12-Apr-2022 |
DISPOSED |
On the last date of hearing
dated 15.02.2022, the complainant was
allowed to file a rectification application against the order dated 22.10.2021
within a period of four weeks with an advance copy to the respondent but no rectification
application has been filed by the complainant till date. The counsel for the
complainant during proceedings today
submitted that they are not filing any rectification application but seeking
clarification regarding delayed possession charges whether payable from the due
date of possession till possession actually taken over by the complainant
although without occupation certificate. The matter be referred to Director
Town and Country Planning. There is violation of Haryana Building Code, as the
builder has offered possession without obtaining OC. The director may initiate
legal proceedings against the promoter.
The DTCP is also advised to dispose of application of the promoter for grant of
occupation certificate and after levying the compounding fees as per applicable
rules from the promoter-respondent. The
complainant has already taken over possession, accordingly from the date he has
taken over possession, he cannot be allowed delayed possession charges.
Although the possession has been offered wrongly by the respondent as mentioned
above. However, the complainant shall be entitled for DPC from the due date of possession till actual
taking over the possession. To that
extent, the matter is clarified.
Complaint stands disposed of.
Detailed order will follow. File be consigned to the registry.
|
K K KHANDELWAL VIJAY KUMAR GOYAL |
View Order |
22-Apr-2022 |
15-Feb-2022 |
PENDING |
MATTER IS ADJOURNED TO 12.04.2022. |
K K KHANDELWAL VIJAY KUMAR GOYAL |
View Order |
04-Mar-2022 |
17-Dec-2021 |
PENDING |
Vide letter dated 09.12.2021 received from
Shri Anil Kumar Yadav, Advocate-Chairman Election Committee, District Bar
Association Gurgaon, the annual election for the year 2021-2022 of District Bar
Association Gurgaon are going to be held
today 0n 17.12.2021 in the judicial complex, as per decision of Election
Committee constituted by the Bar Council of Punjab & Haryana and the work
in the District Courts would remain suspended today.
In view of above, the matter is adjourned to 15.02.2022 for the purpose
already fixed. |
K K KHANDELWAL VIJAY KUMAR GOYAL |
View Order |
17-Dec-2021 |
22-Oct-2021 |
PENDING |
The present complaint has been received on
10.11.2020 and the reply was received on 15.01.2021
Succinct facts of
the case are as under:
Sr.
No.
Particulars
Details
1.
Name
of the project
Gurgaon
21 Next
2.
Unit
No.
904,9th
Floor, Tower A,
Super Area-2337.18 sq. ft.
3.
Addendum
letter dated 06.04.2011
1102,
tower A,
Super
Area-2408.23 sq. ft
3.
Date
of allotment
N/A
4.
Date
of builder buyer agreement
11.04.2009
Note:
Copy of the agreement duly executed by both parties bears stamp date of –
11.04.2009
5.
Possession
clause
10.1 Schedule for possession of
the said apartment
The
company based on its present plans and estimates and subject to all just
exceptions, contemplates to complete construction of the said building /
said
apartment within a period of three years from the date of execution of this
agreement unless there shall be delay or there shall be failure due to
reasons mentioned in clauses (11.1),(11.2),(11.3) and clause (39) or due to
failure of allottee(s) to pay in time the price of the said apartment along
with all other charges and dues in accordance with the schedule of payments
given in annexure iii or as per the demands raised by the company from time
to time or any failure on the part of the allottee(s) to abide by any of the
terms or conditions of this agreement. (emphasis supplied)
7.
Due
date of possession
11.04.2012
8.
Subsequent
allottee
22.02.2011
9.
Occupation
certificate
Not
obtained
10.
Offer
of possession
04.11.2016
11.
Handing
over the possession
21.11.2016
The complainant has sought following reliefs:
1.
Direct the respondent to obtain occupation certificate tower ‘A’ and
issue fresh offer of possession letter to the complainants.
There is nothing on the record to
show that the respondent has applied for granting occupation certificate of the
particular tower of the project in which the allotted unit of the complainant
is situated. So, in such a situation no direction can be given to the
respondent to issue fresh offer of possession when the same has already been
taken by the complainant admittedly on 21.11.2016. Both the respondent as well
as complainant are at fault. The respondent has given the possession of unit
without obtaining OC which is compoundable offer. The complainant has taken
over possession knowing fully well that OC has not been obtained by the
promoter. The complainant is enjoying the possession of the unit. The promoter
shall have to certainly obtain the OC from the competent authority. The matter
be referred to DTCP for initiating action against the builder for not obtaining
OC within the license period and also
offering possession without OC.
2.
Direct the
respondent to register the conveyance deed and transfer title in favour of the
complainants upon receipt of occupation certificate, in accordance with section
17 of RERA, 2016.
When the respondent has not obtained
occupation certificate of the tower of the allotted unit, then the question of
giving a direction to it for execution of conveyance deed does not arise.
3.
Direct the respondent to pay interest charges on account of IBMS amount
paid by the complainant.
A perusal of the statement of account
show that the complainant has already paid a sum of Rs. 1,19,500/- as IBMS with
the respondent/builder beside other charges. There is nothing on the record to
show that any resident welfare association has been formed. Moreover, in the
absence of occupation certificate, the builder cannot validly transfer
ownership of common areas to the resident welfare association and the amount
collected as IBMS. However, as an when occupation certificate of the tower is received,
then within three months the respondent/builder is obligated to transfer the
amount of IBMS collected from the allottees along with interest as per laws.
4.
Impose a penalty upon the respondent to the extent of upto 5% of the
total cost of the project for violation of section 11(4)(b) of RERA, 2016.
The obligation of the builder buyer agreement as has been alleged to
have been violated are for a period prior to coming into force of RERA
accordingly penal proceeding cannot be initiated. The complainant may file a
fresh application for any violation alleged to have been done for the
obligations post implementation of RERA.
Order
reserved.
Matter to
come up on 17.12.2021 |
K K KHANDELWAL SAMIR KUMAR VIJAY KUMAR GOYAL |
View Order |
29-Oct-2021 |
09-Sep-2021 |
PENDING |
It has been brought to the notice of the
Authority that the unit of the complainant is located in the project, namely, “Gurgaon
21 Next” instead of Vatika India Next. The
said project is not registered with the Authority. Counsel for the respondent
is directed to apply for registration of the said project within a period of 10
days and submit due diligence report otherwise
forensic audit shall be ordered.
Matter to come up on
22.10.2021. |
VIJAY KUMAR GOYAL SAMIR KUMAR |
View Order |
15-Sep-2021 |
28-Jul-2021 |
PENDING |
Part arguments heard.
Counsel for the respondent
has stated at bar that the matter is with regard to subsequent allottee.
Adjourned to 09.09.2021 for
final arguments. |
VIJAY KUMAR GOYAL SAMIR KUMAR |
View Order |
04-Aug-2021 |
12-May-2021 |
PENDING |
Matter to come up on 28.07.2021 for further proceedings. |
K K KHANDELWAL SAMIR KUMAR VIJAY KUMAR GOYAL |
View Order |
19-May-2021 |
01-Apr-2021 |
PENDING |
Reply has already been filed by the respondent. Today the case was fixed for arguments but the counsel for the complainant has requested for an adjournment for addressing arguments. On his request, matter is adjourned to 12.05.2021 for final arguments. |
VIJAY KUMAR GOYAL SAMIR KUMAR |
View Order |
23-Apr-2021 |
11-Feb-2021 |
PENDING |
Arguments
heard.
Counsel for the respondent
alongwith authorized representative were asked to submit the circumstances under which the
possession was offered without part completion certificate/completion
certificate. Whether such possession could be taken as the possession under the
Haryana Development and Regulation of Urban Areas Act, 1975.
Authorized representative is directed to appear before the authority
to explain the status w.r.t completion of the project, completion certificate
obtained from the DTCP, offer of possession and charging of maintenance amount
etc. on the next date of hearing.
Director of the company alongwith Architect and Planner of the company
shall also appear before the authority
on the next date of hearing to explain the above mentioned facts in detail and
produce all the relevant documents.
Respondent is directed to
submit the list of all vacant/un-allotted plots in the category of 360 square
yards on an affidavit in the registry within 15 days.
Complainant is directed to
visit the site within 15 days and sort
out the matter amicably and submit
written submissions.
Respondent is directed to send
letter/mail to the complainant for allotting an alternative plot within 15 days
to sort out the matter.
Registry is directed to do
the needful.
Matter to come up on
01.04.2021. |
K K KHANDELWAL SAMIR KUMAR SUBHASH CHANDER KUSH |
View Order |
23-Feb-2021 |
22-Dec-2020 |
FIRST HEARING |
Coram not complete. Matter is listed for 11.02.2021
for the purpose as already fixed. |
K K KHANDELWAL SAMIR KUMAR SUBHASH CHANDER KUSH |
View Order |
28-Dec-2020 |