| 05-Oct-2026 |
Ms. Deepika, Planning Executive and
Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project.
Sh. Jassa Singh Chawla
(Director) & Animesh Khare (AR) are present on behalf of promoter.
The Director of the company states
that the promoter has applied for registration of the project under Section 4
of the Act, 2016, after obtaining all the necessary approvals from the
concerned departments. Further, the deficit documents have also been submitted.
He further states that the approval
of the service plan and estimates is under process. Moreover, the promoter has
already submitted a Bank Guarantee of Rs. 6,12,13,300/- to the concerned
department, i.e. DTCP, vide BG No. 027GT02262580041 dated 15.09.2026. The said
approval has not yet been obtained as on date. Further, the Director of the
promoter undertakes to obtain and submit the same within three months from the
date of grant of registration.
The Authority has taken note of the
aforesaid submission made by the Director of the Promoter Company. The promoter
shall obtain and submit the requisite approval to the Authority within the stipulated
time frame. In the event of non-submission of the said approval within the stipulated
time frame, the Authority shall be at liberty to take appropriate regulatory
action as permissible under the Act of 2016 and the rules and regulations made
thereunder. Further, a condition to this effect shall also be incorporated in
the Registration Certificate.
Further, as per the site visit conducted
by the concerned officials, it is noticed that the branding/name “OKAS” is
being used at the project site. In this regard, the promoter shall submit a
declaration clarifying and confirming the use of the aforesaid name/branding at
the project site.
Approved as proposed, subject to
rectification of the deficiencies mentioned above.
The Registration
Certificate shall be issued after submission of the corrections in Form A–H,
correction in the online DPI, and declaration regarding the use of the brand
name “OKAS”, along with the other remaining deficiencies mentioned at S. No.
34. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |