19-May-2025 |
Proceedings dated: 19.05.2025.
Sh. Shashank Sharma,
Associate Engineer Executive briefed about the facts of the case.
Sh. Ayush Singla (AR), Ms.
Suman Kaushik are present on behalf of promoter and states that EC, Fire Scheme
approval and service plans and estimates have been applied to the concerned
authorities and the same shall be obtained. Further, the project is well
connected to the 12m service road, so road access permission is not required.
Approved
as proposed subject to submission of the requisite BG’s/DD of Rs. 25 lakh each
as a security amount for the submission of EC, approved fire scheme and
approved SPE within four months failing
which, the same shall be forfeited. Mining permission shall be obtained before start of excavation at
site.
The RC shall be issued after
submission of remaining documents including the correction in form A-H and DPI
along with the DD/BG’s as above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |