Comprehensive Complaint Details
Complaint Detail:RERA-GRG-5178-2023
Party Dtls Self / Adv Name District Current Status Next Date of Hearing Complaint Dispatched Complaint Dispatched On Dispatched Tracking Id Complaint Dispatched Remarks First-Hearing/Scrutinized Remarks View Notice
AMITA GUHA AND ARJUN GUHA V/S
NEW LOOK BUILDERS AND DEVELOPERS PRIVATE LIMITED PREVIOUSLY KNOWN AS ANSAL PHALAK INFRASTRUCTURE PRIVATE LIMITED API
ANSHUMAN ASHOK AND MUKUL KUMAR SANWARIYA OUTSIDE HARYANA PENDING 25-Aug-2025 Not Yet FIRST HEARING --
Complaint Listing Details
Date of Hearing Status Proceedings of the day Bench Order Order Uploaded On
14-Apr-2025 PENDING Matter is adjourned to 25.08.2025. RAJINDER KUMAR View Order 21-Apr-2025
12-Nov-2024 PENDING Recovery certificate was issued to the Collector, in this matter Gurugram on 22.02.2024 to recover decretal amount as arrears of land revenue. In view of order/circular issued by Chief Secretary Government of Haryana, No. 50/15/2024-5S (1) dated 11th May 2024, powers of Collector have been conferred upon the Adjudicating Officer and all the recovery certificates have been received back.                         As per learned counsel for DH, no amount has been recovered through Collector, Gurugram till now. He requests to resume execution proceedings.                          In view of the facts as mentioned above, request is allowed and the execution proceedings are resumed.                          Learned counsel for DH further requests for direction to JD to disclose its assets/properties including bank account and unsold inventories which can be attached to realize the decretal amount. Request is allowed. JD is directed to disclose its assets/properties including bank account and unsold inventories which can be attached to realize the decretal amount. Information be given in the form of affidavit to be sworn by anyone from directors of JD, preferably by Managing Director. At the same time, Tehsildar (Recovery Cell) of Authority be asked to enquire about the properties of JD and to file his report till next date.                                                To come on 14.04.2025 for further proceedings. RAJINDER KUMAR View Order 20-Nov-2024
23-Feb-2024 RE-OPEN/PENDING RE-OPENED RAJINDER KUMAR View Order 19-Mar-2024
19-Dec-2023 FIRST HEARING                            No objections are filed on behalf of JD, despite service of notice which is shown to have been served upon JD on 18.11.2023. Same had enough time to file objections, if any.                            This is matter for refund/recovery.  Learned counsel for DH requests to issue recovery certificate as per calculation done by DH. In view of order passed by the Hon’ble High Court of Punjab & Haryana, Chandigarh, in case tilted as M/s International Land Developers Pvt. Ltd. Vs. Aditi Chauhan and others CWP No. 7738 of 2022, and M/s International Land Developers Pvt. Ltd. Vs. Nitin Mathur and others CWP 7750 of 2022, recovery certificate is required to be issued.  Let recovery certificate be issued to the Collector, Gurugram to recover decretal amount as arrears of land revenue.                          File be sent to Accounts Officer immediately to prepare recovery certificate. Same be got signed from the undersigned.                           Compliance report from Accounts Officer be called for 23.02.2024. RAJINDER KUMAR View Order 04-Jan-2024
Complaint Final Judgement Details
Date of Judgement Party Details Judgement Uploading Date View Judgement
23-Feb-2024 AMITA GUHA AND ARJUN GUHA V/S
NEW LOOK BUILDERS AND DEVELOPERS PRIVATE LIMITED PREVIOUSLY KNOWN AS ANSAL PHALAK INFRASTRUCTURE PRIVATE LIMITED API
--- ---