Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
SUMEDHA RESIDENCY Sector 01 GURUGRAM Farrukhnagar Corre Infrastructure & Developers
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/804/536/2024/31 DATED 27.03.2024 RERA-GRG-1456-2023 27-Oct-2023 12-Oct-2023 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 14-Nov-2023 HARERA/GGM/RPIN/666 DISPATCHED ONLINE
First hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/804/536/2024/31 DATED 27.03.2024 21-May-2024 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
27-Mar-2024 Ms. Neeraj Gautam, Associate Architectural Executive briefed about the facts of the project. Sh. Ashok Singh (AR) is present on behalf of the promoter. Approved as proposed.  APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
11-Mar-2024 Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Alok Singh (AR) and Sh. Anand P. Sachdev (AR) are present on behalf of the promoter. The AR of the promoter states that the pending deficiencies will be submitted. The matter to come up on 27.03.2024. ADJOURNMENT ---
26-Feb-2024 Ar. Neeraj Gautam (Associate Architectural Executive) and Mr. Ashish Dubey (Chartered Accountant) briefed about the facts of the case. Sh. Anand P. Sachdeva (AR) is present on behalf of the promoter. The AR states that the zoning plan is under approval before DTCP and approved copy will be submitted within one week along with other deficiencies. The matter to come up on 11.03.2024. ADJOURNMENT ---
19-Feb-2024 ADJOURNMENT ---
12-Feb-2024 Ar. Neeraj Gautam (Associate Architectural Executive) and Mr. Ashish Dubey (Chartered Accountant) briefed about the facts of the case. Sh. Anand. P. Sachdeva is present on behalf of the promoter. AR of the promoter states that the approval of service plan estimates as well as the zoning plan are expected within next two days and will be submitted in the authority within  one week. In meanwhile the pending details and deficiencies in the documents shall be rectified. The matter to come up on 19.02.2024.  ADJOURNMENT View Order
29-Jan-2024 Ar. Neeraj Gautam (Associate Architectural Executive) and Mr. M. L. Sardana (Accountant) briefed about the facts of the case. Sh. Rajesh Kumar (AR) and Sh. Anand Prashar (AR) are present on behalf of the promoter. The AR states that approval of zoning plan is in the advance stage of approval with DTCP along with service plans and estimates for which the requisite BG has been submitted to DTCP. The AR further seeks two weeks’ time to submit the deficit documents including earmarking of the plots of landowners duly signed by all concerned parties and notarized as the application for transfer of license in favor of the developer has been withdrawn. The matter to come up on 12.02.2024 ADJOURNMENT View Order
08-Jan-2024 Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefed about the facts of the case. Sh. Anand Prashar (AR) is present on behalf of the promoter. The AR seeks two weeks’ time for submission of deficit approvals/documents which are in advance stage of approval in office of DGTCP. The matter to come up on 29.01.2024. ADJOURNMENT View Order
20-Nov-2023 Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefed about the facts of the case. None is present on the behalf of the promoter. No reply has been submitted by the promoter company till 16.11.2023 against the deficiencies conveyed by the authority through notice dated 14.11.2023. Therefore, in view of the same the matter is adjourned, and the next date of hearing will be conveyed after submission of reply of deficiencies already conveyed. Further, if no response is received from the promoter within next 4 weeks’ time, in that case the concerned official to put up the matter on file for issuance of show cause notice as to why their application for registration of project may not be rejected following the due procedure under the Act of 2016. EXAMINATION BY AUTHORITY View Order