27-Mar-2024 |
Ms. Neeraj
Gautam, Associate Architectural Executive briefed about the facts of the
project.
Sh. Ashok
Singh (AR) is present on behalf of the promoter.
Approved
as proposed. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
11-Mar-2024 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the project.
Sh.
Alok Singh (AR) and Sh. Anand P. Sachdev (AR) are present on behalf of the
promoter.
The
AR of the promoter states that the pending deficiencies will be submitted. The
matter to come up on 27.03.2024. |
ADJOURNMENT |
--- |
26-Feb-2024 |
Ar.
Neeraj Gautam (Associate Architectural Executive) and Mr. Ashish Dubey (Chartered
Accountant) briefed about the facts of the case.
Sh.
Anand P. Sachdeva (AR) is present on behalf of the promoter.
The
AR states that the zoning plan is under approval before DTCP and approved copy
will be submitted within one week along with other deficiencies.
The
matter to come up on 11.03.2024. |
ADJOURNMENT |
--- |
19-Feb-2024 |
|
ADJOURNMENT |
--- |
12-Feb-2024 |
Ar.
Neeraj Gautam (Associate Architectural Executive) and Mr. Ashish Dubey (Chartered
Accountant) briefed about the facts of the case.
Sh.
Anand. P. Sachdeva is present on behalf of the promoter.
AR
of the promoter states that the approval of service plan estimates as well as
the zoning plan are expected within next two days and will be submitted in the
authority within one week. In meanwhile
the pending details and deficiencies in the documents shall be rectified.
The
matter to come up on 19.02.2024. |
ADJOURNMENT |
View Order |
29-Jan-2024 |
Ar.
Neeraj Gautam (Associate Architectural Executive) and Mr. M. L. Sardana
(Accountant) briefed about the facts of the case.
Sh. Rajesh
Kumar (AR) and Sh. Anand Prashar (AR) are present on behalf of the promoter.
The
AR states that approval of zoning plan is in the advance stage of approval with
DTCP along with service plans and estimates for which the requisite BG has been
submitted to DTCP. The AR further seeks two weeks’ time to submit the deficit
documents including earmarking of the plots of landowners duly signed by all
concerned parties and notarized as the application for transfer of license in favor
of the developer has been withdrawn.
The
matter to come up on 12.02.2024 |
ADJOURNMENT |
View Order |
08-Jan-2024 |
Ar.
Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered
Accountant) briefed about the facts of the case.
Sh.
Anand Prashar (AR) is present on behalf of the promoter.
The
AR seeks two weeks’ time for submission of deficit approvals/documents which
are in advance stage of approval in office of DGTCP.
The
matter to come up on 29.01.2024. |
ADJOURNMENT |
View Order |
20-Nov-2023 |
Ar.
Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered
Accountant) briefed about the facts of the case.
None
is present on the behalf of the promoter.
No reply has been submitted by the
promoter company till 16.11.2023 against the deficiencies conveyed by the
authority through notice dated 14.11.2023. Therefore, in view of the same the
matter is adjourned, and the next date of hearing will be conveyed after
submission of reply of deficiencies already conveyed.
Further, if no response is received
from the promoter within next 4 weeks’ time, in that case the concerned
official to put up the matter on file for issuance of show cause notice as to
why their application for registration of project may not be rejected following
the due procedure under the Act of 2016. |
EXAMINATION BY AUTHORITY |
View Order |