HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-626-2019
Submission Date : 10-07-2019 06:48:55 AM
Applicant Type : Company
Project Type: ONGOING




PARKER VRC INFRASTRUCTURE PRIVATE LIMITED
410, 4TH FLOOR, D MALL, NETAJI SUBHASH PLACE, PITAMPURA, NEW DELHI-110034
01147804747
9811013011 (Number Shared by Promoter in Public)
parkervrcinfo@yahoo.com
http://parkervrc.com
XXXX047D
U70200DL2012PTC235447
 
 


 
 


 
 


 
 


 
 


 
 







WHITE LILY RESIDENCY
SECTOR-27, VILLAGE AHMEDPUR
SONIPAT
SONIPAT
9574003201 (Number Shared by Promoter in Public)
parkervrcinfo@yahoo.com
RAJEEV GUPTA
9574003201 (Number Shared by Promoter in Public)
parkervrcinfo@yahoo.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
13077401-08-2017473074CORPORATION BANKHRERA Panchkula







11.687 (Acre)
1.75
1.749
11.687 (Acre)
292 of 2007 Dated 31.12.2007
No
Address     4B, HANSALAYA BUILDING, 15, BARAKHAMBA ROAD, NEW DELHI-110001
Address     A-26 FRIENDS COLONY WEST NEW DELHI DL 110065 IN
Address     552 FIFTH FLOOR, KRISHNA APRA BUSINESS SQUARE, NSP, PITAMPURA, DELHI-110034
Address     8B, HANSALAYA BUILDING, 15, BARAKHMABA ROAD, DELHI-110001
Annexure-B- DEVELOPER
AFTER GRANT OF LICENSE
Yes
AS PER COLLABORATION AGREEMENT ENCLOSED
No
Yes
Yes







18500 Lakhs
0 Lakhs
11400 Lakhs
4100 Lakhs
3000 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS10741.93
3CONSTRUCTION OF ROADS16596.18
4PAVEMENTS2533.86
5PARKS AND PLAYGROUNDS9077.08
6GREEN BELTS0
7VEHICLE PARKINGS7125
8ELECTRICITY SUB-STATION0
9CLUB HOUSE446.10
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
13NURSERY SCHOOL TWO NUMBER539.08
14SHOPPING236.31
Total47295.54




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHARYANA SHEHRI VIKAS PRADHIKARANNo
WATER SUPPLYHARYANA SHEHRI VIKAS PRADHIKARANNo
ELECTRICITYUTTAR HARYANA BIJLI VITRAN NIGAM LIMITEDNo
SEWAGE DISPOSALHARYANA SHEHRI VIKAS PRADHIKARANNo
STORM WATER DRAINAGEHARYANA SHEHRI VIKAS PRADHIKARANNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS56YET TO BE PREPARED
2WATER SUPPLY SYSTEM248YET TO BE PREPARED
3STORM WATER DRAINAGE35YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM484YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL62YET TO BE PREPARED
6STREET LIGHTING20YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING280YET TO BE PREPARED
8PLAYGROUNDS AND PARKS170YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE100YET TO BE PREPARED
10SHOPPING AREA75YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM30YET TO BE PREPARED
12SCHOOL400YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER500YET TO BE PREPARED


NA (date)
NA (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type 2BHK62.709328672614
2APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK95.039318183006
3APARTMENT/SHOPS/OTHER BUILDINGS Type 4BHK129.134640641
4APARTMENT/SHOPS/OTHER BUILDINGS Type PENTHOUSE150.966600603
5APARTMENT/SHOPS/OTHER BUILDINGS Type SHOPS11.2216001






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
2BHK67STILT PLUS 8 FLOORS
3BHK18STILT PLUS 8 FLOORS


01-06-2015
31-12-2017
31-12-2022
01-06-2015
20
31-12-2022
ENCLOSED


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT0NOT APPLICABLE
01-06-2015
0
01-06-2015
NOT APPLICABLE
NOT APPLICABLE


796
87
883
285
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments650
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other100

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar












Particulars Remarks, if any
i. No. of Flats/Apartments constructed0Under Construction
ii. No. of Flats/ Apartments booked85Under Construction
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter3115 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter938 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter2177 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter2177 Lakhs
vii. Amount invested in the project upto the date of application2730 Lakhs
Land cost (If any)0 Lakhs
Apartments650 Lakhs
Infrastructure100 Lakhs
EDC/ Taxes Etc.2200 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession15550 Lakhs
(a) In respect of existing allottees5500 Lakhs
(b) In respect of rest of the project10050 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS5610
II. WATER SUPPLY SYSTEM2480
III. STORM WATER DRAINAGE350
IV. ELECTRICITY SUPPLY SYSTEM4840
V. SEWAGE TREATMENT & GARBAGE DISPOSAL620
VI. CLUB HOUSE/COMMUNITY CENTRE1000
VII. SCHOOL4000
VIII. ANY OTHER7500
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE1000
XI. NEIGHBOURHOOD SHOPPING750
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.17010
XIII. COVERED PARKING2000200
XIV. OPEN PARKING2005
XV. GARAGES00
XVI. SECURITY SYSTEM300
XVII. OTHER FACILITIES AS PER PROJECT REPORT500









Yes
Yes
CORPORATION BANK, CBB BRANCH, FAIZ ROAD, JHANDEWALAN, NEW DELHI-110005
510101005726262
CORP0000447
110017012
0447
Mr. Manish Garg (Director) and/or Mr. Chander Shekhar Bansal (Director)
Enclosed











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
No
No
No
No
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. SANCTION PLANALREADY BEEN OBTAINED31-10-2013
II. HEIGHT NOC FROM AIRPORT AUTHORITY OF INDIAALREADY BEEN OBTAINED05-12-2013
III. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED17-10-2014
IV. FOREST NOCALREADY BEEN OBTAINED25-04-2014
V. POLLUTION NOCALREADY BEEN OBTAINED05-03-2015








Yes


Yes


Agreement Enclosed







WHITE LILY, SECTOR-8, VILLAGE KAMASPUR, SONEPAT, HARYANA
9.262
578
0
360
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
01820017000
Cost of the apartments092008200
Cost of the infrastructure045004300
Others costs045004500


11600 Lakhs
4800 Lakhs
4500 Lakhs
700 Lakhs
Yes
31-12-2018
07-03-2019










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSE• VITRIFIED TILES IN DRAWING ROOM, BED ROOMS • GRANITE FLOORING N COMMON AREA AND STAIR CASES • WOODEN FLOORING IN MASTER BED ROOM
2WALL FINISHING DETAILS• OIL BOUND DISTEMPER ON INTERNAL WALLS • TEXTURE PAINT ON EXTERNAL WALLS
3KITCHEN DETAILS• STAINLESS STEEL SINK • GRANITE COUNTER • GLAZED TILE DADO ON WALL UPTO 2 FEET OVER COUNTER • CERAMIC TILES FLOORING
4BATHROOM FITTINGS• ANTI SKID CERAMIC TILES • CP FITTINGS BY JAQUAR OR EQUIVALENT • CHINA WARE BY HIND WARE OR EQUIVALENT • GLAZED CERAMIC TILES ON WALLS UPTO 7 FEET
5WOOD WORK ETC• EXTERNAL UPVC/ALUMINUM DOOR & WINDOWS WITH GLAZING • INTERNAL – MASONITE SKIN DOORS • MAIN GATE – MASONITE SKIN DOORS
6DOORS AND WINDOS FRAMES• 15 DOORS AND FRAMES • 2100*1000 • 2100*900 • 2100*950
7GLASS WORKIN UPVC/ALUMINUM DOORS AND WINDOWS
8ELECTRIC FITTINGSCOPPER WIRES, SHEET & SWITCHES, MCBS ETC.
9CONDUCTING AND WIRING DETAILSPVC CONDUITING & COPPER WIRE
10CUPBOARD DETAILSNOT APPLICABLE
11WATER STORAGEUGWT & OHWT
12LIFT DETAILS10 LIFTS, CAPACITY 13-15 PERSONS 11 LIFTS, CAPACITY 13-15 PERSONS
13EXTERNAL GLAZINGS• UPVC/ALUMINUM DOORS & WINDOW WITH GLAZING
13.1WINDOWS/GLAZINGS• UPVC/ALUMINUM DOORS & WINDOW WITH GLAZING
14DOORS• MAIN GATE – MASONITE SKIN DOORS • INTERNAL – MASONITE SKIN DOORS
14.1MAIN DOORS• MAIN GATE – MASONITE SKIN DOORS
14.2INTERNAL DOORS• INTERNAL – MASONITE SKIN DOORS
15AIR CONDITIONINGNOT APPLICABLE
16ELECTRICAL FITTINGSCOPPER WIRES, SHEET & SWITCHES, MCBS ETC.
17CNG PIPE LINEPNG BY GAIL
18PROVISION OF WIFI AND BROADBAND FACILITYYES
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURE PAINT ON EXTERNAL WALLS
20INTERNAL FINISHINGOIL BOUND DISTEMPER
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSOIL BOUND DISTEMPER
1 . 3 CEILINGOIL BOUND DISTEMPER
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORWOODEN FLOORING
2 . 2 WALLSOIL BOUND DISTEMPER
2 . 3 CEILINGOIL BOUND DISTEMPER
2 . 4 MODULAR WARDROBESNOT APPLICABLE
3 . MASTER TOILET
3 . 1 FLOORANTI SKID CERAMIC TILES
3 . 2 WALLSGLAZED CERAMIC TILES UPTO 7 FT HEIGHT
3 . 3 CEILINGOIL BOUND DISTEMPER
3 . 4 COUNTERSGRANITE
3 . 5 SANITARY WARE/CP FITTINGSCP FITTING BY JAGUAR OR EQUIVALENT AND CHINA WARE BY HIND WARE OR EQUIVALENT
3 . 6 FITTING/FIXTURESWASH BASIN, EWC ANGLE VALVE, DIVERTOR, BIB COCK ETC.
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSOIL BOUND DISTEMPER
4 . 3 CEILINGOIL BOUND DISTEMPER
4 . 4 WARDROBESNOT APPLICABLE
5 . TOILET
5 . 1 FLOORANTI SKID CERAMIC TILES
5 . 2 WALLSGLAZED CERAMIC TILES UPTO 7 FT HEIGHT
5 . 3 CEILINGOIL BOUND DISTEMPER
5 . 4 COUNTERSGRANITE
5 . 5 SANITARY WARE/CP FITTINGSCP FITTING BY JAGUAR OR EQUIVALENT AND CHINA WARE BY HIND WARE OR EQUIVALENT
5 . 6 FIXTURESWASH BASIN, EWC ANGLE VALVE, DIVERTOR, BIB COCK ETC.
6 . KITCHEN
6 . 1 FLOORCERAMIC TILES
6 . 2 WALLSGLAZED CERAMIC TILES UPTO 2 FT HEIGHT FROM COUNTER
6 . 3 CEILINGOIL BOUND DISTEMPER
6 . 4 COUNTERSGRANITE
6 . 5 FIXTURESMODULAR KITCHEN BELOW COUNTER
6 . 6 KITCHEN APPLIANCESSTAINLESS STEEL SINK, MIXTURE ETC.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORVITRIFIED TILES
7 . 2 WALLS & CEILINGOIL BOUND DISTEMPER
7 . 3 TOILETAS PER ABOVE
7 . 4 BALCONYCERAMIC TILES
8 . SIT-OUTS
8 . 1 FLOORGRANITE
8 . 2 WALLS & CEILINGOIL BOUND DISTEMPER
8 . 3 RAILINGSMS RAILINGS
8 . 4 FIXTURESNOT APPLICABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.09-07-2019 View Document
2SITE PLAN10-07-2019 ------
3CASH FLOW STATEMENT OF THE PROPOSED PROJECT10-07-2019 View Document
4IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN09-07-2019 View Document
5COPY OF LICENSE ALONG WITH SCHEDULE OF LAND09-07-2019 View Document
6NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT09-07-2019 View Document
7A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS09-07-2019 View Document
8ZONING PLAN09-07-2019 View Document
9DEMARCATION PLAN09-07-2019 View Document
10DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD10-07-2019 View Document
11BALANCE SHEET FOR YEAR ENDED 31.03.201809-07-2019 ------
12BALANCE SHEET FOR YEAR ENDED 31.03.201709-07-2019 ------
13BALANCE SHEET FOR YEAR ENDED 31.03.201609-07-2019 ------
14DRAFT ALLOTMENT LETTER10-07-2019 ------
15DRAFT OF AGREEMENT TO SELL10-07-2019 ------
16IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN10-07-2019 View Document
17BOARD RESOLUTION10-07-2019 ------
18PROMOTER NAME CHANGE APPROVAL16-11-2021 ------












Sr. No.Document DescriptionDate of Document UploadView Document
1 RC Uploaded 01-03-2023 View Document
2 RC Uploaded 01-03-2023 View Document
3 RC APPROVED 06-11-2023 View Document
4 RC APPROVED 02-05-2024 View Document