbage disposal4
Electricity Supply System36
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other54.8

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2222
Water Supply System0000
Sewerage treatment & garbage disposal4444
Electricity Supply System36363636
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other54.854.854.854.8

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements12
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Lift Escalator75
Fire Fighting0

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements5555
Water Supply System02.52.55
Sewerage treatment & garbage disposal0101017.5
Electricity Supply System0404040
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Lift Escalator252545
Fire Fighting155050












Particulars Remarks, if any
i. No. of Flats/Apartments constructed348
ii. No. of Flats/ Apartments booked304
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter11761.35 LakhsWIthout Tax
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter10683.65 LakhsWithout Tax
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter1077.71 LakhsWithout Tax
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter218.17 LakhsWithout Tax
vii. Amount invested in the project upto the date of application10562.57 Lakhs
Land cost (If any)2018.65 Lakhs
Apartments6475 Lakhs
Infrastructure804 Lakhs
EDC/ Taxes Etc.1264.92 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession1476 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
2000 LakhsThe loan of INR 1500 has been paid till date
x. Total liabilities against the project up-to-date. (Annex details in folder C) 500 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS130120
II. WATER SUPPLY SYSTEM00
III. STORM WATER DRAINAGE00
IV. ELECTRICITY SUPPLY SYSTEM25070
V. SEWAGE TREATMENT & GARBAGE DISPOSAL10080
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.00
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT18050









Yes
Yes
HDFC BANK, SHOP NO. 4-8, SOUTH CITY II, COMMERCIAL SHOPPING CENTER, GURGAON - 122018
17212090000023
HDFC0001721
110240222
1721
Mr. Subhash Rustagi
The company has availed the loan facility for the development of the present project from the state bank of india of INR 20 crore out of which INR 15 crore has been paid. However due to unforseen circumstances, the amount of INR 5 crore couldn't be paid and default occured











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Statutory Approvals Statutory Approvals StatusDate
I. AS PER ABOVEALREADY BEEN OBTAINEDNA








Yes


Yes















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSECORRIDOR – UDAIPUR GREEN, DRAWING ROOM & BED ROOMS-VITRIFIED TILE, TOILET – CERAMIC TILE
2WALL FINISHING DETAILSOBD
3KITCHEN DETAILSCOUNTER- BLACK GRANITE, FLOOR- VITRIFIED TILE
4BATHROOM FITTINGSC P ,CHINA – ISI MARKED
5WOOD WORK ETCONLY MODULAR WOOD WORK IN KITCHEN
6DOORS AND WINDOS FRAMESDOOR FRAME- RED MARANDI, MAIN DOOR- SKIN DOOR, INTERNAL DOORS –FLUSH DOORS
7GLASS WORK5MM PLAIN GLASS ON EXTERNAL FACE WITH ALUMINUM
8ELECTRIC FITTINGSMODULAR SWITCH SOCKETS
9CONDUCTING AND WIRING DETAILSRECESSED PVC CONDUTE AND FRLS WIRE.
10CUPBOARD DETAILSNA
11WATER STORAGE UNDER GROUND AND OH TANKS
12LIFT DETAILS ONE 8 PASSENGER AND ANOTHER 13 PASSENGER LIFT
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORS 35 MM THICK SKIN DOORS
14.2INTERNAL DOORS32 MM FLUSH DOORS
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEBUBBLE TEXTURE
20INTERNAL FINISHINGOBD
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILE
1 . 2 WALLSOBD
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILE
2 . 2 WALLSOBD
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORANTI SKID CERAMIC TILES
3 . 2 WALLSCERAMIC TILE
3 . 3 CEILINGNA
3 . 4 COUNTERSBLACK GRANITE
3 . 5 SANITARY WARE/CP FITTINGSISI MARKED
3 . 6 FITTING/FIXTURESISI MARKED
4 . BED ROOMS
4 . 1 FLOORVITRIFIED
4 . 2 WALLSOBD
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORANTI SKID CERAMIC TILE
5 . 2 WALLSCERAMIC TILE
5 . 3 CEILINGNA
5 . 4 COUNTERSBLACK GRANITE
5 . 5 SANITARY WARE/CP FITTINGSBRANDED
5 . 6 FIXTURESISI MARKED
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILE
6 . 2 WALLSCERAMIC TILE 900 HEIGHT
6 . 3 CEILINGNA
6 . 4 COUNTERSBLACK GRANITE
6 . 5 FIXTURESBRANDED
6 . 6 KITCHEN APPLIANCESISI MARKED
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN20-01-2020 View Document
2CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT20-01-2020 View Document
3CASH FLOW STATEMENT OF THE PROPOSED PROJECT20-01-2020 View Document
4SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN20-01-2020 View Document
5COPY OF LICENSE ALONG WITH SCHEDULE OF LAND20-01-2020 View Document
6LAYOUT PLAN - DRAINAGE20-01-2020 ------
7DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.21-01-2020 View Document
8LANDSCAPE & PARKING PLAN20-01-2020 ------
9FIRE FIGHTING LAYOUT20-01-2020 ------
10IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN20-01-2020 View Document
11REP-II21-09-2022 ------
12NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT22-09-2022 View Document