29-Jun-2020 |
Date of
Hearing : 22nd
June, 2020 online. Name of the
Promoter: M/s Experion
Developers Pvt.Ltd.
Name of the Project: Residential Floor Project
– “Zephyr at the Westerlies” Sector-108, Gurugram. (Seven Plots of 210 Sq.Mt. –
each plot stilt+4 floors i.e. 28 floors)
This project comprises of builder’s floor (stilt+4)
on seven floors of 200 sq.mt. each i.e. total 28 floors of builder’s floor. These
seven plots are part of 100.48 acres plotted colony where part completion of
46.257 acres vide Memo No. LC-2755 Vol-II-PA(SN)-2017/18284, dated 31st
July 2017 and part completion of 44.178
acres vide Memo No. LC-2755 Vol-II-PA(SN)-2017/10093, dated 22nd
March, 2018 were issued by Director Town & Country Planning. As far as
builder’s floor registration is concerned the authority decided to grant
registration certificate subject to submission of details of payment plan as
same has not been mentioned in the allotment letter. During online hearing the
authorized representative brought to the notice of the Authority that their
license has been renewed and copy shall be submitted immediately. The time
period for completion of the registered part of the project shall not exceed
the time granted in the renewal of the license. This case is not covered where
3rd party rights have been created on the plot but the promoter
himself is constructing the builder’s floors.
The Authority hereby take cognizance of the
fact that part completion certificates have been issued after publication of
the Haryana Real Estate (Regulation and Development) Rules, 2017. The
promoter’s attention is invited to section 2(1)(o)(ii) where that part of any
project for which part completion/completion, occupation certificate or part
thereof has been granted on or before publication of these rules i.e. 28th
July, 2017 are exempted from the definition of ongoing project, accordingly the
project comes within the definition of ongoing project and needs to be
registered. Furthermore, section 3(2)(b) provides that no registration of real
estate project shall be required where promoter has received completion
certificate for a real estate project prior to commencement of this Act.
Although, rules cannot supersede specific provision of the Act but keeping in
view the definition of ongoing project given in rule 2(o) also the project
needs to be registered. The concerned planning assistant to issue notice to the
promoter.
Sd/-
Dr.
K.K.Khandelwal
Chairman
Sd/-
Samir
Kumar
Member
Sd/-
S.C.
Kush
Member. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
22-Jun-2020 |
Date of
Hearing : 22nd
June, 2020 online. Name of the
Promoter: M/s Experion
Developers Pvt.Ltd.
Name of the Project: Residential Floor Project
– “Zephyr at the Westerlies” Sector-108, Gurugram. (Seven Plots of 210 Sq.Mt. –
each plot stilt+4 floors i.e. 28 floors)
This project comprises of builder’s floor (stilt+4)
on seven floors of 200 sq.mt. each i.e. total 28 floors of builder’s floor. These
seven plots are part of 100.48 acres plotted colony where part completion of
46.257 acres vide Memo No. LC-2755 Vol-II-PA(SN)-2017/18284, dated 31st
July 2017 and part completion of 44.178
acres vide Memo No. LC-2755 Vol-II-PA(SN)-2017/10093, dated 22nd
March, 2018 were issued by Director Town & Country Planning. As far as
builder’s floor registration is concerned the authority decided to grant
registration certificate subject to submission of details of payment plan as
same has not been mentioned in the allotment letter. During online hearing the
authorized representative brought to the notice of the Authority that their
license has been renewed and copy shall be submitted immediately. The time
period for completion of the registered part of the project shall not exceed
the time granted in the renewal of the license. This case is not covered where
3rd party rights have been created on the plot but the promoter
himself is constructing the builder’s floors.
The Authority hereby take cognizance of the
fact that part completion certificates have been issued after publication of
the Haryana Real Estate (Regulation and Development) Rules, 2017. The
promoter’s attention is invited to section 2(1)(o)(ii) where that part of any
project for which part completion/completion, occupation certificate or part
thereof has been granted on or before publication of these rules i.e. 28th
July, 2017 are exempted from the definition of ongoing project, accordingly the
project comes within the definition of ongoing project and needs to be
registered. Furthermore, section 3(2)(b) provides that no registration of real
estate project shall be required where promoter has received completion
certificate for a real estate project prior to commencement of this Act.
Although, rules cannot supersede specific provision of the Act but keeping in
view the definition of ongoing project given in rule 2(o) also the project
needs to be registered. The concerned planning assistant to issue notice to the
promoter.
Sd/-
Dr.
K.K.Khandelwal
Chairman
Sd/-
Samir
Kumar
Member
Sd/-
S.C.
Kush
Member. |
OBJECTION |
View Order |
08-Jun-2020 |
During the online hearing held on 08.06.2020, the
promoter informed about the license renewal application submitted by them in
DTCP office. The promoter is also directed to submit DPI details of total 100
acres. He is also asked to submit compliance of deficiency conveyed to them.
After examining the same, the matter will be taken
up on 22.06.2020. |
ADJOURNMENT |
View Order |
23-Mar-2020 |
Next date of hearing on 08.06.2020 |
ADJOURNMENT |
--- |
03-Feb-2020 |
Next date on 24.03.2020 |
OBJECTION |
View Order |
20-Jan-2020 |
Next date of hearing on 03.02.2020 |
EXAMINATION BY AUTHORITY |
View Order |