08-Jan-2025 |
Sh.
Ashish Kush, Planning Executive and Ms Asha, Chartered Accountant briefed about
the facts of the case.
Sh.
Purushottam Grover (AR), Ms. Priyanka Miglani (AR) and Sh. Anitesh Singh (AR)
are present on behalf of the promoter and states that after seeking public
objections, DTCP Haryana has revised the building plans alongwith the phasing
plan. However, there is no change in the Phase 1 and the Building plans of part area of Phase 3 (EWS) has
been revised as the proportionate EWS units for Phase 2 have been
proposed along with the EWS units for Phase 1 as per requirement of conditions
of license. Further, the promoter also stated that no 3rd party
rights have been created on the EWS Block.
A public notice was
issued in three
newspapers i.e., Hindustan Times on 28.12.2024, Times of India on 29.12.2024
and Dainik Jagran on 29.12.2024 for inviting objections from the
allottees regarding revision in the building plans. No objections have been received in the
Authority in repect of same. Further, there are total 82 allottees out of which
18 units are allotted to the landowner/collaborator. Out of 65 unique allottees,
the consent of 53 allottees has been submitted by the promoter which is more
than two-third consent.
Earlier, the part project was
registered vide registration no. 18 of 2024 wherein the Phase 1 and No phase
comprising EWS component have been registered. Further, the building plans and
phasing plans has been revised and the promoter applied for the registration of
Phase 2 and Phase 3 including the EWS. However, since the EWS is registered in
the earlier registration certificate, the promoter shall apply for
amendment in the registration certificate no. 18 of 2024 incorporating the
changes.
The
promoter has submitted two DD’s vide no. 824830 dated 07.12.2024 and 824831 dated 07.12.2024 amounting
to Rs. 25 lakhs each as security amount for submission of Fire Scheme approval
and Service Plans and Estimates within a period of four months from the date of
grant of registration certificate.
The
environment clearance has expired on 23.12.2024, the promoter stated that they
have applied for the renewal of same. The promoter shall submit the renewed
Environment Clearance within a period of four months from the date of grant of
registration certificate.
Approved
as proposed subject to rectification of deficiencies mentioned above including correction
in A-H form and Online DPI.
The Registration
Certificate shall be issued after submission of remaining deficiencies
mentioned above including correction in A-H form and Online DPI. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |