Quarterly Schedules

HRERA Panchkula
Project Registration Number : HRERA-PKL-RWR- 14-2018 DATED 07.06.208
Project Name : AFFORDABLE RESIDENTIAL PLOTTED COLONY UNDER DDJAY ON 5.712 ACRES
Project Number : RERA-PKL-507-2019
Project Type : NEW
S.No.ParticularsAmount
(In Lakhs)
1Cost of the land (if included in the estimated cost)691
2Estimated cost of construction of apartments0
3Estimated cost of infrastructure & other structure462.66
4Other cost including EDC taxes, levies, etc996.34
Total2150



Name of the approvalStatusDate
Layout PlanObtained Approval on12-05-2017
Demarcation PlanObtained Approval on29-12-2017
Zoning PlanObtained Approval on05-02-2018
Service PlansObtained Approval on08-04-2019
Electricity PlansHave not applied till dateN/A
Total Expenditure on the project6120
Expenditure made upto the date of Registration0.35



EDC due as on the date of Registration0

;
S.No.Cash InflowAmount
(In Lakhs)
1Opening Balance2.07
2Amount collected from allottees against booked plots and/or apartments18.28
3Amount availed from the bank/financial institutions0
4Amount contributed by the promoters/his associates69.60
5Any other receipt71.92
Total166.87



S.No.Cash OutflowAmount
(In Lakhs)
1Expenditure on construction of apartments0
2Expenditure on infrastructure & other structure15.25
3Other costs including EDC, taxes, etc148.60
Total163.85
Balance2.58



S.No.Information relating to Escrow AccountAmount
(In Lakhs)
1Opening balance at the beginning of the quarter2.07
2Amount deposited in Escrow Account142.55
3Amount withdrawn during the quarter165.32
4Balance at the end of the quarter2.58
Total Plots in the colony109
Plots sold upto the date of Registration0



S.No.Type/SizePlots Sold in the Quarter
1A0
2A 10
3A20
4B9
5B12
6C0



S.No.Expenditure on Infrastructure made in the QuarterAmount
(In Lakhs)
1Infrastructure6120
2Apartments0
3EDC, IDC, etc996.34
4Others Expenditure14.39



S.No.Expenditure on Taxes,Levies,EDC etc in the QuarterAmount
(In Lakhs)
1Actual paid as on date0
2EDC due as on date0
Sr. No.Document DescriptionDate of Upload Document View
1 SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. 02-12-2019  View 
2 A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. 02-12-2019  View 
3 CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. 02-12-2019  View 
4 CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT 02-12-2019  View 
5 A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. 02-12-2019  View