| 21-Apr-2025 |
Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the case.
Sh. Siddharth Gandhi (AR) and Sh. Anish Dham (AR) are present on behalf
of the promoter.
The AR of the promoter stated that they have applied for the amendment of
the registration certificate due to revision in the building plans alongwith
the consent of more than two-third existing allottees and requested the
Authority to grant the amendment certificate of the registration.
Further, it is noticed that the contact details of all the allottees has
not been submitted. The Authority directed the promoter to submit the contact
details of random 100 allottees for the purpose of verification of consents by
the office.
Approved as proposed subject to rectification of deficiencies mentioned
above including correction in A-H form and Online DPI.
The addendum Certificate shall be issued after submission of remaining
deficiencies mentioned above including correction in A-H form, Online DPI and
verification of consents. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |