HRERA GurugramTemp Project Id : RERA-GRG-PROJ-483-2019
Submission Date : 19-12-2019 10:50:01 AM
Applicant Type : Company
Project Type: NEW




EXPERION DEVELOPERS PVT LTD
F-9, FIRST FLOOR, MANISH PLAZA 1, PLOT NO. 7, MLU SECTOR 10,DWARKA
01244422630
9560454296 (Number Shared by Promoter in Public)
suneet.puri@experion.net.in
http://www.experion.co
XXXX138L
U70109DL2006FTC151343
 
 


 
 


 
 


 
 


 
 


 
 


 
 







ZEPHYR AT THE WESTERLIES
SECTOR 108, GURUGRAM
KADIPUR ST
GURUGRAM
01246281630
9818559575 (Number Shared by Promoter in Public)
suneet.puri@experion.net.in
VAIBHAV KUMAR SHIVHARE
1246281630
9818559575 (Number Shared by Promoter in Public)
vaibhav.shivhare@experion.net.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1176113-12-2019102564AXIS BANKHRERA Gurugram







0.3633 (Acre)
2.64
2.62
100.48125 (Acre)
Lisence No 57 of 2013
Yes







1620.56 Lakhs
214.63 Lakhs
1250 Lakhs
0 Lakhs
155.93 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 1470.42
3CONSTRUCTION OF ROADS 0
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
Total1470.42




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSG.M.D.A.No
WATER SUPPLYG.M.D.A.Yes
ELECTRICITYD.H.B.V.N.Yes
SEWAGE DISPOSALH.S.V.P.Yes
STORM WATER DRAINAGEH.S.V.P.Yes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS0SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM0SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE0SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM0SUBMITTED TO TOWN & COUNTRY PLANNING
5SEWAGE TREATMENT & GARBAGE DISPOSAL0SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING0SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING0SUBMITTED TO TOWN & COUNTRY PLANNING
8PLAYGROUNDS AND PARKS0SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


28-11-2019 (date)
28-11-2019 (date)
01-08-2020
01-08-2024
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 1470.42 7
Total7


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings420.5641
Apartment/Shops/Other Buildings429.2441
Apartment/Shops/Other Buildings2134.40205





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments362.06
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments24.0806.0816.08
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments132.0828.0888.08126.08
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments148.08138.08146.08182.08
Shops0000
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments10.0996.0878.0920.09
Shops0000
Plots0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments06.096.090
Shops0000
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter (2025)
Apr-JuneJuly-SepOct-DecJan-Mar












Yes
No
AXIS BANK LTD. SECTOR-40, GURUGRAM, HARYANA-122003
920020014929565
UTIB0003102
000
3102
1.Vaibhav Kumar Shivhare (Sr. VP)-1668-C Block,Palam Vihar,Gurugram-122017, 2.Atul Banshal (CFO)- Phase-2,Tower-E The Vilas,12th Floor, DLF Phase-2,Gurgaon,Haryana-122001, 3. Suneet Puri (VP)- B1-151,Regency Park 1,DLF Phase-IV,Gurugram,Haryana-122009, 4. B.K.Malagi(COO)-611-B,Central Park-2,Sohna Road, Opp. Raheja Mall, Sector-48,Gurgaon,Haryana-122001, 5. Sanjeev Ranganath Joshi (Sr.VP)- C-401,Dew Drops Apartment,Netaji Subhash Marg, Near Subhash Chowk, Sector-47,South City-II,Gurgaon,Haryana-12208
Attached











Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
No
Statutory Approvals Statutory Approvals StatusDate
I. BUILDING PLANALREADY BEEN OBTAINED16-12-2019








Yes


Yes









WINDCHANTS,SECTOR 112,GURUGRAM
94821.88
563
0
258
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
10020810020889709
Cost of the apartments10943210943298934
Cost of the infrastructure000
Others costs000


65050 Lakhs
2940 Lakhs
0 Lakhs
0 Lakhs
Yes
31-08-2019
31-08-2020




EXPERION CAPITAL,GOMTI NAGAR,LUCKNOW
17069.98
193
0
166
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
16505165052170
Cost of the apartments19787197875452
Cost of the infrastructure000
Others costs000


3878 Lakhs
14794 Lakhs
0 Lakhs
0 Lakhs
Yes
30-04-2023
30-04-2023










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIEDTILES, LAMINATED WOODEN FLOOR, CERAMIC TILE, KOTA STONE .
2WALL FINISHING DETAILSCEMENT / GYPSUM PLASTER WITH OBD. CERAMIC TILE.
3KITCHEN DETAILS CERAMIC TILES IN DADO 2’-0 HIGH , OBD PAINT.
4BATHROOM FITTINGSCP AND SANITARY FIXTURES.
5WOOD WORK ETCNIL.
6DOORS AND WINDOS FRAMESEXTERNALDOORFRAMES-ALUMINIUM/ UPVC INTERNAL DOOR FRAMES- HARD WOOD FRAME.
7GLASS WORKONLY IN EXTERNAL WINDOWS/ DOOR CUM WINDOWS.
8ELECTRIC FITTINGSMODULAR SWITCH AND SOCKETS.
9CONDUCTING AND WIRING DETAILSPVC CONDUIT. WITH COPPER FLEXIBLE WIRE
10CUPBOARD DETAILSNIL
11WATER STORAGEPVC TANK
12LIFT DETAILSSINGLE LIFT .
13EXTERNAL GLAZINGSALUMINIUM/ UPVC WITH GLASS.
13.1WINDOWS/GLAZINGSALUMINIUM/ UPVC WITH GLASS.
14DOORSVENEERED FLUS DOOR OR PREFABRICATED COMPOSITE DOOR.
14.1MAIN DOORSVENEERED FLUS DOOR OR PREFABRICATED COMPOSITE DOOR.
14.2INTERNAL DOORSPAINTED FLUSH DOOR OR PAINTED MOULDED DOOROR PREFABRICATED COMPOSITE DOOR.
15AIR CONDITIONINGONLY ELECTRICAL PROVISION.
16ELECTRICAL FITTINGSMODULAR SWITCH AND SOCKETS.
17CNG PIPE LINENIL
18PROVISION OF WIFI AND BROADBAND FACILITYNIL
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERIOR GRADE PAINT.
20INTERNAL FINISHINGOBD PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSOBD PAINT.
1 . 3 CEILINGOBD PAINT.
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOOR.
2 . 2 WALLSOBD PAINT.
2 . 3 CEILINGOBD PAINT.
2 . 4 MODULAR WARDROBESNIL
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILES
3 . 2 WALLSCERAMIC TILES
3 . 3 CEILINGOBD PAINT.
3 . 4 COUNTERSGRANITE OR MARBLE COUNTERS.
3 . 5 SANITARY WARE/CP FITTINGSSANITARY WARE/ CP FITTINGS
3 . 6 FITTING/FIXTURESWC , WASHBASIN, SHOWER .
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOOR.
4 . 2 WALLSOBD PAINT.
4 . 3 CEILINGOBD PAINT.
4 . 4 WARDROBESNIL
5 . TOILET
5 . 1 FLOORCERAMIC TILES
5 . 2 WALLSCERAMIC TILES
5 . 3 CEILINGOBD PAINT.
5 . 4 COUNTERSGRANITE OR MARBLE COUNTERS.
5 . 5 SANITARY WARE/CP FITTINGSSANITARY WARE/ CP FITTINGS
5 . 6 FIXTURESWC , WASHBASIN, SHOWER .
6 . KITCHEN
6 . 1 FLOORCERAMIC TILE
6 . 2 WALLSOBD PAINT AND 2 ‘-0 DADO ABOVE COUNTER IN CERAMIC TILE.
6 . 3 CEILINGOBD PAINT.
6 . 4 COUNTERSGRANITE OR MARBLE COUNTERS.
6 . 5 FIXTURESSS SINGLE BOWL SINK WITH DRAINBOARD, SINK MIXTURE.
6 . 6 KITCHEN APPLIANCESNIL
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILE
7 . 2 WALLS & CEILINGOBD PAINT.
7 . 3 TOILETCERAMIC TILE
7 . 4 BALCONYCERAMIC TILE, RAILING.
8 . SIT-OUTS
8 . 1 FLOORNIL
8 . 2 WALLS & CEILINGNIL
8 . 3 RAILINGSNIL
8 . 4 FIXTURESNIL












Sr. No.Document DescriptionDate of Document UploadView Document
1 APPROVAL. D2-25 06-07-2020 ------
2 C6,7-D2-25 ELEVATIONS & SECTIONS 06-07-2020 ------
3 APPROVAL. D2-26 06-07-2020 ------
4 C4,5-D2-19 FLOOR PLANS 06-07-2020 ------
5 PLT APPROVAL OF FOREST NOC RECEIVED FROM DC (1) 06-07-2020 ------
6 BRIII D2-22 06-07-2020 ------
7 NOC W.R.T NON APPLICABILITY OF ARAVALI REVD FROM DC GURGAON_SEC-108 PLT 06-07-2020 ------
8 APPROVAL. D2-20 06-07-2020 ------
9 C4,5-D2-23 FLOOR PLANS 06-07-2020 ------
10 BOARD RESOLUTION 06-07-2020 ------
11 ELECTRICAL LOAD AVAILABILITY 06-07-2020 ------
12 BRIII D2-20 06-07-2020 ------
13 BRIII D2-26 06-07-2020 ------
14 APPROVAL. D2-24 06-07-2020 ------
15 C4,5-D2-20 FLOOR PLANS 06-07-2020 ------
16 C4,5-D2-22 FLOOR PLANS 06-07-2020 ------
17 C4,5-D2-25 FLOOR PLANS 06-07-2020 ------
18 WESTERLIES APPROVAL FROM FOREST 06-07-2020 ------
19 C20-SUPER IMPOSE ON DEMARCATION PLAN 06-07-2020 ------
20 SERVICE ESTIMATES 06-07-2020 ------
21 DEMARCATION PLAN 06-07-2020 View Document
22 ZONING PLAN 06-07-2020 View Document
23 ELECTRICAL LOAD AVAILABILITY 06-07-2020 ------
24 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 06-07-2020 View Document
25 JAMABANDI 06-07-2020 ------
26 CERTIFICATE OF LAND OWNESRSHIP REVD FROM DISTRICT REVENUE OFFICER 06-07-2020 ------
27 GPA - SAS (1) 06-07-2020 ------
28 BOARD RESOLUTION FOR AUTHORIZED SIGNATORY 06-07-2020 ------
29 C6,7-D2-19 ELEVATIONS & SECTIONS 06-07-2020 ------
30 C6,7-D2-24 ELEVATIONS & SECTIONS 06-07-2020 ------
31 C8-251 SQYD IF FLOOR (17.12.2019) D2-20,22,24,26 06-07-2020 ------
32 APPROVAL LETTER FOR SERVICE ESTIMATE 06-07-2020 ------
33 BRIII D2-23 06-07-2020 ------
34 BRIII D2-24 06-07-2020 ------
35 MUTATION 06-07-2020 ------
36 TSR-1 06-07-2020 ------
37 TSR-2 06-07-2020 ------
38 SEC-108 PLOTTED DRO CERTIFICATE 06-07-2020 ------
39 FIRE APPROVAL 06-07-2020 ------
40 APPROVAL. D2-19 06-07-2020 ------
41 APPROVED SPE_LIC 13 NO 57 OF 2013_DTCP_30 09 2015_WESTERLIES 06-07-2020 ------
42 C4,5-D2-24 FLOOR PLANS 06-07-2020 ------
43 C8-251 SQYD IF FLOOR (17.12.2019) D2-19 06-07-2020 ------
44 C14-APPROVED SPE (SEWERAGE SCHEME)_LIC NO 57 OF 2013_DTCP_30.09.15_WESTERLIES 06-07-2020 ------
45 PLT APPROVAL OF FOREST NOC RECEIVED FROM DC 06-07-2020 ------
46 APPROVED SPE (ROAD LAYOUT)_WESTERLIES.PDF 06-07-2020 ------
47 C15,16-APPROVED SPE (STORM WATER DRAINAGE SCHEME)_LIC NO 57 OF 2013_DTCP_30.09.15_WESTERLIES 06-07-2020 ------
48 APPROVAL OF STORM WATER CONNECTION_WESTERLIES_04.02.2019 06-07-2020 ------
49 APPROVAL FOR WATER CONNECTION_WESTERLIES_10.12.2018 06-07-2020 ------
50 BRIII D2-25 06-07-2020 ------
51 C4,5-D2-26 FLOOR PLANS 06-07-2020 ------
52 C6,7-D2-20 ELEVATIONS & SECTIONS 06-07-2020 ------
53 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 06-07-2020 View Document
54 AKS SARJA 06-07-2020 ------
55 MINISTRY OF CORPORATE AFFAIRS - MCA SERVICES 06-07-2020 ------
56 ANNEXURE J-4- APPROVAL FOR WATER CONNECTION_WESTERLIES_10.12.2018 06-07-2020 ------
57 C6,7-D2-26 ELEVATIONS & SECTIONS 06-07-2020 ------
58 APPROVAL OF SEWER CONNECTION_WESTERLIES_04.02.2019 06-07-2020 ------
59 BRIIID2-19 06-07-2020 ------
60 APPROVAL. D2-22 06-07-2020 ------
61 C12-ELECTRICITY SUPPLY PLAN 06-07-2020 ------
62 APPROVAL. D2-23 06-07-2020 ------
63 C6,7-D2-22 ELEVATIONS & SECTIONS 06-07-2020 ------
64 C6,7-D2-23 LEVATIONS & SECTIONS 06-07-2020 ------
65 C8-251 SQYD IF FLOOR (17.12.2019) D2-23 06-07-2020 ------
66 C8-251 SQYD IF FLOOR (17122019)D2-25 06-07-2020 ------
67 C13-WATER SUPPLY PLAN_LIC NO 57 OF 2013_DTCP_30.09.15_WESTERLIES 06-07-2020 ------
68 C17-APPROVED SPE (STREET LIGHTINNG PLAN)_LIC NO 57 OF 2013_DTCP_30.09.15_WESTERLIES - 06-07-2020 ------
69 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 17-12-2019 View Document
70 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 17-12-2019 View Document
71 AUDITED REPORT 2016 17-12-2019 ------
72 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 19-12-2019 View Document
73 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 17-12-2019 View Document
74 BALANCE SHEETS 17-12-2019 ------
75 ANNUAL REPORT 2017 17-12-2019 ------
76 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 17-12-2019 View Document
77 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 17-12-2019 View Document
78 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 16-12-2019 View Document
79 ANNUAL REPORT 2018 17-12-2019 ------
80 GIST OF AGGREMENT 17-12-2019 ------
81 CONVAYANCE DEED 17-12-2019 ------
82 APPLICATION FORM 17-12-2019 ------
83 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 17-12-2019 View Document