| 17-Nov-2025 |
Ms.
Nikita Mittal, Planning Executive and Sh. Ashish Dubey, Chartered Accountant
briefed about the facts of the project.
Sh.
Abhijit Joshi (AR), Ms. Isha Dang (AR) and Mr. Jatin (AR) are present on the
behalf of the promoter.
The
Authorized Representative of the promoter submits that presently fire scheme
approval has not yet been obtained as on date. The AR of the promoter further
undertakes to obtain and submit the Fire Scheme approval within 4 months from
the date of grant of registration. Further, he undertakes to submit the bank
guarantee/ demand draft amounting to Rs. 25 lakhs, as a security deposit for
timely compliance with the above requirement. It is also expressly undertaken
that in the event of failure to obtain and submit the aforesaid approval within
the stipulated time frame, the said security amount shall be liable to be
forfeited by the Authority.
The
Authority has taken note of the submissions made by the Authorized
Representative of the promoter regarding the non-availability of the aforesaid
statutory approval as on date. In view of the above, and in the interest of
regulatory compliance, the Authority hereby directs that the promoter shall
submit Bank Guarantee/Demand Draft amounting to Rs. 25,00,000/- (Rupees
Twenty-Five Lakhs only), in favour of the Authority, as security amount for
timely submission of Fire scheme approval within 4 months from the date of
grant of registration.
In
the event of non-submission of the above approval within the prescribed time
frame, the corresponding security amount shall stand forfeited by the Authority
and such failure may also attract additional regulatory action as permissible
under the Act of 2016, Rules and Regulations made thereunder.
Approved
as proposed subject to rectification of deficiencies mentioned above.
The
Registration Certificate shall be issued after submission of remaining
deficiencies mentioned above including correction in A-H form, Online DPI and
submission of DD of Rs. 25 lakhs for submission of Fire scheme approval within
the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
| 03-Nov-2025 |
Ar. Neeraj Gautam, Associate Architectural
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Abhijeet Joshi (VP), Sh. Jatin (AR) and
Ms. Isha (AR) are present on behalf of the promoter.
The AR of the promoter states that the
approval of fire scheme is under process and requests 4 months’ time to submit
the same in the Authority. The AR further states that they have deposited BG
no. 0548NDDG00121026 dated 18.10.2025 amounting to RS. 25 lakhs as a token of
assurance to submit fire scheme approval within 4 months. It is also expressly
undertaken that in the event of failure to obtain and submit the aforesaid
approvals within the stipulated time frames, the said security amount(s) shall be liable to
be forfeited by the Authority. The AR requests to grant registration subject to
the submission of fire scheme within 4 months and mining permission before
excavation on site.
The Authority has taken note of the
submissions made by the Authorized Representative of the promoter regarding the
non-availability of the aforesaid statutory approvals as on date. In view of
the submission of Bank Guarantee amounting to Rs. 25,00,000/- (Rupees
Twenty-Five Lakhs only) in lieu of timely submission of fire scheme approval, in favour
of the Authority, the promoter is directed to submit of following approvals:
a. Fire scheme: within 4
months from the date of grant of registration; and
b. Mining permission: before
commencement of excavation on site.
In the event of non-submission of fire
scheme approval within the prescribed time frame, the corresponding security
amount shall stand forfeited by the Authority, and the failure to submit any of
the above approvals/ permissions within the prescribed timeframe may also
attract additional regulatory action as permissible under the Act of 2016,
Rules and Regulations made thereunder.
Approved as proposed subject to
rectification of deficiencies mentioned above at S. No. 33.
The Registration Certificate shall be
issued after submission of rectified payment plan. |