HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1923-2025
Submission Date : 23-04-2025 03:00:03 PM
Applicant Type : Company
Project Type: NEW




SUBH HOUSING (GURGAON) LLP
BANNI THE ADDRESS, 402,4TH FLOOR NO. 1, GOLF COURSE ROAD, SECTOR 56 GURGAON- 122011
1244087579
9999300814 (Number Shared by Promoter in Public)
subhhousing@gmail.com
https://subhhousing.com
XXXX321B
ACD1875
 
 


 
 


 
 


 
 







SEGGOVIAS
SECTOR 70A
BADSHAHPUR ST
GURUGRAM
1244087579
9999300814 (Number Shared by Promoter in Public)
subhhousing@gmail.com
HARISH KUMAR
1244087579
9999300814 (Number Shared by Promoter in Public)
subhhousing@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150265121-04-2025512000ICICI BANKHRERA Gurugram







1.57875 (Acre)
2.37
2.368
1.57875 (Acre)
02 OF 2025 DATED 08.01.2025, Memo no Endst No. LC/5272/JE(RK)/2025/906
Yes







12300.28 Lakhs
544.18 Lakhs
8700 Lakhs
209.97 Lakhs
2846.13 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0.43482
3CONSTRUCTION OF ROADS 0.63061
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0.42388
6GREEN BELTS 0
7VEHICLE PARKINGS 0.04064
8ELECTRICITY SUB-STATION 0.00831
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
Total1.53826




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSALREADY CONNECTEDYes
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS5.00AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM23.00AS PER PROJECT REPORT
3STORM WATER DRAINAGE18.41AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM25.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL25.00AS PER PROJECT REPORT
6STREET LIGHTING6.06AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING25.00AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS10.50AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM15.00AS PER PROJECT REPORT
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15ELECTRIFICATION COST5.00AS PER PROJECT REPORT
16RAIN WATER HARVESTING12.00AS PER PROJECT REPORT
17UNDERGROUND WATER TANK14.00AS PER PROJECT REPORT
18STP25.00AS PER PROJECT REPORT
19PARKING1.00AS PER PROJECT REPORT


NA (date)
23-04-2025 (date)
01-01-2026
30-06-2032
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings94.25641
Apartment/Shops/Other Buildings94.2521
Apartment/Shops/Other Buildings94.2521
Apartment/Shops/Other Buildings94.25321
Apartment/Shops/Other Buildings94.2521
Apartment/Shops/Other Buildings94.84201
Apartment/Shops/Other Buildings94.8421
Apartment/Shops/Other Buildings33.4321





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments65.0965.09104.15156.22
Shops0.160.160.250.38
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments195.27195.27260.36364.51
Shops0.480.480.640.89
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments104.15104.15173.58295.08
Shops0.250.250.420.72
Plots0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments295.08295.08295.08512.05
Shops0.720.720.721.25
Plots0000

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments581.48581.48581.48616.19
Shops1.421.421.421.51
Plots0000

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments616.19668.27668.27885.24
Shops1.511.631.632.16
Plots0000

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0.500.500.500.50
Water Supply System2.302.302.302.30
Sewerage treatment & garbage disposal2.502.502.502.50
Electricity Supply System0000
Storm Water Drainage1.841.841.841.84
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Underground Water Tank1.401.401.401.40
Rain Water Harvesting1.201.201.201.20

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0.500.501.001.00
Water Supply System2.302.304.604.60
Sewerage treatment & garbage disposal2.502.505.005.00
Electricity Supply System6.256.256.256.25
Storm Water Drainage1.841.843.863.86
Parks and Playgrounds2.632.632.632.63
Clubhouse/community centres0000
Shopping area0000
Other0000
Street lighting1.51.501.51.5
Security and Fire Fighting6.256.256.256.25
Renewable Energy Charges3.75
Paking Open0.250.25
STP6.256.256.256.25
Underground Water Tank1.401.402.802.80
Rain Water Harvesting1.201.202.402.40
Electrification Cost1.251.251.251.25
Renewable Energy System3.753.75
Parking open0.25
Parking Open0.25
Renewable3.75












Yes
Yes
ICICI BANK LTD & ADDRESS - UNIT NO 8 9 GF BAANI THE ADDRESS ONE SECTOR 56 GURGAON
777705547932
ICIC0007328
110229343
007328
1. Sarita Singla R/o- CTA 091, The Crest Park Drive, Sector 54, DLF Phase 5, Sector 54, Gurgaon, Haryana 122011 2. Abhishek Singla R/o- A Block 091, The Crest DLF, Phase 5, Sikanderpur Ghosi(86), Gurgaon, Haryana 122002 3. Ayush Singla R/o- Tower A 91, The Crest Park Drive Road, Sector 54, DLF Phase 5, Sikenderpur Ghosi(68), Gurgaon, Haryana 122002
YES











No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSEALREADY BEEN OBTAINED08-01-2025
II. ASSURANCE FOR WATER SUPPLYALREADY BEEN OBTAINED10-01-2025
III. ASSURANCE FOR STORM WATER ALREADY BEEN OBTAINED17-01-2025
IV. ASSURANCE FOR SEWERAGE CONNECTIONALREADY BEEN OBTAINED17-01-2025
V. HUDA CONSTRUCTION WATERALREADY BEEN OBTAINED17-01-2025
VI. ELECTRICAL LOADALREADY BEEN OBTAINED30-01-2025
VII. AIRPORT HEIGHT CLEARANCEALREADY BEEN OBTAINED25-10-2024
VIII. FOREST NOCALREADY BEEN OBTAINED16-08-2024
IX. BUILDING PLAN APPROVAL (BR-III)ALREADY BEEN OBTAINED23-04-2025
X. ENVIRONMENT CLEARANCE APPROVALAPPLIED FOR BUT YET TO RECEIVE21-01-2025
XI. SERVICE PLANS AND ESTIMATES APPROVALYET TO FILE FOR APPROVALNA
XII. FIRE SCHEME APPROVALYET TO FILE FOR APPROVALNA








Yes


Yes


As per Norms













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILE, WOODEN FLOORING LAMINATED, KOTA STONE FLOORING , EPOXY PAINT FLOORING
2WALL FINISHING DETAILSVITRIFIED TILE
3KITCHEN DETAILSVITRIFIED TILE, FULL HEIGHT WINDOWS- ALUMINIUM POWDER COATED SECTIONS
4BATHROOM FITTINGSVITRIFIED TILE
5WOOD WORK ETCNO
6DOORS AND WINDOS FRAMES 1 HR FIRE RATED DOOR WITH VENEER FINISH, WOODEN FRAME WITH FLUSH DOOR WITH LAMINATE FINISH (ON BOTH SIDES)
7GLASS WORKFULL HEIGHT WINDOWS- ALUMINIUM POWDER COATED SECTIONS
8ELECTRIC FITTINGSHEAVY DUTY, SWITCHES SOCKET-MODULAR, LED, VARIABLE RATE FLOW SYSTEM.
9CONDUCTING AND WIRING DETAILSHEAVY DUTY, MODULER
10CUPBOARD DETAILSNA
11WATER STORAGEYES
12LIFT DETAILS4 FLATS PER FLOOR, 3 LIFTS PER FLOOR
13EXTERNAL GLAZINGSFULL HEIGHT WINDOWS- ALUMINIUM POWDER COATED SECTIONS
13.1WINDOWS/GLAZINGSFULL HEIGHT WINDOWS- ALUMINIUM POWDER COATED SECTIONS
14DOORS 1 HR FIRE RATED DOOR WITH VENEER FINISH, WOODEN FRAME WITH FLUSH DOOR WITH LAMINATE FINISH (ON BOTH SIDES)
14.1MAIN DOORS 1 HR FIRE RATED DOOR WITH VENEER FINISH
14.2INTERNAL DOORSWOODEN FRAME WITH FLUSH DOOR WITH LAMINATE FINISH (ON BOTH SIDES)
15AIR CONDITIONINGVARIABLE RATE FLOW SYSTEM.
16ELECTRICAL FITTINGSHEAVY DUTY CONDUTING MODULAR SWITCHES, C CURVE MCB
17CNG PIPE LINEYES
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEEXTRANL GRADE TEXTURE PAINT
20INTERNAL FINISHINGPREMIUM ACRYLIC EMULSION
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILE
1 . 2 WALLSPREMIUM ACRYLIC EMULSION
1 . 3 CEILINGPREMIUM ACRYLIC EMULSION
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATE WOODEN FLOORING /VITRIFIED TILE
2 . 2 WALLSPREMIUM ACRYLIC EMULSION
2 . 3 CEILINGPREMIUM ACRYLIC EMULSION
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORVITRIFIED / CERAMIC TILES
3 . 2 WALLSVITRIFIED / CERAMIC TILES
3 . 3 CEILINGPREMIUM ACRYLIC DISTEMPER
3 . 4 COUNTERSSINGLE LEVER COUNTER TOP
3 . 5 SANITARY WARE/CP FITTINGSCHINAWARE
3 . 6 FITTING/FIXTURESTOWEL RAIL, SOAP DISH, ETC
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSPREMIUM ACRYLIC EMULSION
4 . 3 CEILINGPREMIUM ACRYLIC EMULSION
4 . 4 WARDROBESNO
5 . TOILET
5 . 1 FLOORVITRIFIED / CERAMIC TILE
5 . 2 WALLSPREMIUM ACRYLIC DISTEMPER EMULSION
5 . 3 CEILINGPREMIUM ACRYLIC DISTEMPER EMULSION
5 . 4 COUNTERSSINGLE LEVER COUNTER TOP
5 . 5 SANITARY WARE/CP FITTINGSSINGLE LEVER COUNTER TOP
5 . 6 FIXTURESTOWEL RAIL, SOAP DISH, ETC
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILE
6 . 2 WALLSPREMIUM ACRYLIC EMULSION
6 . 3 CEILINGPREMIUM ACRYLIC EMULSION
6 . 4 COUNTERSSINGLE LEVER COUNTER TOP
6 . 5 FIXTURESCHINAWARE
6 . 6 KITCHEN APPLIANCESSINK, WASH BASIN, TAPS
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORVITRIFIED TILE
7 . 2 WALLS & CEILINGOBD
7 . 3 TOILETVITRIFIED / CERAMIC TILE, PREMIUM ACRYLIC DISTEMPER EMULSION,
7 . 4 BALCONYANTI STICK TILES AND RAILING
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1ASSUANCE FOR STORM WATER21-04-2025 View Document
2NEC15-04-2025 View Document
3LOI15-04-2025 View Document
4DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD15-04-2025 View Document
5LC-IV15-04-2025 View Document
6AKS-SHJRA15-04-2025 View Document
7ELECTRICAL LOAD21-04-2025 View Document
8COPY OF LICENSE ALONG WITH SCHEDULE OF LAND15-04-2025 View Document
9ZONING PLAN15-04-2025 View Document
10MUTATION15-04-2025 View Document
11HUDA CONSTRUCTION21-04-2025 View Document
12JAMABANDI15-04-2025 View Document
13INFORMATION OF REVENUE DEPARTMENT19-04-2025 View Document
14AAI NOC21-04-2025 View Document
15FOREST NOC21-04-2025 View Document
16ASSURANCE FOR WATER SUPPLY21-04-2025 View Document
17ASSURANCE FOR SEWERAGE CONNECTION21-04-2025 View Document
18BANK UNDERTAKING21-04-2025 View Document
19SALE DEED21-04-2025 View Document
20DEMARCATION PLAN21-04-2025 View Document
21SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN21-04-2025 View Document
22IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN21-04-2025 View Document
23ENVIORNMENT CLEARENCE21-04-2025 View Document
24AFFIDAVIT 4(2)(L)(D)23-04-2025 View Document
25LANDSCAPE PLAN23-04-2025 View Document
26CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT23-04-2025 View Document
27IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN23-04-2025 View Document
28A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS23-04-2025 View Document
29NCZ UNDERTAKING23-04-2025 View Document
30DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.23-04-2025 View Document
31CASH FLOW STATEMENT OF THE PROPOSED PROJECT23-04-2025 View Document
32NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT23-04-2025 View Document
33ANNUAL 2023-2423-04-2025 View Document