| 05-Jan-2026 |
Ar. Neeraj Gautam, Associate Architectural
Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of
the project.
Sh. Ashok Kumar (Partner, AR) is present on
behalf of the promoter.
The AR of the promoter states that the
approvals of environmental clearance, fire scheme and service plans &
estimates are under process and requests 4 months’ time to submit the same in
the Authority. The AR further assures that the mining permission will be
obtained before excavation on the site and a copy of the same will be submitted
in the Authority. The AR requests to grant the registration subject to the
submission of above approvals/ permissions.
Further, he undertakes to submit
three Demand Drafts / Bank Guarantees amounting to Rs. 25 lakhs each, as a
security deposit for timely submission of environmental clearance, approved
fire scheme and approved service plans and estimates. It is also expressly
undertaken that in the event of failure to obtain and submit the aforesaid
approvals within the stipulated time frames, the said security amount(s) shall
be liable to be forfeited by the Authority.
The Authority has taken note of the
submissions made by the Authorized Representative of the promoter regarding the
non-availability of the aforesaid statutory approvals as on date. In view of
the submission of proposal to submit the Demand Draft / Bank Guarantee,
amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only) each in lieu of
timely submission of environmental clearance, fire scheme approval and approved
service plans and estimates, in favour of the Authority, the promoter is
directed to submit of following approvals:
a. Environmental clearance:
within 4 months from the date of grant of registration;
b. Fire scheme: within 4 months
from the date of grant of registration;
c.
Service Plans and Estimates: within 4 months from the date of
grant of registration; and
d. Mining permission: before
commencement of construction;
In the event of non-submission of above
approvals within the prescribed time frame, the corresponding security amount
shall stand forfeited by the Authority, and the failure to submit any of the
above approvals/ permissions within the prescribed timeframe may also attract
additional regulatory action as permissible under the Act of 2016, Rules and
Regulations made thereunder.
Approved as proposed subject to
rectification of deficiencies mentioned above at S. No. 21.
The Registration Certificate shall be
issued after deposition of above BGs/DDs and rectification of other
deficiencies as listed above at S. No. 21. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |