05-Feb-2025 |
Sh.
Shashank Sharma, Associate Engineer Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the case.
Sh.
Raj Kaushik (Authorized Signatory), Ms. Vaishali Garg (Authorized Signatory)
are present on behalf of the promoter and states that site is accessible from
the existing service road as well as 24 mtr. road and same has been applied to
GMDA on 08.01.2025. Further the approval of EC is in final stage.
Approved
as proposed subject to submission of BG/DD of Rs. 25 lakhs in lieu of EC
approval within four months and mining permission
shall be obtained before start of excavation at site. The AR states that the
site is accessible from the existing service road as well as 24 mtr. road and
has applied to GMDA for requisite permission. A condition be incorporated for
submission of road access permission within two months from GMDA failing which
the RC is liable to be suspended. Further the floors on plots Sr. No. 1 to 17
shall remain frozen till the same are released by DTCP and no sale or booking
in respect of frozen plots/floors shall be undertaken.
The
RC shall be issued after submission of remaining deficiencies along with the
BG/DD as per above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |