Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
AIPL Joy Gallery Sector 66 GURUGRAM Advance India Projects Limited
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-1872-2025 28-Jan-2025 28-Jan-2025 EXTENSION APPROVED NOT REQUIRED Yes 19-Feb-2025 Online and by hand Deficiency notice
First hearing
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
23-Jun-2025 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Ms. Julie Jha (AR), Sh. Vijay Singh (AR) and Sh. Sonam Sharma (AR) are present on behalf of the promoter. An objection was received in the Authority against the public notice issued for extension of registration of project stating that a unit was booked from AIPL and on non-completion of project on time a complaint was filed with Authority wherein Authority ordered to refund the amount with interest but after lapse of time AIPL did not comply with orders of the Authority. Further stating that extension has been sought on frivolous grounds and consequences of granting extension will be further harassment & loss to allottees. In view of the above submission, allottee/objector prays to reject the application for extension and direct the builder to comply with orders. Further if extension is granted, then it should be conditional that AIPL shall pay interest to allottees on sum collected for entire period of extension and initiate penal proceedings under section 63and/or 64 for non-compliance with Authority judgement & non-performance of project obligations. The promoter has submitted the reply to the above objection stating that the objector is an investor and desired to invest in the project AIPL Joy Square which is separate project of the promoter than the one AIPL Joy Gallery in which objection has been filed. A BBA was signed for allotted unit in project AIPL Joy Square but due to breach of terms and conditions, Allotment was cancelled on 12.08.2022. Further complaint was filed and same is decided on 20.11.2024 by the Authority. In view of the same promoter states that as neither the objector is allottee nor having any right or interest in the project AIPL Joy Gallery, hence the present objection should be dismissed. Further, the grievance of the objector has already been addressed vide judgement dated 20.11.2024. After perusal of the objection and reply of the promoter, the Authority hereby dismisses the objection as the same does not relate to the project applied for extension of registration and also the grievances of the objector are already addressed and Authority passed a separate order dated 20.11.2024 which is to be complied by the promoter. The promoter has obtained the part occupation certificate dated 09.05.2024 for the project and further construction is going on in the project. The site of project has been inspected on 19.06.2025 by concerned Engineering Officer & Chartered Accountant and it has been reported that the project site is located on 12 mt wide service road adjacent to 90 mt SPR. Service Road is not fully developed, however, the promoter has developed the part area of the road falling in their share and directly connected to 90 mt SPR. Further part OC has been granted and balance works are being carried out at the site. Some shops have also been made operation in the project. It is noted that the promoter has made changes in the approved plans of the project, increasing the number of units in the project, submitted at the time of registration of the project. Part changes in the approved plan have been compounded by DTCP, Haryana at the time of grant of part OC dated 09.05.2024 for the project and the balance changes are yet to be compounded by DTCP, Haryana. Since the above application is for extension of registration of the project already registered and hence extension of one year under section 6 of the Act of 2016 is allowed as per the details of the project already submitted at the time of registration. Further, this extension of registration is without prejudice to the rights of the existing allottees under the Act of 2016. Further, the promoter is also directed to apply for revision in the registration of the project once the all changes in the building plans are compounded by the DTCP, Haryana along with consent os more than 2/3rd existing allottees. A condition to this effect shall also be incorporated in the extension certificate. The extension of registration certificate shall be issued after submission of pending deficiencies mentioned at remarks. EXTENSION APPROVED View Order
09-Jun-2025 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Ms. Julie Jha (AR), Sh. Vijay Singh (AR) and Sh. Sonam Sharma (AR) are present on behalf of the promoter. Sh. Ashwani Kumar (Advocate) on behalf of the Shailendra Kumar Sinha objectioner to the public notice dated 27.05.2025. A objection has been received in the Authority against the public notice issued for extension of registration of project and the copy of same is handed over to the promoter for submission of reply to the same. The concerned official is directed to verify the consents submitted by the promoter on random basis. Meanwhile, the site of the project be also got inspected regarding the development works. The matter to come up on 23.06.2025. ADJOURNMENT View Order
19-May-2025 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Ms. Julie Jha (AR) and Sh. Vijay Singh (AR) are present on behalf of the promoter. The AR of the promoter states that they have hold the revision in building plans and applied for revalidation of existing building plans along with applicable revalidation fee. It is noted that as per registration certificate based on earlier building plans there were 401 units in the project and the promoter has sold out the 439 units with 110 units still unit, thereby making total 549 units in the project. This states that the promoter has sold the excess units which were not approved by the competent authorities. In view of the above, the promoter is directed to explain the fact as to how the excess units have been sold out in the project. Further, the promoter is also show caused as to why penal proceedings under Section 59(1) of the Act of 2016 should not be initiated against the promoter for violation of Section 3 of the Act Ibid. The promoter has also submitted the consent of 2/3rd existing allottees in the project but all the consents are undated. A prominent public notice of 14 days for inviting objections if any in three newspapers (One Hindi and Two English) be published regarding the extension of registration of the project under Section 6 of the Act, 2016 for one year and the consent of 2/3rd existing allottees submitted prior to revision in building plans. Meanwhile, the promoter to submit the deficit documents along with above clarifications. The matter to come up on 09.06.2025. ADJOURNMENT View Order
21-Apr-2025 The matter is adjourned and to come up on 19.05.2025.  ADJOURNMENT View Order
10-Mar-2025 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Ms. Julie Jha (AR) and Sh. Vijay Singh (AR) are present on behalf of the promoter. The AR of the promoter states that they had obtained the part occupation certificate on 09.05.2024 for the project (Ground floor to 3rd floor) after paying the composition fees on account of violations made viz-a-viz approved building plans and obtained the as built plans for that area. Further, the promoter had also applied for revision in building plan in lieu of TDR certificate and the same is expected shortly. The promoter is directed to submit the as built plans in respect of occupation certificate and also to submit consent of 2/3rd existing allottees before revision in building plans as per section 14(2) of Act, 2016 along with rectification of all other remaining deficiencies. The matter to come up on 21.04.2025 ADJOURNMENT View Order
24-Feb-2025 The matter is adjourned and to come up on 10.03.2025. EXAMINATION BY AUTHORITY View Order