04-Nov-2024 |
Ar. Neeraj Gautam,
Associate Architectural Executive and Sh. Ashish Dubey, Chartered Accountant
briefed about the facts of the project.
Sh. Ashok Singh Jaunapuria (AR), Sh. Manoj
Shukla (AR) and Sh. Sunil Shekhawat (AR) are present on behalf of the promoter
and clarify that the collaborator landowner share is only 3500 sq. ft. which
shall be sold only after obtaining OC and an undertaking to this effect shall
be submitted. Further after technical approval of service plans and estimates,
the requisite BG of Rs. 196 lakhs has been submitted to DTCP for issuance of
approval service plans and estimates. Further SEIAA vide proceedings dated
28.10.2024 has already approved the grant of environmental clearance to the project
with gold rating and final approval shall be issued within three months and a
condition to this effect shall be incorporated in the RC. The revised bank
undertaking shall be submitted today along with corrections in form REP-I (A to
H) and DPI.
Approved as proposed subject to corrections in
form REP I, DPI and other deficiencies. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |