| 02-Nov-2026 |
Sh. Sumeet, Engineering Officer and Sh. Ashish
Dubey, Chartered Accountant briefed about the facts of the case.
Sh. Saurabh Chattergee, Sh.
Ajay Kumar and Sh. Priyank Mehta (AR) are present on behalf of the promoter.
The Authorized Representative of the promoter
states that they have obtained license no. 135 of 2024 dated 04.11.2024 for
setting up a Mix Land Use under TOD Policy project over an area measuring 7.095715
acres in Sector- 88A, Gurugram. Further submits that as on date the project
site is connected to Dwarka Expressway through 6 mt wide road part of licensed
land and the promoter has applied for road access permission. The Airport
Height Clearance for all khasra numbers of the project has been applied with
competent Authority. Further the promoter states that building plans for the
project were initially approved on 06.03.2026 and then revised on 30.09.2026.
The approved building plans have been revised and the revised BR-III dated
30.09.2026 is applicable for Phase 1 & No phase as the revised site plan is
issued for both Phase 1 & No phase. No separate BR-III is granted by DTCP for
no phase and affidavit to this effect shall be filed in the Authority.
The AR of the promoter states that they will
revise the completion date of the project from 30.09.2035 to 30.09.2034 and
will submit the revised REP-II along with other related documents and remaining
documents in the Authority within 2 days.
Further states that the Environmental clearance, fire scheme approval,
service plan and estimates approval, updated airport height clearance, road access
permission and
mining permission are under process, and the said approvals have not yet been
obtained as on date. Further, the Authorized Representative of the promoter
undertakes to obtain and submit:
i.
Environmental clearance, Fire scheme approval, service plan
and estimates approval within 6 months from the date of grant of registration;
ii.
Updated airport height clearance and road access permission within 3 months from the
date of grant of registration; and
iii. Mining permission before
start of construction of project.
Further, he undertakes to
submit three separate BG/DD amounting to Rs. 25 lakhs each, as a security
deposit for timely compliance with the above requirements at point (i). It is
also expressly undertaken that in the event of failure to obtain and submit the
aforesaid approval within the stipulated time frame, the said security amount
shall be liable to be forfeited by the Authority.
The Authority has taken
note of the submissions made by the AR of the promoter regarding the
non-availability of the aforesaid statutory approvals as on date. In view of
the submission made by the AR of the Promoter and in the interest of regulatory
compliance, the Authority hereby directs that the promoter shall submit three
separate BG/DD amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only)
each, in favour of the Authority as security amount for timely submission of environment
clearance, fire scheme approval, service plan and estimates approval within 6
months from the date of grant of registration.
Needless to say that in
the event of non-submission of the above approvals within the stipulated time
frames as requested by the Promoter during the course of hearing, the said
security amount shall stand forfeited by the Authority, and such failure may
also attract additional regulatory action as permissible under the Act of 2016,
rules and regulations made thereunder. Further, the promoter shall submit the
updated airport
height clearance and road access permission within 3 months from the date of
grant of registration and mining permission before the start of construction of
project. The conditions to the above effect be incorporated in the registration
certificate.
Approved as proposed
subject to rectification of deficiencies mentioned above.
The Registration Certificate shall be
issued after submission of correction in Form A–H, correction in online DPI,
revised REP-II with related documents and submission of three BG/DD of Rs.
25,00,000/- (Rupees Twenty-Five Lakhs only) each for submission of environment
clearance, fire scheme approval, service plan and estimates within the time
frame mentioned above, along with the other remaining deficiencies mentioned at
S. No. 36. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |