| 05-Nov-2026 |
Ms. Deepika, Planning Executive and Ms. Asha,
Chartered Accountant briefed about the facts of the case.
Sh. Purushottam Grover,
Sh. Venkat Rao, Sh. Anitesh Singh and Ms. Prabhleen Singh Sagu (AR’s) are
present on behalf of the promoter.
The Authorized
Representative of the promoter states that a reply dated 05.11.2026 has been
submitted to the Authority regarding the pending documents. Further, the
promoter submits that a part of the area of Phase 4 was already registered with
the Authority vide Registration Certificate No. 08 of 2021 dated 01.03.2021, as
Phase 2, which has subsequently been amended vide order dated 09.10.2026. The
office is directed to examine the reply dated 05.11.2026.
The AR of the promoter
states that the project is accessible from 12-meter-wide service road along the
sector dividing road of sector 65 & 66, which is constructed and
operational. Further, the AR of the promoter states that revised layout plan
dated 23.04.2026 as well as site plan of commercial colony dated 21.10.2026
have been approved by DTCP Haryana and in view of the same, the promoter has applied
for registration of Phase 4 on 16.10.2026 wherein no third-party rights have
been created till date. In this regard, an affidavit of CEO of the promoter
company has been submitted regarding no sale, marketing of project area under
Phase 4.
Further, as per clause
4.1.1 of phasing policy dated 24.04.2023, obtaining of consents shall be
limited to the phase in which revision proposed. Since no third-party rights
created in land area under Phase 4, hence requirement of consents is not
applicable for revision of layout plan/ site plan of Phase 4. Clause 4.1.1 of
phasing policy dated 24.04.2023 is reproduced as under:
In cases where colony is proposed to
be developed in phases, obtaining two third consents, for revision of layout/
building plan shall be limited to the phase in which such revision is proposed.
In view of the above
submissions made by the promoter, the Authority is of the view that the
requirement of obtaining consent of two-third allottees does not arise in the
present application for registration of Phase-4 area, keeping in view the
clause 4.1.1 of the Phasing Policy dated 24.04.2023, as reproduced above, and
also considering the submission of the promoter that no third-party rights have
been created in the area falling under Phase-4 applied for registration of the
project.
The AR of the promoter
further submits that, as on date, the Environmental Clearance, approval of
revised service plans and estimates, Fire Scheme Approval, and Tree Cutting
Permission are yet to be obtained. With regard to the Environmental Clearance,
the promoter submits that the project has been recommended for grant of EC by
SEIAA in its meeting held on 30.09.2026.
Further,
the AR of the promoter undertakes to obtain and submit the following approvals:
i.
Environmental Clearance within 4
months from the date of grant of registration;
ii.
Revised Service Plans and Estimates
approval within 6 months from the date of grant of registration;
iii.
Fire scheme approval within 6
months from the date of grant of registration; and
iv.
Tree cutting permission prior to
cutting of any tree.
Further, he undertakes to
submit one Demand Drafts / Bank Guarantees amounting to Rs. 25 lakhs, as a
security deposit for timely compliance with the above requirements at point (i).
Further, the AR of the promoter submits that DDs amounting to Rs. 25 lakhs each
towards the revised service plans and estimates and Fire Scheme Approval have
already been deposited. It is also expressly undertaken that in the event of
failure to obtain and submit the aforesaid approvals within the stipulated time
frame, the said security amount(s) shall be liable to be forfeited by the
Authority.
The Authority has taken
note of the submissions made by the AR of the promoter regarding the
non-availability of the aforesaid statutory approvals as on date. In view of
the above, and in the interest of regulatory compliance, the Authority hereby
directs that the promoter shall submit a Demand Drafts / Bank Guarantees,
amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only), in favour of the
Authority, as security amounts for timely submission of the Environmental
Clearance within 4 months from the date
of grant of registration. Further, the promoter has already
deposited the Demand Drafts amounting to Rs. 25,00,000/- (Rupees Twenty-Five
Lakhs only) each, as security for timely submission of the approval of revised
Service Plans and Estimates and Fire Scheme Approval within a period of six
months from the date of grant of registration, respectively.
Needless
to say that in the event of non-submission of the above approvals within the
stipulated time frames as requested by the Promoter during the course of
hearing, the
corresponding security amount shall stand forfeited by the Authority, and such
failure may also attract additional regulatory action as permissible under the
Act of 2016, rules and regulations made thereunder. Further, the promoter shall
submit Tree cutting permission prior to cutting of any tree and mining
permission before the start of construction of project. A condition to this
effect shall also be incorporated in the Registration Certificate.
Approved as proposed
subject to rectification of deficiencies mentioned above at S. No. 34.
The Registration
Certificate shall be issued after submission of corrections in A-H form, Online
DPI, along with the other remaining deficiencies mentioned at S. No. 34 and
submission of one DD/BG of Rs. 25 lakhs for submission of Approved
Environmental Clearance within the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |