Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
EMAAR BUSINESS DISTRICT NEXT 114 VILLAGE BAGHERA, SECTOR 114 GURUGRAM GURUGRAM Badshahpur ST Emaar India Limited
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/1055/787/2026/27 DATED 07.04.2026 RERA-GRG-2173-2026 27-Feb-2026 27-Feb-2026 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 17-Mar-2026 HARERA/GGM/RPIN/2171 DISPATCHED
First Hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/1055/787/2026/27 DATED 07.04.2026 15-Apr-2026 PROJECT RC UPLOADED
Project Listing Details
Date of Hearing Proceedings of the day Status Order
30-Mar-2026 Ms. Neeraj Gautam, Associate Architectural Associate and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Venkat Rao (Advocate), Sh. Purshottam Grover (AR), Ms. Priyanka Miglani and Sh. Anitesh Singh (AR) appeared on behalf of the promoter. The Authorized Representative of the promoter submits that a reply including the pending deficiencies has been submitted in the Authority today. The Authorized Representative of the promoter further states that presently service plans and estimates and electrical load are under process and the said approvals have not yet been obtained as on date. Further, the AR of the promoter undertakes to obtain and submit: i.       Approved Service Plans and Estimates within 4 months from the date of grant of registration; and ii.    Approved Electrification plan within 6 months from the date of grant of registration; and   Further, he undertakes to submit a Demand Draft/Bank Guarantee amounting to Rs. 25 lakhs, as a security deposit for timely compliance with the above requirements at point (i). It is also expressly undertaken that in the event of failure to obtain and submit the aforesaid approvals within the stipulated time frame, the said security amount shall be liable to be forfeited by the Authority. The Authority has taken note of the submissions made by the Authorized Representative of the promoter regarding the non-availability of the aforesaid statutory approvals as on date. In view of the above, and in the interest of regulatory compliance, the Authority hereby directs that the promoter shall submit  a Demand Draft/ Bank Guarantee, amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only), in favour of the Authority, as security amounts for timely submission of Approved Service Plans and Estimates within 4 months from the date of grant of registration. In the event of non-submission of the above approval within the prescribed time frame, the corresponding security amount shall stand forfeited by the Authority, and such failure may also attract additional regulatory action as permissible under the Act of 2016, rules and regulations made thereunder. Further, the promoter shall submit Approved Electrification plan within 6 months from the date of grant of registration. Approved as proposed subject to rectification of deficiencies mentioned above at S. No. 31. The Registration Certificate shall be issued after submission of remaining deficiencies mentioned above including correction in A-H form, Online DPI and submission of a DD/BG of Rs. 25 lakhs for submission of Approved Service Plans and Estimates within the timeframe mentioned above. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
16-Mar-2026 The matter has been adjourned to 30.03.2026. EXAMINATION BY AUTHORITY View Order