23-Jun-2025 |
Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the case.
Sh. Rahul Sharma (AR) is present on behalf of the promoter.
Meanwhile, the project site was visited by the concerned PE and it is
observed that the site has approach from service road of Dwarka Expressway.
The promoter has submitted three
DD vide no. 588857, 588858 and 588859 dated 06.06.2025 amounting to Rs 25 lakhs
each as a security amount for submission of Approved Environment Clearance,
Fire Scheme approval, Approved Service plan and Estimates within 4 months from
the grant of registration.
Approved as proposed subject to rectification of deficiencies mentioned
above.
The promoter shall submit the Approved Environment Clearance, Fire Scheme
approval and Approved Service Plans and Estimates within a period of four
months from the date of grant of registration certificate and Mining permission
before start of excavation work.
The Registration Certificate shall be issued after submission of
remaining deficiencies mentioned above including correction in A-H form, Online
DPI. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |