30-Jun-2025 |
Ms. Nikita Mittal, Planning Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the case.
Sh. Vikas Jain
(AR) and Sh. Chirag Nagpal (AR) are present on behalf of the promoter.
Approved as
proposed subject to rectification of remaining deficiencies.
The registration
certificate shall be issued after corrections in A to H and DPI. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
23-Jun-2025 |
Ms.
Nikita Mittal, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts
of the case.
Sh. Vikas Jain (AR), Sh.
Chirag Nagpal (AR) and Ms. Kavia Anand (AR) are present on behalf of the
promoter. Sh. Pranav Verma (Adv.), Sh. Yajur Bhola (Adv.), Sh. Apoorv Anmol and
Sh. Paritosh Agarwal are present on behalf of the complainants.
Public notices dated
21.05.2025 and 23.05.2025 were issued with
respect to the application of the promoter for registration of project wherein
objections had been received in the Authority dated 30.05.2025 & 02.06.2025
and the copy of the same were supplied to the promoter. The promoter had
submitted the reply to the objections dated 04.06.2025. The objections and
reply were discussed/heard in the Authority meeting and Authority during
hearing dated 02.06.2025 reserved the same for orders. Accordingly, the
Authority has passed the orders separately. The copy of same be supplied to all
the concerned.
In respect of the
application under section 4, the promoter is directed to submit the remaining
deficiencies along with corrections in DPI and A to H.
The matter to come up on
30.06.2025. |
ADJOURNMENT |
View Order |
16-Jun-2025 |
|
ADJOURNMENT |
View Order |
02-Jun-2025 |
Sh. Vikas Jain (Director),
Sh. Parveen Jain (CMD), Sh. Chirag Nagpal (AR) and Ms. Kavia Anand (AR) are present
on behalf of the promoter.
Sh. Garv Malhotra (Adv.)
and Sh. Yajur Bhola (Adv.) are present on behalf of the complainants.
Sh. Bharat Shawen
(Resident), Sh. Pulkit Gupta (Resident) and Sh. Kunal Sethi (Resident) are
present.
Objections on the behalf
of allottees were received against the public notice inviting objections in the
Authority for which copy of the same to be supplied to the promoter, who may submit
the reply against a complaint received from the allottees within a period of
one week. Meanwhile, the site of the project was visited by the concerned executive
and status of connectivity of the project site with the service road of 60 mtr
wide road is confirmed by the concerned executive along with the construction
of two towers (Block 9 and 10) has been started on the site.
In view of the above,
detailed order shall follow.
The
matter to come up on 16.06.2025. |
ADJOURNMENT |
View Order |
19-May-2025 |
Ms.
Nikita Mittal, Planning Executive 0briefed about the facts of the case.
Sh. Vikas Jain (AR), Sh.
Chirag Nagpal (AR) and Ms. Kavia Anand (AR) are present on behalf of the
promoter.
Sh. Ram Niwas S/o Sh. Roshan Lal (Landowner), Sh. Sumit
(Landowner), Sh. Amit (Landowner), Sh. Deepak (Landowner) are present.
A public notice to be
published in three prominent newspapers, one Hindi and two English newspapers
for two weeks w.r.t. revision in the site plan for inviting objections if any
along with submission of 2/3rd consent of the allottees submitted regarding
revision in building plans.
The
matter to come up on 02.06.2025. |
EXAMINATION BY AUTHORITY |
--- |