| 27-Jan-2023 |
PENDING |
|
|
--- |
--- |
| 06-Jan-2023 |
PENDING |
Proceedings dated:
06-01-2023
No one appeared on
behalf of the promoter.
One final
opportunity is given to the promoter to submit the approval of service plan
and estimates before next date of hearing. Matter to come up on 27-01-2023.
|
K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
--- |
--- |
| 09-Dec-2022 |
PENDING |
Proceedings dated: 09-12-2022
No one has appeared on
behalf of the promoter.
The matter to come up on 06-01-2023. |
K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
02-Jan-2023 |
| 25-Nov-2022 |
PENDING |
Proceedings
dated: 25-11-2022
None is present on behalf
of the promoter.
Last opportunity given to the promoter. Matter
to come up on 09-12-2022. |
K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
--- |
--- |
| 18-Nov-2022 |
PENDING |
Proceedings dated:
18-11-2022
Ms. Jyoti Yadav, Planning
Executive briefed about the facts of the project.
Ms. Himani Sharma (CS-AR) is present on behalf
of the promoter. The AR of the promoter states that environment clearance has
been obtained on 30.08.2019. A copy of the same shall be submitted in the
office on 21.11.2022. Regarding service estimates and plans, a letter No.
EIC/SE(HQ)/SDE(W)/2020/173834, dated 30.10.2020 has been forwarded from CE HSVP
to DTCP Haryana. Regarding fire scheme approval. An application has been made
on 15.10.2022 to the fire department. Since the AR of the promoter has not
complete information about the pending approvals therefore, the matter is
adjourned for further proceeding on 25-11-2022. |
K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
View Order |
29-Nov-2022 |
| 01-Jul-2022 |
FIRST HEARING |
The promoter is directed to submit the deficit documents to comply with the conditions of registration certificate. Matter to come up on 18-11-2022. |
K K KHANDELWAL VIJAY KUMAR GOYAL ASHOK SANGWAN SANJEEV KUMAR ARORA |
--- |
--- |