Ms. Nikita Mittal, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
case.
Sh. Ajay Pathania (AR), Sh. Sumit
(Collaborator), Sh. Prabhleen Singh and Sh. Rajendra Singh (CA) are present on
behalf of the promoter.
The promoter stated that 2/3rd
consent of the allottees has been submitted with respect to revision in
building plan which includes addition of three licenses (15 of 2025 dated
29.01.2025, 99 of 2025 dated 13.06.2025 and 100 of 2025 dated 17.06.2025) and
alterations in previous sanctioned plan.
The
Authorized Representative for the promoter submits that presently, the Fire
Scheme Approval is under process and the said approval has not yet been
obtained as on date. Further, the AR of the promoter undertakes to obtain and
submit:
i. The Fire Scheme Approval within 3 months
from the date of grant of registration.
Further,
he undertakes to submit a Demand Draft/Bank Guarantee amounting to Rs. 25
lakhs, as a security deposit for timely compliance with the above requirement.
It is also expressly undertaken that in the event of failure to obtain and
submit the aforesaid approval within the stipulated time frame, the said
security amount shall be liable to be forfeited by the Authority.
The
Authority has taken note of the submissions made by the Authorized
Representative of the promoter regarding the non-availability of the aforesaid
statutory approval as on date. In view of the above, and in the interest of
regulatory compliance, the Authority hereby directs that the promoter shall
submit a Demand Draft / Bank Guarantee, amounting to Rs. 25,00,000/- (Rupees
Twenty-Five Lakhs only), in favor of the Authority, as security amount for
timely submission of the Fire Scheme Approval within 4 months from the date of
grant of registration.
In
the event of non-submission of the above approval within the prescribed time
frame, the corresponding security amount shall stand forfeited by the
Authority, and such failure may also attract additional regulatory action as
permissible under the Act of 2016, rules and regulations made thereunder. Approved as proposed
subject to rectification of deficiencies mentioned above at Sr. No. 31. The
Registration Certificate shall be issued upon submissions of remaining
deficiencies mentioned at Sr. No. 31 including corrections in A-H form, Online
DPI and submission of BG/DD of Rs. 25 lakhs towards submission of Fire Scheme
approval within the timeframe mentioned above, along with DPI
along with the notarized affidavit from the Director of the promoter company
regarding the submission of consents of two third existing allottees submitted
to the Authority. |