07-Jul-2025 |
Proceedings dated 07.07.2025.
Sh.
Shashank Sharma, Associate
Engineer Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the
facts of the case.
Sh. Ajit Arora (Director) and
Sh. Ajit Kumar (AR) are present on behalf of promoter.
The site of the project was
visited physically on 04.06.2025 by the concerned Associate Engineer Executive along
with Chartered Accountant and it has been noted that the project namely “Avani
Signature Floors” is a part of the project namely “Anand Niketan” which is registered
with the Authority vide RC no. 105 of 2023 dated 04.12.2023 and connected to
the Mohammadpur-Sohna road. The 11KV HT line passing along the side of existing
Mohammadpur-Sohna road has been shifted/removed/underground at the site and the
same has been acknowledged in the DTP report dated 19.09.2023 also. The services
such as water supply, sewer line, electrical and storm line are being carried
out at the site.
Approved as proposed. The RC
shall be issued after submission of corrections in form A-H and DPI. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
23-Jun-2025 |
The matter has been adjourned to 07.07.2025 |
ADJOURNMENT |
View Order |
09-Jun-2025 |
Proceedings
dated 09.06.2025.
Sh.
Shashank Sharma, Associate
Engineer Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the
facts of the case.
Sh. Ajit Arora (Director) and
Sh. Ajit Kumar (AR) are present on behalf of promoter and states that reply to
the deficiencies will be submitted.
The Authority observes that,
promoter i.e., M/s N.S Buildtech Pvt. Ltd. has applied for Independent residential floors on the 35 plots through unregistered MOU/agreement.
The promoter shall register the collaboration agreement for the same. Further,
promoter is directed to submit the remaining deficiencies along with the
building plan approval from the competent authority for all the floors applied
for registration.
The matter to come up on 23.06.2025. |
ADJOURNMENT |
View Order |
02-Jun-2025 |
The matter has been adjourned to 09.06.2025 |
EXAMINATION BY AUTHORITY |
View Order |