| 23-Dec-2022 |
Sh.
Sumeet, Engineer Executive and Ms. Asha, Chartered Accountant briefed about the
facts of the project.
Sh. Abhijeet Singh (AR), Sh. Manik Sharma (AR), Sh. Bharat Vigmal(AR) and
Sh. Ayush Gupta (AR) are present on
behalf of the promoter.
The AR of the promoter states that the project is complete and CC is
already applied.
Approved as proposed. |
EXTENSION APPROVED |
View Order |
| 19-Dec-2022 |
The matter to come up on 23.12.2022 |
ADJOURNMENT |
View Order |
| 12-Dec-2022 |
The matter is adjourned to 19.12.2022 |
ADJOURNMENT |
View Order |
| 28-Nov-2022 |
The
authorized representative of the promoter is advised to rectify the
deficiencies and submit the deficit fee (if any) along with the deficit documents
apart from filing information in REP-I A to H format and online detailed
project information. Matter to come up
on 12.12.2022 |
EXAMINATION BY AUTHORITY |
View Order |