Quarterly Schedules

HRERA Gurugram
Project Registration Number : GGM/458/190/2021/26 DATED 22.06.2021
Project Name : HABITAT PRIME
Project Number : RERA-GRG-806-2021
Project Type : NEW
Report Online Submission Date : 15-Apr-2022
S.No.ParticularsAmount
(In Lakhs)
1Cost of the land (if included in the estimated cost)3496.40
2Estimated cost of construction of apartments11450
3Estimated cost of infrastructure & other structure563.92
4Other cost including EDC taxes, levies, etc3755.96
Total19266.28



Name of the approvalStatusDate
Demarcation PlanObtained Approval on16-10-2020
Zoning PlanObtained Approval on26-11-2020
Service PlansObtained Approval on14-06-2021
Electricity PlansHave not applied till dateN/A
Site PlansObtained Approval on24-02-2021
Building PlansObtained Approval on24-02-2021
FIre NOCObtained Approval on02-06-2021
Total Expenditure on the project19266.28
Expenditure made upto the date of Registration3712.12



EDC due as on the date of Registration118.35

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0
2Amount collected from allottees against booked plots and/or apartments0
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates3872.40
5Any other receipt0
Total3872.40



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments167.35
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc3705.05
Total3872.40
Balance15393.88



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account0
3Amount withdrawn during the quarter0
4Balance at the end of the quarter0
Total Apartments in the colony844
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
12BHK SOLD/ ALLOTTED DURING THE QUARTER0
23BHK SOLD/ ALLOTTED DURING THE QUARTER0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1PARKING SOLD/ ALLOTTED DURING THE QUARTER0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments106.71
3EDC, IDC, etc0
4Others Expenditure53.57



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date77.89
2EDC due as on date118.35
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 03-11-2021  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 03-11-2021  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 03-11-2021  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 03-11-2021  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 03-11-2021  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0.00
2Amount collected from allottees against booked plots and/or apartments4479.85
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total4479.85



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments808.58
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc3847.70
Total4656.28
Balance14610



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter0
2Amount deposited in Escrow Account3174.57
3Amount withdrawn during the quarter1268.82
4Balance at the end of the quarter1905.75
Total Apartments in the colony844
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
12 BHK (TYPE 1) SOLD/ BOOKED DURING THE QUARTER88
22 BHK (TYPE 1) CANCELLED/ SURRENDERED DURING THE QUARTER8
32 BHK (TYPE 2) SOLD/ BOOKED DURING THE QUARTER72
42 BHK (TYPE 2) CANCELLED/ SURRENDERED DURING THE QUARTER4
52 BHK+UTILITY SOLD/ BOOKED DURING THE QUARTER340
62 BHK+UTILITY CANCELLED/ SURRENDERED DURING THE QUARTER18
73 BHK SOLD/ BOOKED DURING THE QUARTER344
83 BHK CANCELLED/ SURRENDERED DURING THE QUARTER20



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TWO WHEELER PARKING BOOKED DURING THE QUARTER844
2TWO WHEELER PARKING CANCELLED/ SURRENDERED DURING THE QUARTER50



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments747.94
3EDC, IDC, etc125
4Others Expenditure71.22



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date202.87
2EDC due as on date114.59
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 14-01-2022  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 14-01-2022  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 14-01-2022  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 14-01-2022  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 14-01-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance16
2Amount collected from allottees against booked plots and/or apartments765.29
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total781.29



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments1609.28
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc3985.28
Total5594.56
Balance13671.72



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter1905.75
2Amount deposited in Escrow Account556.30
3Amount withdrawn during the quarter1011
4Balance at the end of the quarter1451.05
Total Apartments in the colony844
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
12BHK {TYPE 1} ALLOTTED DURING THE QUARTER4
22BHK {TYPE 1} CANCELLED/ SURRENDERED DURING THE QUARTER7
32BHK {TYPE 2} ALLOTTED DURING THE QUARTER3
42BHK {TYPE 2} CANCELLED/ SURRENDERED DURING THE QUARTER3
52BHK+UTILITY ALLOTTED DURING THE QUARTER29
62BHK+UTILITY CANCELLED/ SURRENDERED DURING THE QUARTER33
73BHK ALLOTTED DURING THE QUARTER12
83BHK CANCELLED/ SURRENDERED DURING THE QUARTER19



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TWO WHEELER PARKING BOOKED DURING THE QUARTER48
2TWO WHEELER PARKING CANCELLED/ SURRENDERED DURING THE QUARTER62



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments1548.64
3EDC, IDC, etc245
4Others Expenditure88.80



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date322.87
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-04-2022  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-04-2022  View 
3 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-04-2022  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-04-2022  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-04-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance45.59
2Amount collected from allottees against booked plots and/or apartments2507.15
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total2552.74



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments2358.80
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc4112.44
Total6471.24
Balance12795.04



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter1451.05
2Amount deposited in Escrow Account1747.55
3Amount withdrawn during the quarter1577.20
4Balance at the end of the quarter1621.40
Total Apartments in the colony844
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
12BHK {TYPE 1} ALLOTTED DURING THE QUARTER0
22BHK {TYPE 1} CANCELLED/ SURRENDERED DURING THE QUARTER2
32BHK {TYPE 2} ALLOTTED DURING THE QUARTER2
42BHK {TYPE 2} CANCELLED/ SURRENDERED DURING THE QUARTER2
52BHK+UTILITY ALLOTTED DURING THE QUARTER4
62BHK+UTILITY CANCELLED/ SURRENDERED DURING THE QUARTER2
73BHK ALLOTTED DURING THE QUARTER8
83BHK CANCELLED/ SURRENDERED DURING THE QUARTER4



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TWO WHEELER PARKING BOOKED DURING THE QUARTER 14
2TWO WHEELER PARKING CANCELLED/ SURRENDERED DURING THE QUARTER 10



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments2298.16
3EDC, IDC, etc354.04
4Others Expenditure106.92



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date322.87
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 15-07-2022  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 15-07-2022  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 15-07-2022  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 15-07-2022  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 15-07-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance0
2Amount collected from allottees against booked plots and/or apartments434.41
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total434.41



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments3382.98
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc4130.71
Total7513.69
Balance11752.59



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter1621.40
2Amount deposited in Escrow Account377.39
3Amount withdrawn during the quarter1009.54
4Balance at the end of the quarter989.25
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



Total Apartments in the colony844
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
12BHK (TYPE 1) ALLOTTED DURING THE QUARTER0
22BHK (TYPE 1) CANCELLED/ SURRENDERED DURING THE QUARTER1
32BHK (TYPE 2) ALLOTTED DURING THE QUARTER1
42BHK (TYPE 2) CANCELLED/ SURRENDERED DURING THE QUARTER2
52BHK+UTILITY ALLOTTED DURING THE QUARTER3
62BHK+UTILITY CANCELLED/ SURRENDERED DURING THE QUARTER5
73BHK ALLOTTED DURING THE QUARTER3
83BHK CANCELLED/ SURRENDERED DURING THE QUARTER3



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TWO WHEELER PARKING BOOKED DURING THE QUARTER 7
2TWO WHEELER PARKING CANCELLED/ SURRENDERED DURING THE QUARTER 11



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments3322.34
3EDC, IDC, etc354.04
4Others Expenditure125.19



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date431.93
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 14-10-2022  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 14-10-2022  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 14-10-2022  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 14-10-2022  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 14-10-2022  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance49.55
2Amount collected from allottees against booked plots and/or apartments2396.27
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total2445.82



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments4103.79
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc4249.35
Total8353.14
Balance10913.14



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter989.25
2Amount deposited in Escrow Account1734.15
3Amount withdrawn during the quarter1229.44
4Balance at the end of the quarter1493.97
Total Apartments in the colony844
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
1APARTMENTS BOOKED DURING THE QUARTER0
23 BHK CANCELLED/ SURRENDERED DURING THE QUARTER1



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TWO WHEELER PARKING BOOKED DURING THE QUARTER 0
2TWO WHEELER PARKING CANCELLED/ SURRENDERED DURING THE QUARTER 1



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments4043.15
3EDC, IDC, etc459.29
4Others Expenditure138.58



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date537.18
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 13-01-2023  View 
2 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 13-01-2023  View 
3 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 13-01-2023  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 13-01-2023  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 13-01-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2
2Amount collected from allottees against booked plots and/or apartments317.36
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total319.36



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments5077.83
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc4261.30
Total9339.13
Balance9927.15



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter1493.97
2Amount deposited in Escrow Account230.65
3Amount withdrawn during the quarter923.56
4Balance at the end of the quarter801.06
Total Apartments in the colony844
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
12BHK {TYPE 1} BOOKED DURING THE QUARTER0
22BHK {TYPE 2} BOOKED DURING THE QUARTER0
32BHK+UTILITY BOOKED DURING THE QUARTER0
42BHK+UTILITY CANCELLED/ SURRENDERED DURING THE QUARTER1
53BHK BOOKED DURING THE QUARTER0
63BHK CANCELLED/ SURRENDERED DURING THE QUARTER1



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TWO WHEELER PARKING BOOKED DURING THE QUARTER0
2TWO WHEELER PARKING CANCELLED/ SURRENDERED DURING THE QUARTER2



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments5017.19
3EDC, IDC, etc459.29
4Others Expenditure150.53



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date537.18
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 17-04-2023  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 17-04-2023  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 17-04-2023  View 
4 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 17-04-2023  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 17-04-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance3.32
2Amount collected from allottees against booked plots and/or apartments2479.16
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total2482.48



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments5872.53
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc4275.97
Total10148.50
Balance9117.78



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter801.06
2Amount deposited in Escrow Account1772.34
3Amount withdrawn during the quarter2569.90
4Balance at the end of the quarter3.50
Total Apartments in the colony844
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
12BHK (TYPE 1) BOOKED DURING THE QUARTER0
22BHK (TYPE 1) CANCELLED/ SURRENDERED DURING THE QUARTER0
32BHK (TYPE 2) BOOKED DURING THE QUARTER0
42BHK (TYPE 2) CANCELLED/ SURRENDERED DURING THE QUARTER0
52BHK+UTILITY BOOKED DURING THE QUARTER0
62BHK+UTILITY CANCELLED/ SURRENDERED DURING THE QUARTER1
73BHK BOOKED DURING THE QUARTER0
83BHK CANCELLED/ SURRENDERED DURING THE QUARTER0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TWO WHEELER PARKING BOOKED DURING THE QUARTER0
2TWO WHEELER PARKING CANCELLED/ SURRENDERED DURING THE QUARTER1



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments5811.89
3EDC, IDC, etc459.29
4Others Expenditure165.20



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date537.18
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 17-07-2023  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 17-07-2023  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 17-07-2023  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 17-07-2023  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 17-07-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance39.99
2Amount collected from allottees against booked plots and/or apartments487.36
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates800.00
5Any other receipt0
Total1327.35



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments6989.63
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc804.50
Total11290.53
Balance7975.75



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter3.50
2Amount deposited in Escrow Account346.02
3Amount withdrawn during the quarter328.35
4Balance at the end of the quarter21.17
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



Total Apartments in the colony844
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
12BHK + UTILILITY BOOKED DURING THE QUARTER6
22BHK + UTILILITY CANCELLED/SURRENDER DURING THE QUARTER0
32BHK (TYPE-2) BOOKED DURING THE QUARTER1
42BHK (TYPE-2) CANCELLED/SURRENDER DURING THE QUARTER0
52BHK (TYPE-1) BOOKED DURING THE QUARTER6
62BHK (TYPE-1) CANCELLED/ SURRENDER DURING THE QUARTER0
73BHK UNITS BOOKED DURING THE QUARTER5
83BHK UNITS CANCELLED/ SURRENDER DURING THE QUARTER0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TWO WHEELER PARKING BOOKED DURING THE QUARTER18
2TWO WHEELER PARKING CANCELLED/ SURRENDER DURING THE QUARTER0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments6928.99
3EDC, IDC, etc459.29
4Others Expenditure190.13



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date537.18
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 13-10-2023  View 
2 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 13-10-2023  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 13-10-2023  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 13-10-2023  View 
5 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 13-10-2023  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance50.11
2Amount collected from allottees against booked plots and/or apartments2488.39
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt0
Total2538.50



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments8199.77
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc926.91
Total12623.08
Balance6643.20



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter21.17
2Amount deposited in Escrow Account1779.41
3Amount withdrawn during the quarter1305.83
4Balance at the end of the quarter494.75
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



Total Apartments in the colony844
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
12BHK + UTILILITY BOOKED DURING THE QUARTER0
22BHK + UTILILITY CANCELLED OR SURRENDER DURING THE QUARTER0
32BHK, TYPE-1 BOOKED DURING THE QUARTER0
42BHK, TYPE-1 SURRENDER OR CANCELLED DURING THE YEAR0
52BHK, TYPE-2 BOOKED DURING THE QUARTER0
62BHK, TYPE-2 CANCELLED OR SURRENDER DURING THE QUARTER0
73BHK UNITS BOOKED DURING THE QUARTER0
83BHK UNITS CANCELLED OR SURRENDER DURING THE QUARTER0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TWO WHEELER PARKING BOOKED DURING THE QUARTER0
2TWO WHEELER PARKING CANCELLED OR SURRENDER DURING THE QUARTER0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments8139.13
3EDC, IDC, etc563.97
4Others Expenditure207.86



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date757.04
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 12-01-2024  View 
2 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 12-01-2024  View 
3 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 12-01-2024  View 
4 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 12-01-2024  View 
5 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 12-01-2024  View 

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance17.10
2Amount collected from allottees against booked plots and/or apartments451.91
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates0
5Any other receipt7
Total476.01



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments9262.67
2Expenditure on infrastructure & other structure0
3Other costs including EDC, taxes, etc949.20
Total13708.27
Balance5558.01



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter494.75
2Amount deposited in Escrow Account333.72
3Amount withdrawn during the quarter788.25
4Balance at the end of the quarter40.22
Total Plots in the colony0
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
10



Total Apartments in the colony844
Apartments sold upto the date of Registration0



S.No.Type/SizeApartments Sold in the Quarter
12BHK + UTILILITY BOOKED DURING THE QUARTER0
22BHK + UTILILITY CANCELLED/SURRENDER DURING THE QUARTER0
32BHK + TYPE 1 BOOKED DURING THE QUARTER0
42BHK + TYPE 1 CANCELLED/SURRENDER DURING THE QUARTER0
52BHK + TYPE 2 BOOKED DURING THE QUARTER0
62BHK + TYPE 2 CANCELLED/SURRENDER DURING THE QUARTER2
73BHK UNITS BOOKED DURING THE QUARTER0
83BHK UNITS CANCELLED/SURRENDER DURING THE QUARTER0



Total Garages in the colony0
Garages sold upto the date of Registration0



S.No.Type/SizeGarages Sold in the Quarter
1TWO WHEELER PARKING SOLD DURING THE QUARTER0
2TWO WHEELER PARKING CANCELLED OR SURRENDER DURING THE QUARTER0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure0
2Apartments9202.03
3EDC, IDC, etc568.53
4Others Expenditure225.59



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date757.04
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 11-04-2024  View 
2 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 11-04-2024  View 
3 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 11-04-2024  View 
4 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 11-04-2024  View 
5 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 11-04-2024  View