| 02-Feb-2026 |
Ar. Neeraj Gautam, Associate Architectural
Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of
the project.
Sh. Tanish Bhutani (AR) and Sh. Mangal Sain
Mittal are present on behalf of the promoter and states that they are in the
process of preparing the demand draft for deposition of deficit fee and will
submit the same in the Authority before the issuance of the registration
certificate along with the other deficit documents. The AR further undertakes
that the approvals of fire scheme, service plans & estimates, electrical
load availability and tree cutting permission will be submitted within a period
of 4 months and mining permission before the commencement of excavation on
site.
Further, he undertakes to submit two
Demand Drafts / Bank Guarantees amounting to Rs. 25 lakhs each, as a security
deposit for timely submission of approved fire scheme and approved service
plans and estimates. It is also expressly undertaken that in the event of
failure to obtain and submit the aforesaid approvals within the stipulated time
frames, the said security amount(s) shall be liable to be forfeited by the
Authority.
The Authority has taken note of the
submissions made by the Authorized Representative of the promoter regarding the
non-availability of the aforesaid statutory approvals as on date.
In view of the aforesaid submission and
undertaking made by the authorized representative of the promoter, the
promoter is directed to submit of following approvals:
a. Fire scheme: within 4
months from the date of grant of registration;
b. Service Plans and
Estimates: within 4 months from the date of grant of registration;
c. Approved electrical load
availability: within 4 months from the date of grant of registration;
d. Tree cutting permission:
within 4 months from the date of grant of registration; and
e. Mining permission: before
commencement of excavation on site
In the event of non-submission of fire
scheme approval and approved service plans & estimates within the
prescribed time frame, the corresponding security amount shall stand forfeited
by the Authority, and the failure to submit any of the above approvals/
permissions within the prescribed timeframe may also attract additional
regulatory action as permissible under the Act of 2016, Rules and Regulations
made thereunder.
Approved as proposed subject to
rectification of deficiencies mentioned above at S. No. 33.
The Registration Certificate shall be
issued after deposition of deficit fees and above BGs/DDs and submission of remaining
deficiencies including the rectification of form REP-I and DPI. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |