14-Apr-2025 |
PENDING |
Matter is adjourned to 25.08.2025. |
RAJINDER KUMAR |
View Order |
21-Apr-2025 |
12-Nov-2024 |
PENDING |
Recovery
certificate was issued to the Collector, in this matter Gurugram on 22.02.2024
to recover decretal amount as arrears of land revenue. In view of
order/circular issued by Chief Secretary Government of Haryana, No.
50/15/2024-5S (1) dated 11th May 2024, powers of Collector have been
conferred upon the Adjudicating Officer and all the recovery certificates have
been received back.
As per learned counsel for DH, no amount has
been recovered through Collector, Gurugram till now. He requests to resume
execution proceedings.
In view of the facts as mentioned above,
request is allowed and the execution proceedings are resumed.
Learned counsel for DH further requests for
direction to JD to disclose its assets/properties including bank account and
unsold inventories which can be attached to realize the decretal amount.
Request is allowed. JD is directed to disclose its assets/properties including
bank account and unsold inventories which can be attached to realize the
decretal amount. Information be given in the form of affidavit to be sworn by
anyone from directors of JD, preferably by Managing Director. At the same time,
Tehsildar (Recovery Cell) of Authority be asked to enquire about the properties
of JD and to file his report till next date.
To come on 14.04.2025
for further proceedings. |
RAJINDER KUMAR |
View Order |
20-Nov-2024 |
23-Feb-2024 |
RE-OPEN/PENDING |
RE-OPENED |
RAJINDER KUMAR |
View Order |
19-Mar-2024 |
19-Dec-2023 |
FIRST HEARING |
No objections are
filed on behalf of JD, despite service of notice which is shown to have been
served upon JD on 18.11.2023. Same had enough time to file objections, if
any.
This is matter for refund/recovery. Learned counsel for DH requests to issue
recovery certificate as per calculation done by DH. In view of order passed by
the Hon’ble High Court of Punjab & Haryana, Chandigarh, in
case tilted as M/s International Land Developers Pvt. Ltd. Vs. Aditi Chauhan
and others CWP No. 7738 of 2022, and M/s International Land Developers Pvt.
Ltd. Vs. Nitin Mathur and others CWP 7750 of 2022, recovery
certificate is required to be issued.
Let recovery certificate be issued to the Collector, Gurugram to recover
decretal amount as arrears of land revenue.
File be sent to
Accounts Officer immediately to prepare recovery certificate. Same be got
signed from the undersigned.
Compliance report from
Accounts Officer be called for 23.02.2024. |
RAJINDER KUMAR |
View Order |
04-Jan-2024 |