| 18-Feb-2026 |
Ms.
Nikita Mittal, Planning Executive and Ms. Asha, Chartered Accountant briefed
about the facts of the project.
Sh.
Sandeep Patwa (Regional head), Ms. Lipika Jain (Architect), Sh. Aman Sharma
(AR) , Sh. Nitin Sharma (AR), and Sh. Vidyashankar are present on behalf of the
promoter.
The
Authorized Representative of the promoter stated that DTCP has granted
license no. 116 of 2011 dated 23.12.2011 for the development of Group Housing
Colony over an area admeasuring 13.275 acres and phasing plan has been approved
vide memo no. ZP-1321/JD(RA)/2024/41292 dated 24.12.2024 consisting of Phase-1,
Phase-2 and EWS Block. Thereafter, the promoter had applied for Phase-1 and EWS
Block admeasuring 11.745 acres which was registered with the Authority in the name of “Birla
Arika” vide RC No. 17 of 2025 dated 20.02.2025.
Now, the promoter has
obtained the revised phasing plan approval vide memo no. ZP-1321
Vol-II/JD(G)/2026/1951 dated 16.01.2026 consisting of Phase-1, Phase-2 and
Phase-III (EWS Block) and applied
for the registration under Section 4 of the Act, 2016 for Phase-2 area admeasuring
1.53 acres which includes Towers 4, 5, 6, Community Building-04, Nursery school
and proportionate EWS units of these towers .The
Authorized Representative of the promoter further submitted that presently, the
revised Environment clearance, revised Fire Scheme Approval and revised approved
service plans and estimates, mining permission are under process and the said approvals have
not yet been obtained as on date. Further, the AR of the promoter undertakes to
obtain and submit:
i.
Approved Environmental Clearance, Fire Scheme
Approval and Approved Service Plans and Estimates within 4 months from the date
of grant of registration; and
ii.
Mining
permission before the start of construction.
Further, to show the bonafide
on its part, he has submitted three Demand Drafts amounting to Rs. 25 lakhs
each vide DD No. 511459 dated 05.02.2026 (Revised approved
Environment Clearance), 511460 dated 05.02.2026 (Fire Scheme
Approval) and 511483 dated 11.02.2026 (Approved Service Plans and
Estimates), as a security deposit for timely compliance with the above requirements
at point (i). It is also
expressly undertaken that in the event of failure to obtain and submit the
aforesaid approvals within the stipulated time frames, the said security
amount(s) shall be liable to be forfeited by the Authority.
The Authority has taken note of the submissions made
by the Authorized Representative of the promoter regarding the non-availability
of the aforesaid statutory approvals as on date. Further, in the event of
non-submission of any of the above approvals within the prescribed time frames,
the corresponding security amount shall stand forfeited by the Authority, and
such failure may also attract additional regulatory action as permissible under
the Act of 2016, rules and regulations made thereunder. Further, the promoter
shall submit mining permission before start of construction at site.
Regarding
the registration of the EWS units with this project, the same cannot be
registered with this current application for registration, as EWS (no phase as
per earlier approved phasing plan) blocks already stand registered with the
Authority vide RC no 17 of 2025 dated 20.02.2025. In view of the above, the
promoter shall apply for amendment of registration certificate 17 of 2025 dated
20.02.2025 to incorporate the proportionate EWS units.
Approved
as proposed subject to rectification of deficiencies mentioned above at S. No.
31.
The
Registration Certificate shall be issued after submission of corrections in A-H
form, Online DPI along with the remaining deficiencies mentioned at S. No. 31.
|
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |