11-Feb-2025 |
Sh.
Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed
about the facts of the case.
Sh.
Nitin Sharma (AR) and Sh. Aman Sharma (AR) are present on behalf of the
promoter.
No objection has
been received in the Authority from any allottee in respect of public notice
dated 29.01.2025 regarding revision in the building plans.
Approved
as proposed subject to rectification of deficiencies mentioned above including
correction in A-H form, Online DPI and deposit of penalty of Rs. 50 lakhs
imposed for issuing advertisement before RERA registration in violation of Section
3 of the Act, 2016.
The
Registration Certificate shall be issued after submission of remaining
deficiencies mentioned above including correction in A-H form, Online DPI and deposit
of penalty of Rs 50 lakhs for violation of Section 3 of the Act. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
10-Feb-2025 |
The matter is adjourned and to come up on 11.02.2025 at 03:00 PM. |
ADJOURNMENT |
--- |
27-Jan-2025 |
Sh.
Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed
about the facts of the case.
Sh.
Aman Sharma (AR), Sh. Nitin Sharma (AR) and Sh. Vidya Sagar (AR) are present on
behalf of the promter.
A
public notice of ten days for inviting objections from the
allottees be issued in at least three prominent newspapers (Two English and One
Hindi) of wide circulation regarding non creation of 3rd party
rights in the project.
An
affidavit regarding sharing of revenue with land owners shall be submitted.
Further, a show cause notice for violation of section 3 of the Act, 2016 was
issued to the promoter in complaint No. 6238 of 2024 for which the reply dated
27.12.2024 and 22.01.2025 have been submitted. However, even as on date, numerous
websites are promoting the unregistered project on internet. The promoter is
again advised not to indulge or allow any other entity for sale of units in the
unregistered project failing which legal consequences shall follow.
Matter
be put up on file with regard to imposition of penalty for violation of section
3 of the Act, 2016.
The
matter to come up on 10.02.2025. |
ADJOURNMENT |
View Order |
13-Jan-2025 |
The matter is adjourned and to come up on 27.01.2025. |
EXAMINATION BY AUTHORITY |
View Order |