HRERA GurugramTemp Project Id : RERA-GRG-PROJ-2027-2025
Submission Date : 06-09-2025 04:55:02 PM
Applicant Type : Company
Project Type: NEW




SV INFRA MANAGEMENT SOLUTIONS PVT. LTD. (FORMERLY KNOWN AS SV INFRA MANAGEMENT SOLUTIONS LLP)
PLOT NO.8, SECTOR-44, GURUGRAM - 122002
01244989300
8860640088 (Number Shared by Promoter in Public)
info@satyadevelopers.com
http://www.satyagroups.in
XXXX479K
U39000DL2025PTC447215
 
 


 
 


 
 


 
 


 
 


 
 







LEVANTE RESIDENCES
REVENUE ESTATE OF VILLAGE DHANWAPUR SECTOR 104,GURUGRAM
KADIPUR ST
GURUGRAM
9821685163
9821685163 (Number Shared by Promoter in Public)
amit.parmar@satyadevelopers.com
AMIT PARMAR
9821685163
9821685163 (Number Shared by Promoter in Public)
amit.parmar@satyadevelopers.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
17879806-09-20254386160HDFC BANK LIMITEDHRERA Gurugram
27879906-09-2025906850HDFC BANK LIMITEDHRERA Gurugram







4.65625 (Acre)
4.82
4.82
4.65625 (Acre)
140 of 2024 dated 11.11.2024 Valid up 10.11.2029
Yes







114210.84 Lakhs
19952.13 Lakhs
50108.14 Lakhs
11630.31 Lakhs
32520.26 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 1.930
3CONSTRUCTION OF ROADS 1.047
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 1.34525
6GREEN BELTS 0
7VEHICLE PARKINGS 0.111
8ELECTRICITY SUB-STATION 0.11
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
13RWH 0.113
Total4.65625




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVP / GMDA No
WATER SUPPLYGMDA Yes
ELECTRICITYDHBVNL No
SEWAGE DISPOSALHSVP / GMDA Yes
STORM WATER DRAINAGEGMDA Yes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS611.67AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM425.03AS PER PROJECT REPORT
3STORM WATER DRAINAGE75.22AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM2075.76AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL56.41AS PER PROJECT REPORT
6STREET LIGHTING25.00AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING115.09AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS135.62AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM56.5AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER227.72AS PER PROJECT REPORT
15PARKING7298.46AS PER PROJECT REPORT
16STP100.00AS PER PROJECT REPORT
17UNDERGROUND WATER TANK95.00AS PER PROJECT REPORT
18RAIN WATER HARVESTING30.00AS PER PROJECT REPORT
19ELECTRICAL SUB STATION292.83AS PER PROJECT REPORT
20COST OF CONSTRUCTION OF TWENTY FOUR MTR WIDE ROAD10.0AS PER PROJECT REPORT


27-08-2025 (date)
27-08-2025 (date)
01-12-2025
31-03-2032
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings7718.47683
Apartment/Shops/Other Buildings7198.55683
Apartment/Shops/Other Buildings11207.52843
Apartment/Shops/Other Buildings11207.52843
Apartment/Shops/Other Buildings6504.32383
Apartment/Shops/Other Buildings6504.32383
Apartment/Shops/Other Buildings5608.71423
Apartment/Shops/Other Buildings5608.70423
Apartment/Shops/Other Buildings615.1543
Apartment/Shops/Other Buildings615.1543
Apartment/Shops/Other Buildings1090.3463
Apartment/Shops/Other Buildings1025.1363
Apartment/Shops/Other Buildings354.6123
Apartment/Shops/Other Buildings332.6023
Apartment/Shops/Other Buildings2542.8150





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments177.25
Shops0
Plots0

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments413.581181.651477.061794.52
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2333.912450.224054.34778.3681
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments5393.804877.802823.612430.29
Shops0000
Plots0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2467.062239.971833.971668.87
Shops0000
Plots0000

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1233.751317.471570.731363.30
Shops0000
Plots0000

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments908.13742.22576.310
Shops0000
Plots0000

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other00.500
Boundary Wall11.3922.7734.1645.54
Construction of road0.522.770.50.5

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Boundary Wall40.9929.6022.7720.49
Construction of road0.50.50.50.5
Fire Fighting Services001.882.26

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0002.82
Electricity Supply System0000
Storm Water Drainage0003.76
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Security Fire fighting2.632.633.013.38
Construction of road0.50.50.50.5

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements30.5830.5861.1773.40
Water Supply System42.5097.7685.01106.26
Sewerage treatment & garbage disposal5.648.468.4611.28
Electricity Supply System000622.72
Storm Water Drainage7.5211.2811.2815.04
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Security Fire fighting3.763.383.383.01
Parking729.851021.781167.751459.69
Construction of road0.40.40.40.4
Rain water0009.0

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements110.1079.5273.4061.17
Water Supply System63.7529.7500
Sewerage treatment & garbage disposal14.105.6400
Electricity Supply System830.30622.7200
Storm Water Drainage18.817.5200
Parks and Playgrounds20.3427.1236.6228.48
Clubhouse/community centres0000
Shopping area0000
Other0000
Electric Sub Station146.42146.42
Renewable Energy System016.9522.6016.95
Security Fire fighting2.6325.8732.8724.37
Street Light12.512.5
Underground Water tank9.542.7542.750
Rain water harvesting129
STP104545
Construction of road0.40.40.50.4
Parking1094.761021.78802.83

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements36.7030.5824.470
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds9.496.786.780
Clubhouse/community centres0000
Shopping area0000
Other0000
Construction of road0.30.20.20

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Construction of road0000












Yes
Yes
HDFC BANK, PLOT NO-1, BLOCK A-2, COMMERCIAL COMPLEX, SECTOR-110, NOIDA-201304 UTTAR PRADESH
57500001826474
HDFC0000930
110240127
930
Manish Agarwal-03, Silver Oak Avenue, Westend Greens, Rajokari, New Delhi-110038
Yes











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENCEALREADY BEEN OBTAINED11-11-2024
II. NOC FOR HEIGHT CLEARANCE ALREADY BEEN OBTAINED03-09-2024
III. ZONING PLAN ALREADY BEEN OBTAINED20-06-2025
IV. ARAVALI/NCZ ALREADY BEEN OBTAINED09-10-2024
V. FOREST NOCALREADY BEEN OBTAINED12-09-2024
VI. CONSTRUCTION WATER NOC ALREADY BEEN OBTAINED31-01-2025








Yes


Yes


Attached













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSETILE
2WALL FINISHING DETAILSACRYLIC EMULSION PAINT
3KITCHEN DETAILSTILE FLOORING & GRANITE COUNTER
4BATHROOM FITTINGSWC, WASH BASIN ,TAP AND FIXTURES FITTING(SS FINISH)
5WOOD WORK ETCENGINEERED WOOD
6DOORS AND WINDOS FRAMESALUMINUM
7GLASS WORKHIGH PERFORMANCE GLASS
8ELECTRIC FITTINGSMODULAR SWITCH SOCKETS
9CONDUCTING AND WIRING DETAILSPVC CONDUITS, FRLS WIRE
10CUPBOARD DETAILSN.A.
11WATER STORAGECENTRALIZED
12LIFT DETAILS24 PAX LIFT, 3.0 MPS
13EXTERNAL GLAZINGSALUMINIUM FRAMING WITH HIGH PERFORMANCE GLASS
13.1WINDOWS/GLAZINGSALUMINUM FRAMING WITH HIGH PERFORMANCE GLASS
14DOORSVENEER FINISH SHUTTER
14.1MAIN DOORSVENEER FINISH SHUTTER
14.2INTERNAL DOORSVENEER FINISH SHUTTER
15AIR CONDITIONING"VARIABLE RATE FLOW SYSTEM/ SPLIT UNITS/ OR EQUIVALENT"
16ELECTRICAL FITTINGSISI MARKED OR EQUIVALENT
17CNG PIPE LINEAS PER AVAILABILITY
18PROVISION OF WIFI AND BROADBAND FACILITYPROVISION
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERNAL GRADE PAINT/ OR EQUIVALENT
20INTERNAL FINISHINGEMULSION PAINT OR EQUIVALENT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOOR 800MMX 1600MM VITRIFIED TILE
1 . 2 WALLSACRYLIC EMULSION PAINT
1 . 3 CEILINGACRYLIC EMULSION PAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOOR - AC4 GRADE
2 . 2 WALLSACRYLIC EMULSION PAINT
2 . 3 CEILINGACRYLIC EMULSION PAINT
2 . 4 MODULAR WARDROBESN.A.
3 . MASTER TOILET
3 . 1 FLOOR600MMX 1200MM VITRIFIED TILE
3 . 2 WALLSVITRIFIED TILE UPTO FALSE CEILING 2400MM HIGH
3 . 3 CEILINGMR BOARD FALSE CEILING + ACRYLIC EMULSION PAINT
3 . 4 COUNTERSSTONEX
3 . 5 SANITARY WARE/CP FITTINGSWC, WASH BASIN ,TAP AND FIXTURES FITTING(SS FINISH)
3 . 6 FITTING/FIXTURES KOHLER/EQUIVALENT
4 . BED ROOMS
4 . 1 FLOOR800MMX 1600MM VITRIFIED TILE
4 . 2 WALLSACRYLIC EMULSION PAINT
4 . 3 CEILINGACRYLIC EMULSION PAINT
4 . 4 WARDROBESNOT APPLICABLE
5 . TOILET
5 . 1 FLOOR600MMX 1200MM VITRIFIED TILE
5 . 2 WALLSVITRIFIED TILE UPTO FALSE CEILING 2400MM HIGH
5 . 3 CEILINGMR BOARD FALSE CEILING + ACRYLIC EMULSION PAINT
5 . 4 COUNTERSSTONEX
5 . 5 SANITARY WARE/CP FITTINGSWC, WASH BASIN ,TAP AND FIXTURES FITTING(SS FINISH)
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOOR800MMX 1600MM VITRIFIED TILE
6 . 2 WALLSPREMIUM TILE UP TO 600MM HIGH ABOVE COUNTER
6 . 3 CEILINGACRYLIC EMULSION PAINT
6 . 4 COUNTERSGRANITE STONE
6 . 5 FIXTURESKOHLER/EQUIVALENT
6 . 6 KITCHEN APPLIANCESMODULAR KITCHEN CABINET INCLUDING DRAWER WITH PVC CUTLERY TRAY, CHIMNEY AND HOB (REFRIGERATOR- DOUBLE DOOR, OVEN, MICROWAVE, DISHWASHER, WASHING MACHINE)
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORANTI-SKID VITRIFIED TILES
7 . 2 WALLS & CEILINGOIL BOUND DISTEMPER
7 . 3 TOILETANTI-SKID VITRIFIED TILES
7 . 4 BALCONYUTILITY ROOM/UTILITY TOILET/UTILITY BALCONY
8 . SIT-OUTS
8 . 1 FLOORANTI-SKID VITRIFIED TILES
8 . 2 WALLS & CEILINGACRYLIC EMULSION PAINT
8 . 3 RAILINGSALUMINIUM RAILING WITH 12MM THICK CLEAR TOUGHENED GLASS
8 . 4 FIXTURESALUMINIUM RAILING WITH 12MM THICK CLEAR TOUGHENED GLASS












Sr. No.Document DescriptionDate of Document UploadView Document
1 LC IV 22-08-2025 View Document
2 LOI 22-08-2025 View Document
3 TREATED WATER NOC FOR CONSTRUCTION 22-08-2025 View Document
4 TOD APPROVAL 23-08-2025 View Document
5 WATER NOC 22-08-2025 View Document
6 ZONING PLAN 22-08-2025 View Document
7 FOREST NOC 22-08-2025 View Document
8 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 22-08-2025 View Document
9 CHANGE OF COMPANY NAME 22-08-2025 View Document
10 ARAVALI NOC 22-08-2025 View Document
11 SALEDEED 22-08-2025 View Document
12 ASSURANCE OF SEWERAGE CONNECTION 22-08-2025 View Document
13 HEIGHT NOC 22-08-2025 View Document
14 BOARD RESOLUTION 23-08-2025 View Document
15 BUILDING PLAN APPROVAL BR-III 01-09-2025 View Document
16 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 02-09-2025 View Document
17 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 01-09-2025 View Document
18 MUTATION 06-09-2025 View Document
19 SERVICE PLAN ESTIMATE APPLIED 03-09-2025 View Document
20 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 02-09-2025 View Document
21 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 02-09-2025 View Document
22 EC APPLIED 03-09-2025 View Document
23 FIRE SCHEME APPLIED 03-09-2025 View Document
24 C1 SUPERIMPOSED KHASRA NO 18-11-2025 View Document
25 C13_COMMUNITY & MLCP ELEVATION 18-11-2025 View Document
26 C21_ TOWER-02 ELEVATIONS-A&C 18-11-2025 View Document
27 ASSURANCE STORM WATER 18-11-2025 View Document
28 C14_COMMUNITY & MLCP SECTION 18-11-2025 View Document
29 AFFIDAVIT AUTO CREDIT 10% 18-11-2025 View Document
30 C11_SECOND TO FOURTH LEVEL PODIUM 18-11-2025 View Document
31 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 18-11-2025 View Document
32 C26_TOWERS-03,TYPICAL FLOOR 18-11-2025 View Document
33 C29_TOWERS-03,26TH.(REFUGE)UPPER DUPLEX FLOOR 18-11-2025 View Document
34 C22_TOWER-02 TYPICAL FLOOR 18-11-2025 View Document
35 LENDER DETAILS AND LIST OF SHAREHOLDERS 18-11-2025 View Document
36 AFFIDAVIT 4(2)(L)(D) 18-11-2025 View Document
37 C33_ EWS STILT -GROUND FLOOR 18-11-2025 View Document
38 DD FOR RERA 18-11-2025 View Document
39 DRAFT ALLOTMENT LETTER 18-11-2025 View Document
40 C23_TOWER-02 REFUGE(17TH,34TH43RD) TYPICAL FLOOR 18-11-2025 View Document
41 C37 EWS_SECTIONS-1,1&2,2 18-11-2025 View Document
42 C24_TOWER-02 REFUGE 26TH FLOOR 18-11-2025 View Document
43 CONSENT AND NOC FOR THIRD PARTY RIGHTS 18-11-2025 View Document
44 C32_TOWERS(T-01-T-02 &T-03) TERRACE& MUMTY 18-11-2025 View Document
45 BANK UNDERTAKING 18-11-2025 View Document
46 ELECTRICAL LOAD AVAILABILITY APPLIED 18-11-2025 View Document
47 UNDERTAKING FOR ROAD ACCESS, MINING PERMISSION AND NO LITIGATION 18-11-2025 View Document
48 C31_TOWER-03- SECTIONS-1,1&2,2 18-11-2025 View Document
49 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 18-11-2025 View Document
50 C39_TOWER-1,2,3 & EWS WATER SUPPLY SCHEMATIC DIAGR 18-11-2025 View Document
51 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 18-11-2025 View Document
52 CA CERTIFICATE FOR LAND PREMIUM 18-11-2025 View Document
53 C7_BASEMENT-01 18-11-2025 View Document
54 CA CERTIFICATE OF ESTIMATE COST AND FINANCIAL INVENTORY 18-11-2025 View Document
55 C18_TOWER-01 26 TH.(REFUGE)UPPER DUPLEX FLOOR 18-11-2025 View Document
56 C25_TOWER-02 SECTIONS-1,1&2,2 18-11-2025 View Document
57 C10_FIRST FLOOR LEVEL PODIUM 18-11-2025 View Document
58 C20 _TOWER-01 SECTIONS-1,1&2,2 18-11-2025 View Document
59 C36 EWS_ELEVATIONS A & B 18-11-2025 View Document
60 AKS SAJRA 18-11-2025 View Document
61 C9_GROUND FLOOR PLAN 18-11-2025 View Document
62 C19 TOWER-01 ELEVATIONS -A,B&C 18-11-2025 View Document
63 C30_ TOWER-03 ELEVATION-AC&D A0 18-11-2025 View Document
64 C35_ EWS TYPICAL & 7TH.FLOOR 18-11-2025 View Document
65 DEMARCATION PLAN 18-11-2025 View Document
66 NEC 18-11-2025 View Document
67 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 18-11-2025 View Document
68 NATURAL CONSERVATION ZONE NOC 18-11-2025 View Document
69 C16_TOWER-01 DUPLEX LOWER(16TH,25,33TH&43ND;) FLOOR 18-11-2025 View Document
70 C17_TOWER-01 TYPICAL(REFUGE)17TH,34&43RD;-UPPER DUP 18-11-2025 View Document
71 C34_ EWS TERRACE& MUMTY 18-11-2025 View Document
72 JAMABANDI 18-11-2025 View Document
73 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 18-11-2025 View Document
74 BR FOR BANK OPERATION 18-11-2025 View Document
75 CA CERTIFICATE NET WORTH 18-11-2025 View Document
76 DRAFT CONVEYANCE DEED 18-11-2025 View Document
77 C28_TOWERS-03,TYPICAL (REFUGE) UPPER DUPLEX FLOOR 18-11-2025 View Document
78 DRAFT APP FORM 18-11-2025 View Document
79 DRAFT BBA 18-11-2025 View Document
80 TITLE SEARCH REPORT NEW 18-11-2025 View Document
81 C3 MLU REV APP ZON 18-11-2025 View Document
82 C6_SITE PLAN WITH GREEN AREA CAL 18-11-2025 View Document
83 C15_TOWER-01 TYPICAL FLOOR 18-11-2025 View Document
84 C8_BASEMENT-02 18-11-2025 View Document
85 C12_FIFTH (SERVICE) FLOOR 18-11-2025 View Document
86 C38 EWS_ELEVATIONS C & D 18-11-2025 View Document
87 C27_TOWERS-03,LOWER DUPLEX FLOOR 18-11-2025 View Document
88 AFFIDAVIT FOR NON APPLICABILITY OF NCZ , TREE CUTTING, POWERLINE, FOREST LAND 18-11-2025 View Document