| 06-Oct-2025 |
Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the case.
Sh. Manoj Kumar (AR), Sh. Vivek Kr. Singh (AR) and Sh. Ashish Tyagi (AR) are
present on behalf of the promoter.
The Authorized
Representative of the promoter submits that presently, the Environment clearance, Fire Scheme
Approval, Approved service plans and estimates, mining permission and
Electrical load availability are under process and the said approvals have not yet
been obtained as on date. Further, the AR of the promoter undertakes to obtain and submit:
i.
The Approved Environmental Clearance, Fire Scheme
Approval and Approved Service Plans and Estimates within 3 months from the date
of grant of registration.
ii.
Electrical load availability within 2 months from the
date of grant of registration.
iii. Mining permission
before the start of construction.
Further, he
undertakes to submit three Demand Drafts / Bank Guarantees amounting to Rs. 25
lakhs each, as a security deposit for timely compliance with the above
requirements at point (i). It is also expressly undertaken that in the event of
failure to obtain and submit the aforesaid approvals within the stipulated time
frames, the said security amount(s) shall be liable to be forfeited by the
Authority.
The Authority has
taken note of the submissions made by the Authorized Representative of the
promoter regarding the non-availability of the aforesaid statutory approvals as
on date. In view of the above, and in the interest of regulatory compliance,
the Authority hereby directs that the promoter shall submit three separate
Demand Drafts / Bank Guarantees, each amounting to Rs. 25,00,000/- (Rupees
Twenty-Five Lakhs only), in favour of the Authority, as security amounts for
timely submission of the following approvals:
a. Approved Environmental
Clearance: within 3 months from the date of grant of registration;
b. Fire Scheme Approval:
within 3 months from the date of grant of registration; and
c. Approved Service
Plans and Estimates: within 3 months from the date of grant of registration.
In the event of
non-submission of any of the above approvals within the prescribed time frames,
the corresponding security amount shall stand forfeited by the Authority, and
such failure may also attract additional regulatory action as permissible under
the Act of 2016, rules and regulations made thereunder. Further, the promoter
shall submit the Electrical load availability within 2 months from the grant of
registration certificate and Mining permission before start of construction.
Approved as proposed subject to rectification of deficiencies mentioned
above.
The Registration Certificate shall be issued after submission of
remaining deficiencies mentioned above including correction in A-H form, Online
DPI and submission of three BG/DD of Rs. 25 lakhs each for submission of Approved Environment Clearance,
Fire Scheme approval and approved Service plan and Estimates within the
timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |