| 08-Dec-2025 |
Ar. Neeraj Gautam, Associate Architectural
Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of
the project.
Sh. Sumit Chaudhary, Chief- Business
Development along with Sh. Ravi Kant Gautam appeared on behalf of the promoter.
Sh. Madhup Johri, Sh. Puneet Kumar Jain and
Sh. Vikas Bajaj, landowners are also present.
The AR of the promoter states that they have
already applied for the approval of environmental clearance, fire scheme and
service plans and estimates in the respective authorities. With respect to the
environmental clearance, it is stated that the promoter had applied for the
approval vide application dated 27.12.2024 and the EAC, MoEF, GoI in its
meeting held from 09.01.2025 to 10.01.2025 recommended for approval of
environmental clearance. The final clearance is still awaited and will be
submitted to the Authority within 3 months. With respect to the approval of
service plans & estimates, it is stated that the Bank Guarantee dated 06.12.2025 of
Rs. 13,400,000/- on account of IDW for approval of service plans and estimates
has already been submitted to the DTCP and the final approval is still awaited.
The application for approval of fire scheme has also been made before the
Municipal Corporation Gurugram vide application dated 07.11.2025. The Promoter
ensures to submit the environmental clearance, approved service plans &
estimates and approved fire scheme within 3 months; mining permission before
commencement of construction and remaining rectified documents/ clarification
before the issuance of the registration certificate. The promoter further
proposes to submit the security amount of Rs. 25 lakhs each on account of
timely submission of environmental clearance and fire scheme approval and for service
plans estimates, the promoter has already submitted a bank guarantee dated
06.12.2025 of Rs. 13.4 crores with DTCP.
The Authority has taken note of the
submissions made by the Authorized Representative of the promoter regarding the
non-availability of the aforesaid statutory approvals as on date. In view of
the above, the promoter is directed to submit two Demand Draft
/ Bank Guarantee, amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only) each
in lieu of timely submission of environmental clearance and approved fire
scheme, respectively, in favour of the Authority. The promoter is directed to
submit of
following approvals:
a. Service Plans and
Estimates: Within 3 months from the date of grant of registration;
b. Fire scheme: Within 3
months from the date of grant of registration;
c. Environmental clearance:
Within 3 months from the date of grant of registration; and
d. Mining permission: Before
commencement of construction
In the event of non-submission of
environmental clearance and approved fire scheme within the prescribed time
frame, the corresponding security amount shall stand forfeited by the
Authority, and the failure to submit any of the above approvals/ permissions
within the prescribed timeframe may also attract additional regulatory action
as permissible under the Act of 2016, Rules and Regulations made thereunder.
The registration of the project is
approved as proposed subject to rectification of deficiencies mentioned above
at S. No. 32.
The Registration Certificate shall be
issued after deposition of above BG/DD and rectification of other deficiencies
as listed above at S. No. 32. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |