| 11-Feb-2026 |
Ms. Deepika, Planning
Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of
the project.
Sh. Narender Singh (AR), Sh. Anshul (AR) & Sh.
Amit (AR) is present on behalf of the
promoter.
The Authorized Representative of the promoter submits
that presently Fire Scheme Approval and Mining Permission are under process and
the said approvals have not yet been obtained as on date. Further, the AR of
the promoter undertakes to obtain and submit:
i.
The
Fire Scheme Approval within 3 months from the date of grant of registration;
and
ii.
Mining
permission before the start of construction.
Further, he undertakes to submit Demand Draft / Bank Guarantee amounting
to Rs. 25 lakhs, as a security deposit for timely compliance with the above
requirements at point (i). It is also expressly undertaken that in the event of
failure to obtain and submit the aforesaid approvals within the stipulated time
frame; the said security amount shall be liable to be forfeited by the
Authority.
The Authority has taken note
of the submissions made by the Authorized Representative of the promoter
regarding the non-availability of the aforesaid statutory approvals as on date.
In view of the above, and in the interest of regulatory compliance, the Authority
hereby directs that the promoter shall submit Demand Draft /Bank Guarantee,
amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only) in favour of the
Authority, as security amount for timely submission of the Fire Scheme Approval within 3 months from
the date of grant of registration.
In the event of
non-submission of the above approval within the prescribed time frame, the
corresponding security amount shall stand forfeited by the Authority, and such
failure may also attract additional regulatory action as permissible under the
Act of 2016, rules and regulations made thereunder.
Approved as proposed subject to rectification of
deficiencies mentioned above.
The Registration Certificate shall be issued after
deposition of above DD/BG and rectification of other deficiencies as listed
above at S. No. 34. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
| 02-Feb-2026 |
The matter was adjourned and fixed for 16.02.2026. |
ADJOURNMENT |
View Order |
| 12-Jan-2026 |
The matter was adjourned and fixed for 02.02.2026. |
ADJOURNMENT |
View Order |
| 29-Dec-2025 |
The
matter was adjourned and fixed for 12.01.2026. |
ADJOURNMENT |
View Order |
| 22-Dec-2025 |
Ms. Deepika, Planning
Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of
the project.
Sh. Narendra Singh (AR), Sh.
Rajiv Dubey (AR) & Sh. Anshul Vijay (AR) are present on behalf of the promoter and stated that no renewal of License
No. 55 of 2019 is required for the project, as the entire development work was
completed within the validity period from 08.03.2019 to 07.03.2024 under the
DDJAY policy. They further stated that the development works were completed
well before the prescribed 7-year period, and the Completion Certificate was
obtained on 18.07.2022 in accordance with Rule 12 of the Haryana Development
and Regulation of Urban Areas Rules, 1976. Renewal under Rule 13 applies only
in cases of delay or incomplete development, which does not apply here.
Accordingly,
the matter is to be examined legally by the legal team of HARERA, Gurugram and
reported back in the next meeting.
The
matter to come up on 29.12.2025. |
ADJOURNMENT |
View Order |
| 15-Dec-2025 |
Ms. Deepika, Planning Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the project.
Sh. Amit (AR), Sh.
Narendra Singh (AR) & Sh. Rajiv Dubey (AR) are present on behalf of the promoter and stated that the EKAM project
(DDJAY), Sector-5 Sohna, measuring 15 acres, already stands registered with
RERA vide Registration Certificate No. 38 of 2019 dated 08.07.2019 and has been
issued the Completion Certificate in 2022 vide Memo No. LC-3712B+3723-JE(MK)-2022/20756
dated 18.07.2022. The 0.599-acre commercial component forms part of the same
15-acre licensed area and is already covered in the issued CC. As per DTCP
guidelines, once the Completion Certificate is granted, no license renewal is
required, and the building plans have also been duly approved on this basis.
Further, the Authority observes that the BR-III approved by DTCP vide
Memo No. 3279 dated 25.06.2025 for Distinct Commercial Component of DDJAY
Plotted Colony which includes the condition that the BR-III is valid subject to
the validity of the license. Accordingly, the promoter is directed to submit
any policy/clarification from DTCP exempting license renewal within a week.
The
matter is adjourned and listed for 22.12.2025. |
ADJOURNMENT |
View Order |
| 01-Dec-2025 |
The
matter was adjourned and fixed for 15.12.2025. |
EXAMINATION BY AUTHORITY |
View Order |