| 05-Dec-2022 |
Sh. Shashank Sharma, Associate Engineer Executive briefed
about the facts of the project.
Sh.
Anurag Srivastava (AR) is present on behalf of the promoter.
Approved
as proposed. Subject to payment of a penalty of Rs 5 Lakhs each for delayed
compliance of conditions of registration certificate i.e., failure to submit
fire scheme approval, EC and Approved service plan and estimates within the
time as directed by the Authority which otherwise have been subsequently
obtained.
For new allottees of unallotted units the promoter has
to clarify the payment plan in the advertisement itself which is mandatory. (Sanjeev
Kumar Arora)
Member, HARERA, Gurugram
(Ashok Sangwan)
Member, HARERA, Gurugram
(Vijay
Kumar Goyal)
Member,
HARERA, Gurugram
(Dr. K.K.
Khandelwal)
Chairman, HARERA, Gurugram
|
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
| 21-Nov-2022 |
Proceedings dated 21.11.2022
Sh. Shashank Sharma, Associate Engineer Executive briefed
about the facts of the project.
Sh.
Anurag Srivastava (GM) is present on behalf of the promoter.
The
promoter has submitted consent of 457 allottees out of 690 units allotted
making the same more than 2/3rd allottees for having revised the
building plans and hence a newspaper publication be made for information of all
concerned and objections if any within 10 days. The balance deficiencies have
also been conveyed to the promoter who assures that the same shall be removed
before the next date of hearing. The
matter to come up on 05.12.2022.
(Sanjeev
Kumar Arora)
Member, HARERA, Gurugram
(Ashok Sangwan)
Member, HARERA, Gurugram
(Vijay
Kumar Goyal)
Member,
HARERA, Gurugram
(Dr. K.K.
Khandelwal)
Chairman, HARERA, Gurugram
|
ADJOURNMENT |
View Order |
| 27-Oct-2022 |
The promoter is directed to rectify the deficiencies and submit the deficit fee if any. The matter is adjourned for 21.11.2022. |
ADJOURNMENT |
View Order |
| 26-Oct-2022 |
The coram is not complete. So the matter is adjourned for 27.10.2022. |
OBJECTION |
View Order |
| 11-Oct-2022 |
The major deficiencies are Zoning Plan,
Approved Building Plan, Approved service plan and estimates, Fire Scheme
approval, Non- encumbrance certificate, Mutation, Jamabandi and Aks- Shajra. The promoter is further advised to rectify the
deficiencies and submit the deficient document apart from filing information in
REP-I A to H format and detailed project information. Matter to come up on 26.10.2022. |
ADJOURNMENT |
View Order |
| 27-Sep-2022 |
Shashank AEE (Associate Architectural Executive) briefed about the facts of the project and following major deficiencies have pointed out i.e. (1)
Zoning Plan. (2)
Approved Building Plan. (3)
Approved service plan and estimates. (4)
Fire Scheme approval. (5)
Non- encumbrance certificate. (6) Mutation,
Jamabandi and Aks- Shajra. The matter is adjourned for 11.10.2022. |
ADJOURNMENT |
View Order |
| 05-Sep-2022 |
Proceedings
dated 05.09.2022
Sh. Shashank Sharma, Associate Engineer Executive briefed
about the facts of the project.
Sh.
Anurag Srivastava (GM) is present on behalf of the promoter. The applicant
promoter is required to rectify the deficiencies noticed by the Authority and a
copy of deficiencies be supplied to the AR today itself. Since there are
changes in the approved building plan and hence a consent of existing 2/3
allottees is also required to be submitted by the promoter along with issuance
of a public notice for objection if any.
The
matter to come up on 27.09.2022. |
EXAMINATION BY AUTHORITY |
View Order |